The pressure surge at the moment of blasting seriously threatens the safety of pipeline structures and other buildings. This article established two numerical simulation models of the hydraulic transition process and water–air two-phase flow based on the one-dimensional transient flow theory and considering the actual flow characteristics of water and air. The hydraulic characteristics and blasting parameters of the blasting system were studied under two different conditions of the tunnel with and without the pressure flow. The observed parameters of an actual blasting engineering prototype verified the accuracy of the mathematical model. The maximum pressure of pressure blasting was 2.55 times as high as hydrostatic pressure. The maximum pressure of non-pressure blasting was 1.77 times as high as hydrostatic pressure. Pressure blasting impact was 2.17 times greater than nonpressure blasting. Discrepancies between actual and simulated data for gushing and overflow heights ranged from 9 to 14%. The model can provide a reference for blasting engineering on the simulation calculation of hydraulic characteristics such as impact pressure, overflow time, and overflow of the underwater rock plug blasting system.

  • The simulation model of the hydraulic transient process in underwater rock plug blasting engineering was established by method of characteristics and water–air two-phase flow equation, respectively.

  • The observed parameters of an actual blasting prototype verified the accuracy of the mathematical model.

  • The blasting should be carried out in the nonfull flow in the tunnel when the impact pressure could meet the pressure standard of the system.

Rock plug blasting is a controlled blasting under the water. The tunnel inlet is built on the reservoir or slope protection. After the completion of the tunnel construction, the rock plug blasting enables an unobstructed connection between the reservoir and the tunnel. Rock plug blasting technology has been widely used for saving investment, shortening the construction period, and its relatively mature construction technology (Ding 1998; Sharafat et al. 2019). Researchers have done much research on blasting monitoring technology, blasting method, blasting device, blasting technology, and explosive dosage, thus accumulating rich experience in underwater rock block blasting technology (Zhao et al. 2016; Choudhary & Agrawal 2022; Li et al. 2022). Many underground caverns were also excavated by blasting (Van Kien et al. 2022). A new blasting method was proposed to prevent premature emission of explosive gas, reduce unit consumption of explosives, and improve the utilization rate (Yang et al. 2018). The Fluent–EDEM coupling algorithm simulated the block motion (Wu et al. 2023). To comprehensively consider the deformation and failure mechanism caused by the strain rate effect and energy flow, a Johnson-Holmquist-Rock (JHR) constitutive model was proposed to simulate the failure process of rock under a blasting load (Xie et al. 2019). Hu et al. (2016) revealed that the numerical simulation and penetration test of rock plug blasting confirmed each other. Also, the difference in the actual blasting depth increased significantly with the increase in the drilling depth.

For the hydraulic characteristics of underwater rock plug blasting, the primary performance of the rock plug blasting in blasting dynamics was shown as a peak in an instant on the inlet system produced by shock wave blasting. The pressure of the building, such as the water conveyance tunnel and the gate shaft in the system, would rise rapidly after a few seconds when blasting occurred (Wu et al. 2023; Xie et al. 2019). Too much pressure could cause dangerous accidents in each building of the water supply system (Qasim et al. 2022). The water hammer pressure in the water supply system was mainly caused by the sudden opening and closing of the valve in the water supply or the impact of pressurized water on the retained air mass during the flushing process of the tunnel (Aminoroayaie Yamini et al. 2021; Wang et al. 2022; Zhang et al. 2022). For a closed pipe containing an air pocket in the end or air released in an exhaust hole, the air pocket impacted by pressurized water with a valve opening would produce several times direct water hammer pressure (Zhou et al. 2011). The transient theory and models have been applied with substantial progress and achievement for traditional elastic pipes, such as one-dimensional (1D) and two-dimensional (2D) water hammer models and unsteady friction or turbulence models (Duan et al. 2018, 2020). Computational fluid dynamics techniques were now routinely employed for unsteady hydraulic engineering problems (Kyriakopoulos et al. 2022). It has been widely used for studying two-phase pressurized flows such as the free surface-pressurized flow (Cong et al. 2017; He et al. 2022), transient cavitating flow (Zhou et al. 2018), transient flows with entrapped air pockets (Huang & Zhu 2021; Zhai et al. 2021), and geyser formation in vertical shafts (Chang & Wei 2022; Liu et al. 2022).

After the rock plug blasting, the air and water are the two-phase unsteady flow. The transition process of water and gas is highly complex, which causes the difficulty in setting up a mature theory. Most blasting projects obtained the blasting effect and impact pressure through onsite blasting prototype observation and the hydraulic model test. However, a few studies did numerical simulation calculations on the transition process after underwater rock plug blasting. Numerical simulation has the advantages of fast computation and saving test costs and time. The pressure generated at the rock plug blasting may cause harm to the pipeline system and related buildings. It is necessary to calculate the hydraulic dynamic characteristics of the water flow in the pipeline to ensure the safe and stable operation of the whole water conveyance system and downstream buildings after rock plug blasting. Chen et al. introduced the principle and application of air cushion underwater rock plug blasting technology, put forward the numerical simulation model of the hydraulic transition process of air cushion underwater rock plug blasting, and discussed the sensitivity analysis of blasting parameters on hydraulic characteristics (Chen et al. 2022). Zhang et al. (2020) established a 1D mathematical model of the underwater rock plug blasting system using the method of characteristics (MOC) based on the transient flow theory. The changes in water hammer pressure and flow were studied, generated by the system after blasting when the end of the tunnel was blocked and full of flow and pressure. The results showed that the negative pressure along the system is severe after blasting. It was necessary to increase the area of the ventilation shaft for water hammer protection. A reasonable diameter of the ventilation shaft (D = 10.0 m) was proposed to ensure the safe operation of the system after blasting. This article only studied the blasting condition of the tunnel with full pressure flow. The pressure safety should be met at all locations in the system, which caused the diameter of the ventilation shaft to be expanded to 10 m, which was too high in construction cost. Whether the safety structure of the foundation meets the requirements needs further discussion.

Therefore, based on previous studies and saving engineering costs, a method of blasting under nonfull flow conditions without pressure was put forward. Based on 1D transient flow theory and considering the mechanical characteristics of water and air, a mathematical model of a water–air two-phase flow in the rock plug blasting system was proposed in this article, and the changes of water–air impact pressure, overflow flow, overflow time, and other parameters produced by blasting in a tunnel with no pressure and nonfull flow were simulated. Specifically, this study focuses on:

  • (1)

    Two different simulation models of transition processes in the tunnel with full and nonfull pressure flow were established according to the 1D MOC and the water–air two-phase flow equation.

  • (2)

    The tunnel with and without pressure blasting was simulated. The hydraulic characteristics were studied, such as impact pressure fluctuation, flow rate, water level, velocity, and overflow time at different locations of the blasting system. The changes in hydraulic characteristics of key buildings were analyzed in detail.

  • (3)

    Comparing the difference between the simulation results of two different models, a better blasting scheme was proposed.

  • (4)

    The numerical simulation results of the water–air two-phase flow model were compared with the actual engineering prototype observation results to illustrate the reliability of the mathematical model.

In rock plug blasting, two mathematical models were proposed to meet different calculation conditions according to the different flow movement states in the tunnel downstream of the blasting point. The first mathematical model was based on MOC, which was used to simulate the impact pressure, water level change, overflow flow, overflow time, and other parameters of the burst water flow in the tunnel. The second mathematical model was based on the actual flow characteristics of water and air, which was used to simulate the impact pressure, overflow flow, air pressure, air mass, and other parameters after blasting in the tunnel with no pressure and nonfull flow. The two mathematical models are described in the following sections.

Mathematical model of the blasting system with pressure flow in the tunnel

The blasting point model of the rock plug was like the valve model. The blasting moment was like the sudden opening of the valve. From the beginning of the blasting to the end, the corresponding valve was closed at the beginning. This state was instantaneous. The reservoir, blasting point, tunnel, ventilation shaft, and terminal maintenance gate model were established according to the composition of the rock plug blasting project's water conveyance system. The specific mathematical models were as follows:

Water hammer equation of pressurized pipeline

Based on MOC, the partial differential equation of the water hammer is transformed into an ordinary differential equation along the characteristic line. The characteristic compatibility equation is established:
(1)
(2)
where is the water head at node A (m); is the flow at node A (m3/s); are coefficients, which can be obtained from the pipeline parameters and head flow before and after the node at the previous moment.

Upstream reservoir model

In the process of hydraulic transition, the reservoir water level can be assumed to be constant, as shown in Equation (3). The rock plug blasting moment will inevitably release huge pressure in the blasting process. To be close to the actual blasting situation, the pressure generated at the blasting is set to three times the hydrostatic pressure () of the reservoir. The reservoir pressure rises rapidly to at the blasting and then decreases to the inlet pressure after a short period unchanged. The change of the upstream reservoir with time is shown in Figure 1. By introducing Equation (3) into Equation (1) C-compatibility equation, the inlet flow of the pipeline at time could be obtained as follows:
(3)
where is the pressure measuring pipe head at the inlet of the pipeline, is the reservoir water level, and C is the constant.
(4)
Figure 1

Water level of the upstream reservoir after blasting.

Figure 1

Water level of the upstream reservoir after blasting.

Close modal

Blasting point model

The rock plug blasting point model is like the general valve model in the numerical simulation of rock plug blasting using MOC. In a very short period, the blasting point is set from static to detonation, corresponding to the process of the valve from closing (τ = 0) to fully opening (τ = 1). According to the flow equation of the valve node, combined with the characteristic line Equations (1) and (2), the control equation of the rock plug blasting point can be established as follows:
(5)
(6)
(7)
(8)
(9)
where is the blasting node flow (m3/s); is the head difference when the valve orifice is fully open (m); is the overflow when the valve is fully open (m3/s); and is the flow coefficient of the dimensionless valve.

Ventilation shaft model

To avoid the huge water hammer pressure after blasting, the ventilation shaft can be adequately reduced by arranging the ventilation shaft in the tunnel after the blasting point. The ventilation shaft is an overflow surge shaft with one inlet and one outlet. The flow continuity equation, head balance equation, water level flow relationship, and pressure pipeline compatibility equation of the ventilation shaft are obtained.
(10)
(11)
(12)
(13)
(14)
(15)
where are the known values at the moment of .

Mathematical model of the blasting system in the tunnel with water and air two-phase flow

When there is no pressure flow in the tunnel behind the rock plug, when the rock plug blasting occurs, because there is a large amount of air in the tunnel, it is necessary to establish an air valve model to simulate the intake and exhaust characteristics. The corresponding water–air two-phase mathematical model is based on the actual characteristics of the water and air in the tunnel and branch hole.

Air valve model

Air valve boundary conditions are divided into the following four cases:

Air flows in at a subsonic speed:
(16)
Air flows in at a critical speed:
(17)
Air flows out at a subsonic speed:
(18)
Air flows out at a critical speed:
(19)
where is the air mass flow; is the flow coefficient of the valve during intake; is the flow area of the valve during intake; is the atmospheric density; is the flow area of the valve during exhaust; is the flow coefficient of the valve during exhaust; and p is the pressure in the pipe.
The air valve is opened to let the air flow in. Before the air is discharged, the air satisfies the constant ideal gas equation:
(20)
The difference equation can be approximately achieved at time of :
(21)
where is the flow out of section i at time of ; is the flow out of section i at time of t; is the flow into the cross section i at time of ; is the mass of the air in the cavity at time of ; is the mass of the air flow into and out of the cavity at time of ; and is the mass of the air flow into and out of the cavity at time of t.

Water–air two-phase flow calculation equations

Based on the actual flow characteristics of actual water and air, according to the flow continuity equation, the relationship between the flow and the water level, the head balance equation, the air valve exhaust equation, and the ideal gas state equation, the calculation equations of water–air two-phase flow are established. After simplification, the differential equations can be obtained as follows:

The flow continuum equation is given in Equations (22)–(23):
(22)
(23)
The relationship between the flow and the water level is shown in Equation (24):
(24)
The head balance equation is given in Equation (25):
(25)
The air valve equation is given in Equation (26):
(26)
The ideal gas state equation is given in Equation (27):
(27)
where is the water level of the upstream reservoir (m); is the tunnel water level (m); is the water level of 1 # branch hole (m); is the area of 1 # branch hole (m2); is the actual flow area of the tunnel (m2); V is the pipe flow rate (m/s); is the flow in the tunnel (m3/s); is the local atmospheric pressure (1.013 × 105Pa); P is the air pressure in the tunnel (Pa); g is the gravitational acceleration (9.81 m/s2); and is the actual flow area at the valve (m2).
A practical rock plug blasting project with different flow patterns has a large scale. The water intake of the project is constructed by rock plug blasting. The schematic diagram of the project inlet layout is shown in Figure 2. It mainly comprises an imported rock plug blasting section, slag pit, ventilation shaft, pressure tunnel, 1# branch hole, and maintenance shaft. The rock plug blasting section is 12 m long, and the rock plug body is funnel shaped. The slag pit is located under the blasting section of the rock plug body, with a length of 44 m. The downstream of the slag pit is a ventilation shaft with a diameter of 1.2 m. After the ventilation shaft, there is a pressure tunnel section with a length of 4,070 m and a diameter of 7.3 m. The tail of the tunnel is a maintenance shaft, which is 81.1 m high, 12.78 m long, and 11.60 m wide. The distance between the head of 1# branch hole and the head of the pressure tunnel section is 3,129 m. The length of 1# branch hole is 713 m, the diameter is 5.6 m, the bottom elevation of the inlet pipeline is 260.37 m, and the outlet elevation is 320.0 m. The water level of the upstream reservoir is 316.0 m during blasting. It is necessary to carry out the safety review calculation of the water level, water pressure, flow rate, and surge changes of the relevant buildings after the blasting to ensure the safe operation of the water pipeline and facilities.
Figure 2

Underwater rock plug blasting system layout: (a) plan view and (b) side view. Notes: ① reservoir, ② rock plug, ③ slag pit, ④ ventilation shaft, ⑤ main tunnel, ⑥ No.19 node, ⑦ 1# branch hole, and ⑧ maintenance shaft.

Figure 2

Underwater rock plug blasting system layout: (a) plan view and (b) side view. Notes: ① reservoir, ② rock plug, ③ slag pit, ④ ventilation shaft, ⑤ main tunnel, ⑥ No.19 node, ⑦ 1# branch hole, and ⑧ maintenance shaft.

Close modal
As shown in Table 1, the upstream reservoir water level is selected as 316 m to carry out numerical simulation research on different states (pressure and no pressure) of the tunnel, which are as follows: Condition 1 is full pipe flow pressure blasting and Condition 2 is water–air two-phase flow nonpressure blasting. When using MOC for simulation, according to the actual layout of the project, the whole pipeline is divided into 62 sections, a total of 63 nodes (Figure 3). The upstream reservoir is No. 1 node; the ventilation shaft close to the reservoir is No. 4 node; the equivalent of 1# branch hole is the surge shaft, which is No. 30 node; and the terminal gate shaft is No. 63 node, which is in a closed state. There is no water in the gate shaft, equivalent to the plugging body. When the water–air two-phase flow equation is used for calculation, the water–air two-phase layout diagram of the blasting system is shown in Figure 4. The initial water level in the main tunnel during blasting is 266.0 m, and the tunnel is not filled with the water flow. In the whole system, the air can only be excluded from the ventilation shaft after blasting. An air valve is set at the top of the ventilation shaft to simulate the mass and pressure change of the air in the system. Under two different conditions, the overflow water level of the ventilation shaft and the 1# branch hole is set to 32.0 m.
Table 1

Calculation conditions of rock plug blasting

ConditionWater level of the reservoirWater level of the tunnelFlow regime of the tunnelCalculation values
316.0 m 267.85 m Pressure flow Water pressure, flow velocity, flowrate, surge change, and total overflow in the ventilation shaft, pressure tunnel, and 1# branch hole. 
316.0 m 266.00 m Nonpressure flow Exhaust process, air pressure, water pressure, air mass, surge height, flow rate changes in the ventilation shaft, 1# branch hole. 
ConditionWater level of the reservoirWater level of the tunnelFlow regime of the tunnelCalculation values
316.0 m 267.85 m Pressure flow Water pressure, flow velocity, flowrate, surge change, and total overflow in the ventilation shaft, pressure tunnel, and 1# branch hole. 
316.0 m 266.00 m Nonpressure flow Exhaust process, air pressure, water pressure, air mass, surge height, flow rate changes in the ventilation shaft, 1# branch hole. 
Figure 3

MOC node layout diagram.

Figure 3

MOC node layout diagram.

Close modal
Figure 4

Air–water two-phase layout diagram of the blasting system.

Figure 4

Air–water two-phase layout diagram of the blasting system.

Close modal
Figure 5

Extreme value distribution of water hammer pressure at different nodes.

Figure 5

Extreme value distribution of water hammer pressure at different nodes.

Close modal

Results of pressure flow in the tunnel

The maximum and minimum distribution of water hammer pressure generated at each node of the water conveyance system under the blasting condition of a tunnel's full flow state is shown in Figure 5. The more considerable pressure of the whole pipeline was distributed between the No. 4 node (ventilation shaft) and No. 30 node (1# branch hole). The pressure value was more significant than 130 m. Most nodes' negative pressure extreme value distribution area was −3.82 to −10 m. The minimum pressure of the whole pipeline was also distributed between the No. 4 node (ventilation shaft) and No. 30 node (1# branch hole). The negative pressure value was −10.0 m (under the vaporization pressure), which indicated that the water body in this area had vaporized. The pressure behind 1# branch hole was almost unchanged, stable at 3.65 m. Affected by the water level fluctuation and water hammer wave reflection of the two surge wells of the ventilation shaft and 1# branch hole, the node between the ventilation shaft and 1# branch hole produced a considerable water hammer pressure. Due to the large area of 1# branch hole, the pressure wave propagating from the upstream to the downstream was effectively cut off, and the pressure wave was prevented from propagating downstream, equivalent to effectively shortening the distance of the pressure pipeline.

The No. 19 node in the middle of the ventilation shaft and 1# branch hole was selected as a typical node to analyze the variation law of water hammer pressure generated at the node. Figure 6(a) shows that the water hammer pressure at the node reached the maximum value of 131.26 m on 3.16 s after blasting. Due to the reflection of the water hammer wave at the ventilation shaft and the 1# branch hole, the minimum pressure reached −75.37 m on 5.49 s. As shown in Figure 6(b), the variation trend of the flow at this node rapidly rose and then declined. At the moment of blasting, when the upstream water level rose sharply, and the downstream water level did not change, the difference between the upstream and downstream water levels increased, resulting in a sudden rise in the flow at node 19, with a maximum flow value of 293.81 m3/s, and a gradual decrease in the water level difference after that. The flow of the tunnel decreased gradually, and the flow returned after 297.1 s, with a minimum value of −5.38 m3/s. The pressure value of the water hammer changed periodically. Although the area of 1# branch hole was significant, which weakened part of the water hammer pressure, the elimination effect of the water hammer wave was not strong due to the considerable pressure generated by blasting, and considerable water hammer pressure was still generated at No. 19 node.
Figure 6

Variations in water hammer pressure and flowrate at No. 19 node during pressure blasting: (a) water hammer pressure change and (b) flow rate change.

Figure 6

Variations in water hammer pressure and flowrate at No. 19 node during pressure blasting: (a) water hammer pressure change and (b) flow rate change.

Close modal
Figure 7 shows the variation of water hammer pressure, water level, inflow and outflow, and overflow flow with time at the ventilation shaft (No. 4 node). The distance between the ventilation shaft and the rock plug blasting port of the upstream reservoir was very close, 25 m, and the shaft diameter was 1.2 m.
Figure 7

Variations in hydraulic characteristics at the ventilation shaft during pressure blasting: (a) water hammer pressure change, (b) water level change, (c) inflow and outflow changes, and (d) ventilation shaft overflow changes.

Figure 7

Variations in hydraulic characteristics at the ventilation shaft during pressure blasting: (a) water hammer pressure change, (b) water level change, (c) inflow and outflow changes, and (d) ventilation shaft overflow changes.

Close modal

From Figure 7(a), the maximum water hammer pressure in the ventilation shaft was the extreme value of the first wave pressure rise, 131.6 m, which occurred within 1 s after blasting. Because the ventilation shaft was close to the rock plug blasting mouth, the pressure in the blasting ventilation shaft rose to the maximum value at the beginning. Then, the subsequent water hammer pressure shows a periodic change. There was a trend of gradual decrease from the maximum value of the second wave water hammer pressure of 56.74–53.17 m. Figure 7(b) shows that the water level of the ventilation shaft rose rapidly to 323 m after blasting, exceeding the overflow water level of 320 m. Similar to the water hammer pressure fluctuation, the ventilation shaft's water level variation presented periodicity. After a period, the water level gradually decreased to 316 m, tended to be stable, and remained unchanged. The relationship between the inflow and the outflow of the ventilation shaft and the time is shown in Figure 7(c). The relative flow rate was the inlet flow value of the ventilation shaft at a specific time minus the flow value of the outlet of the ventilation shaft. Due to the ventilation shaft's small area and the blasting's front end, the inflow of the ventilation shaft quickly reached the maximum of 42.12 m3/s, which occurred at 0.67 s after the blasting. The outlet flow reached the maximum of 17.03 m3/s, which happened in 6.66 s after the blasting. The relationship between the overflow of the ventilation shaft and time is shown in Figure 7(d). The ventilation shaft overflows with the maximum overflow of 27.98 m3, which occurred at 1.8 s after the blasting. The first overflow lasted for 1.3 s. With the subsequent fluctuation of the water hammer pressure, water gushed out from one shaft after another at each time point in the later period. The total number of gushes was three. The overflow of the first overflow was the largest. No overflow occurred after 16 s. From the aforementioned analysis, because the ventilation shaft was close to the location of the blasting point, the blasting point was similar to the valve opening process. An enormous water hammer pressure was generated at the ventilation shaft. After the blasting began, the ventilation shaft began to overflow, and the overflow in the shaft was large. However, due to the small area of the ventilation shaft, the water hammer wave was not well eliminated, and the pipeline was still in a more dangerous state.

Figure 8 shows the relationship between water hammer pressure, flow rate, and overflow with time after blasting in 1# branch hole (30 nodes). The distance between the 1# branch hole and the dam bursting hole of the upstream reservoir is far, i.e., 3,129 m. The diameter of the 1# branch hole is 5.6 m. According to Figure 8(a), after the explosion, the initial pressure of the 1# branch tunnel was 3.82 m, which quickly increased to the maximum pressure value. After 82 s, the water hammer pressure value stabilized at about 57 m. The variation relationship of water level in branch tunnel 1# was consistent with pressure. As shown in Figure 8(b), the maximum water level in branch tunnel 1# was 321.98 m at 83.5 s. After blasting, the water flow rapidly flowed into 1# branch hole. As shown in Figure 8(c), when the maintenance gate held back water well, water flowed into the tunnel from the beginning of blasting. Due to the large diameter of branch hole 1#, the flow into and out of the branch hole was also large when blasting occurred. Also, the distance from the blasting point was relatively large. As a result, the inflow duration was 87 s, and the maximum flow value was 330.73 m3/s, which occurred 56 s after blasting. The maximum outlet flow was 25.69 m3/s, which happened in 90.81 s after blasting. Figure 8(d) shows that 1# branch hole exceeds the overflow water level by 320 m, and an overflow occurred. The overflow occurred at 77.64 s, and the overflow time lasted 227.45 s. After 305.09 s, there was no overflow. The maximum overflow during the overflow process was 248.8 m3. After blasting, the more considerable water hammer pressure propagated from upstream to downstream, and the reflection period was short when it propagated to the end gate well and then returned to 1# branch hole.
Figure 8

Variations in hydraulic characteristics at 1# branch hole during pressure blasting: (a) water hammer pressure change, (b) water level change, (c) inflow and outflow changes, and (d) ventilation shaft overflow changes.

Figure 8

Variations in hydraulic characteristics at 1# branch hole during pressure blasting: (a) water hammer pressure change, (b) water level change, (c) inflow and outflow changes, and (d) ventilation shaft overflow changes.

Close modal

Results of nonpressure flow in the tunnel

Figure 9 shows the change of water hammer pressure in the nonpressure blasting of the ventilation shaft. From Figure 9(a), the pressure in the shaft fluctuated up and down at 2.9 m within 1,540 s after the blasting of the rock plug. When the blasting occurred at 1,543 s, the pressure in the ventilation shaft rose rapidly, reaching a maximum of 60.43 m at about 27 min after the blasting, and the water level rose. After 6 min of continuous fluctuation, the water level began to decline. After 33 min of blasting, the water level dropped to 51.5 m, and then the pressure fluctuation was slight. The final pressure was maintained at 51.5 m, and the final water level was 316 m, consistent with the upper reservoir water level no longer changing. In the water–air two-phase flow model, the overflow height of the ventilation shaft was set to 320 m. That is, the water level of the ventilation shaft began to overflow after the water level of the ventilation shaft exceeded 320 m. Figure 9(b) shows the change process of the height of the water gushing in the ventilation shaft with time. It can be seen from the diagram that the ventilation shaft began to overflow at 1,609 s after the blasting. The maximum overflow height was 5.36 m, and the total duration was about 6 min. The water level in the shaft was below the overflow water level. Due to the existence of a large amount of air in the tunnel before blasting and the high water level of the upstream reservoir, the water body entering the tunnel at the moment of blasting squeezed the air into the ventilation shaft and the outlet of the branch tunnel. For a period after blasting, the air pressure was high, and the water flow did not have enough pressure to impact the air upward, resulting in the water level being almost unchanged in the first 1,500 s. Water did not overflow from the shaft until sometime after the blasting.
Figure 9

Variations in pressure and overflow height at the ventilation shaft during nonpressure blasting: (a) pressure change and (b) overflow height change

Figure 9

Variations in pressure and overflow height at the ventilation shaft during nonpressure blasting: (a) pressure change and (b) overflow height change

Close modal
Figure 10 shows the changes in pressure, water inflow height, and flow velocity during the nonpressure blasting of 1 # branch hole. From Figure 10(a), the pressure of 1 # branch hole rose rapidly after blasting, and the first wave pressure reached the maximum of 60.29 m at 72 s after blasting. The pressure of 1 # branch hole fluctuated around 57–60 m within 1,500 s after blasting, and the fluctuation range was small. After 1,543 s, the pressure suddenly dropped to the lowest point of 31.47 m. After 2,000 s, the pressure of 1 # branch hole was stable at 51.5 m, consistent with the upper reservoir water level. Figure 10(b) shows the surge height change process at the 1 # branch hole outlet with time. According to the project's actual situation, the overflow water level of 1 # branch hole was set to 320 m. When the water level in the branch hole exceeded 320 m, it began to overflow. About 72 s after blasting, 1 # branch hole began to overflow. The maximum overflow height was 5.42 m, with an average of 3.47 m. After 2,000s, the water level of 1 # branch hole was below the overflow water level. As shown in Figure 10(c), the maximum flow velocity of 1 # branch hole was 4.81 m/s, which occurred at 30.2 s after blasting. After blasting for a period, the air in the tunnel was discharged completely. Currently, the water body was full of the tunnel where the air in the tunnel was gradually discharged, and the air pressure gradually decreased. As the water pressure rose, the water pressure in the tunnel and the ventilation shaft began to increase, resulting in the water level in the ventilation shaft spraying upward after reaching the overflow height with a relatively large overflow height. As the whole blasting system was connected, the water flow in the ventilation shaft overflowed, resulting in the drop of the water level in the branch tunnel until it did not change at the upper reservoir water level of 316 m.
Figure 10

Variations in pressure, overflow height, and flow rate at 1 # branch hole during nonpressure blasting: (a) pressure change, (b) overflow height change, and (c) flow rate change.

Figure 10

Variations in pressure, overflow height, and flow rate at 1 # branch hole during nonpressure blasting: (a) pressure change, (b) overflow height change, and (c) flow rate change.

Close modal
Before the rock plug body blasted, the tunnel had much air. The water level in the tunnel was 266 m, which was 1.7 m away from the top elevation of the tunnel. After calculation, the tunnel's initial air volume was 31,000 m3. The pressure and mass of the air in the tunnel changed with time, as shown in Figure 11. From Figure 11(a), after blasting, due to the high water level of the upper reservoir, the water pressure entering the tunnel was considerable, and the air in the tunnel was squeezed into the 1 # branch hole. At 119 s after the blasting, the air pressure in the tunnel reached a maximum of 75.11 m, and then the air pressure decreased slightly with time. When the time reached 1,500 s, the air pressure decreased suddenly, from 62.03 m to the local atmospheric pressure directly. After 1,550 s, the air in the tunnel was discharged entirely through the ventilation shaft, and the tunnel was filled with water. The relationship between the air change in the tunnel and time is shown in Figure 11(b). The air mass in the first 1,500 s after the rock plug blasting was 40,220 kg of the initial air mass, which did not change. After 1,550 s, the air mass in the tunnel decreased rapidly to 0 kg, indicating that the air in the pressure tunnel had been discharged through the ventilation shaft and the tunnel had been filled with water.
Figure 11

Variation in air pressure and mass during nonpressure blasting: (a) air pressure and (b) air mass change.

Figure 11

Variation in air pressure and mass during nonpressure blasting: (a) air pressure and (b) air mass change.

Close modal

The numerical simulation results of pressure blasting and nonpressure blasting in this project were different. When the pressure blasting was carried out, the whole pipeline would produce enormous water hammer pressure. The maximum positive pressure was 131.6 m. Also, the negative pressure was below the vaporization pressure. The extreme value was distributed between the ventilation shaft and the 1 # branch hole node. If the blasting was carried out according to this scheme, the water conveyance system and related buildings may be destroyed. However, when the nonpressure blasting was carried out, the positive pressure was significantly reduced. The maximum positive pressure of the pipeline was 60.43 m. Also, there was no negative pressure along the line. The pressure value of the pipeline met the pressure standard. Therefore, it was recommended to select nonpressure blasting.

The blasting project has been successfully implemented. Given safety considerations, the blasting conditions in the actual project are consistent with the pressure-free blasting of the tunnel. The actual flow pattern of the ventilation shaft and 1 # branch hole after blasting is shown in Figure 12. The water inflow height of the ventilation shaft after blasting, the water inflow height of the 1 # branch hole, and the flow velocity change were measured. The measured data were compared with the numerical simulation results, as shown in Figure 13. The ventilation shaft began to gush water 28.3 min after the blasting. The maximum gushing height was 5.93 m, and the duration was 5.38 min. In the numerical simulation, the ventilation shaft began to gush water 26.6 min after the blasting. The maximum gushing height was 5.35 m, and the duration was 6.2 min. The maximum overflow height in the actual blasting of 1 # branch hole was 4.74 m, with an average of 3.5 m. The maximum overflow height in the numerical simulation was 5.42 m, with an average of 3.24 m. Among them, the measured data of the maximum gushing height of the ventilation shaft differed by 9% from the numerical simulation, and the measured data of the maximum overflow height of the 1# branch hole differed by 14% from the numerical simulation. The aforementioned data show that the numerical simulation results were consistent with the actual blasting results, and the numerical simulation results were credible.
Figure 12

Flow pattern of main buildings after actual blasting: (a) ventilation shaft and (b) 1 # branch hole.

Figure 12

Flow pattern of main buildings after actual blasting: (a) ventilation shaft and (b) 1 # branch hole.

Close modal
Figure 13

Comparison between the actual and simulation results: (a) ventilation shaft and (b) 1 # branch hole.

Figure 13

Comparison between the actual and simulation results: (a) ventilation shaft and (b) 1 # branch hole.

Close modal

This study established mathematical models for the full and nonfull flow modes in the tunnel. Compared with previous studies, this article compared the pressure surge, overflow flow, overflow time, and other parameters generated by the two models under different flow modes in the tunnel. The flow state of the tunnel after the burst point was the critical parameter affecting the impact pressure of rock plug blasting. When the tunnel was filled with water, the impact pressure generated at the blasting moment was much larger than in the state of no pressure. The maximum pressure reached 2.55 times the static pressure of the tunnel, while the maximum pressure in the state of nonpressure blasting was only 1.17 times the static pressure of the tunnel. The maximum impact pressure of the tunnel under pressure blasting was 2.17 times that of nonpressure blasting. Negative pressure occurred along the first half of the blasting system when the tunnel was under pressure. No negative pressure occurred along the system when the tunnel was under no pressure.

In the mathematical model of the blasting system with the pressure flow in the tunnel, it was considered that the valve was opened instantaneously, which meant that the valve opening time was completed instantaneously. Therefore, a significant negative pressure was generated in the first half of the blasting system, and the values were all under the vaporization pressure. Although the ventilation shaft in the system could eliminate part of the water hammer wave, the water hammer wave cannot be eliminated due to the small area of the ventilation shaft. In the author's previous research results, it is also mentioned that to effectively reduce the positive pressure of the water hammer and make the negative pressure meet the system requirements, the diameter of the ventilation shaft should be expanded to 10 m. This approach increased the engineering cost and the need to demonstrate the bearing capacity of rock mass and foundation. Therefore, a mathematical model of the rock plug blasting system was proposed in this article when the tunnel presented the nonpressure flow, which was a new model applicable to the simulated pressure surge after the tunnel shows the nonpressure flow and the changes of the overflow time and the overflow height of the building after the explosion. Compared with the calculation results of the pressure flow in the tunnel of the rock plug blasting system proposed earlier, the tunnel's nonpressure blasting advantages were illustrated. The actual prototype observation data demonstrated the reliability of the mathematical model.

In the mathematical model of the blasting system in the tunnel with water and air two-phase flow, the nonpressure flow contains many different water levels. So long as the wet circumference is not greater than the wet circumference of the full flow, it can be called the nonpressure flow. This article did not propose the change of pressure surge after the explosion of the nonpressure flow under different water levels, which made the research in this article have certain limitations. Moreover, only the actual water and air movement were studied in these two mathematical models. However, in actual engineering, there is a three-phase flow of water, gas, and rock slag (solid) after rock plug blasting. The model proposed in this article ignores the hydraulic transition process law of the three-phase flow, so it is necessary to study further the three-phase flow characteristics of liquid, solid, and gas phases. This research contributes that the model can be extended to the simulation of the hydraulic characteristics of the underwater rock plug blasting system, such as impact pressure, overflow time, and overflow rate. It can predict the parameters under various working conditions before blasting in advance and has a specific reference role for blasting engineering.

Rock plug blasting technology has been applied increasingly in developing and utilizing water and hydropower resources and flood control and disaster reduction projects. The pressure surge of blasting seriously threatens the safety of pipeline structures and other buildings. Predicting the pressure surge and other parameters before rock plug blasting is necessary. This article proposed two mathematical models to simulate the impact pressure of the underwater rock plug blasting system for the pressure flow and the nonpressure flow in the tunnel. The variations of hydraulic characteristics such as pipeline pressure, water flow velocity, flow rate, surge, and overflow after rock plug blasting in the upstream reservoir when the downstream tunnel of a practical project was under pressure and no pressure were simulated. Although the two mathematical models cannot entirely reflect the actual blasting, they can fully reflect the pressure surge and overflow situation of the blasting system after rock block blasting. The relevant conclusions can be applied to predicting transient pressure changes in similar underwater rock plug blasting projects and provide a reference for selecting actual blasting methods in similar blasting projects.

The reliability of the numerical simulation results was illustrated by comparing the measured results after engineering blasting with the numerical simulation results. The main conclusions are as follows:

  • (a)

    A mathematical model of the hydraulic transition process based on MOC was proposed for the pressure flow in the tunnel. In the mathematical model, the pressure blasting of the tunnel was approximately an instantaneous valve opening. The valve opening time was instantaneous, so a considerable water hammer pressure was generated along the blasting system, with the maximum pressure being 2.55 times the hydrostatic pressure. A large negative pressure was generated in the first half of the blasting system. The values were all under the vaporization pressure. Although there was a ventilation shaft in the system to eliminate part of the water hammer wave, due to the small area of the ventilation shaft not eliminating the water hammer wave, it is not recommended to blast the tunnel in the condition of full flow and pressure for the actual project.

  • (b)

    When there was no pressure and nonfull flow in the tunnel, a mathematical model of the water–air transition process based on the actual motion process of the water–air two-phase flow was proposed. When the tunnel behind the blasting point was in a state of no pressure, the impact pressure after blasting was discharged to the maximum 27 min after blasting, and the maximum pressure was only 1.17 times the static water pressure of the tunnel. The maximum impact pressure of the tunnel under pressure blasting was 2.17 times that of the nonpressure blasting, and there was no negative pressure along the system. Under this condition, the difference between prototype observation and numerical simulation was 9–14%. As a result, selecting the tunnel as a nonpressure state for actual blasting was recommended.

The mathematical model proposed in this article provides a valuable and reliable guide for predicting the impact pressure of the underwater rock plug system after blasting to ensure the safety of the tunnel, ventilation shaft, branch tunnel, gate shaft, and other buildings in the blasting system. In the mathematical model proposed in this article, only the actual movement of water and air is considered. In engineering, there is a three-phase flow of water, gas, and rock slag (solid) after rock plug blasting. For the model of rock plug blasting with water and gas two-phase flow, only the nonpressure state in the tunnel is considered, and the sudden change of pressure of the nonpressure flow after blasting at different water levels is not considered, which leads to certain limitations in the research in this article. It is necessary to study further the three-phase flow characteristics of the liquid phase, solid phase, and gas phase, as well as the actual flow characteristics and pressure changes of the tunnel after blasting at different water levels.

The authors gratefully thank the support of the Natural Science Foundation of Xinjiang Uygur Autonomous Region (Grant No. 2021D01B57), Major science and technology projects in Xinjiang Uygur Autonomous Region (Grant No. 2022A02003-4), and Xinjiang Key Laboratory of Hydraulic Engineering Security and Water Disasters Prevention Open Project in 2022 (Grant No. ZDSYS-JS-2022-01).

All relevant data are included in the paper or its Supplementary Information.

The authors declare there is no conflict.

Aminoroayaie Yamini
O.
,
Mousavi
S. H.
,
Kavianpour
M. R.
&
Safari Ghaleh
R.
2021
Hydrodynamic performance and cavitation analysis in bottom outlets of dam using CFD modelling
.
Advances in Civil Engineering
2021
,
1
14
.
Chang
L.
&
Wei
W.
2022
Numerical study on the effect of tangential intake on vortex dropshaft assessment using pressure distributions
.
Engineering Applications of Computational Fluid Mechanics
16
(
1
),
1100
1110
.
Chen
S.
,
Xu
M.
,
Sun
J.
&
Zhang
J.
2022
Hydraulic characteristics study on transient process of air cushion underwater rock plug blasting
.
Journal of Huazhong University of Science and Technology. (Natural Science Edition)
50
(
1
),
113
118 + 131
.
(In Chinese)
.
Cong
J.
,
Chan
S. N.
&
Lee
J. H.
2017
Geyser formation by release of entrapped air from horizontal pipe into vertical shaft
.
Journal of Hydraulic Engineering
143
(
9
),
04017039
.
Ding
L.
1998
Underwater rock plug blasting and its application in hydropower engineering
.
Sichuan Hydropower
17 (
3
),
12
16
.
(In Chinese)
.
Duan
H.
,
Che
T.
,
Lee
P. J.
&
Ghidaoui
M. S.
2018
Influence of nonlinear turbulent friction on the system frequency response in transient pipe flow modelling and analysis
.
Journal of Hydraulic Research
56
(
4
),
451
463
.
Duan
H.
,
Pan
B.
,
Wang
M.
,
Chen
L.
,
Zheng
F.
&
Zhang
Y.
2020
State-of-the-art review on the transient flow modeling and utilization for urban water supply system (UWSS) management
.
Journal of Water Supply: Research and Technology – AQUA
69
(
8
),
858
893
.
He
J.
,
Hou
Q.
,
Lian
J.
,
Tijsseling
A. S.
,
Bozkus
Z.
,
Laanearu
J.
&
Lin
L.
2022
Three-dimensional CFD analysis of liquid slug acceleration and impact in a voided pipeline with end orifice
.
Engineering Applications of Computational Fluid Mechanics
16
(
1
),
1444
1463
.
Hu
Y.
,
Wu
X.
,
Zhao
G.
,
Liu
M.
,
Zhou
X.
&
Li
W.
2016
Through mechanism and experimental study of rock-plug blasting with single and double free faces
.
Chinese Journal of Rock Mechanics and Engineering
35
(
S2
),
3716
3724
.
(In Chinese)
.
Huang
B.
&
Zhu
D. Z.
2021
Rigid-column model for rapid filling in a partially filled horizontal pipe
.
Journal of Hydraulic Engineering
147
(
2
),
06020018
.
Kyriakopoulos
G. L.
,
Aminpour
Y.
,
Yamini
O. A.
,
Movahedi
A.
,
Mousavi
S. H.
&
Kavianpour
M. R.
2022
Hydraulic performance of Howell–Bunger and butterfly valves used for bottom outlet in large dams under flood hazards
.
Applied Sciences
12
(
21
),
10971
.
Li
W.
,
Zhao
G.
,
Zhou
X.
,
Sun
Q.
&
Du
S.
2022
Design and practice of rock-plug blasting by central cracking cutting
.
Engineering Blasting
28
(
5
),
52
59
.
(In Chinese)
.
Liu
J.
,
Qian
Y.
,
Zhu
D. Z.
,
Zhang
J.
,
Edwini-Bonsu
S.
&
Zhou
F.
2022
Numerical study on the mechanisms of storm geysers in a vertical riser-chamber system
.
Journal of Hydraulic Research
60
(
2
),
341
356
.
Qasim
R. M.
,
Mohammed
A. A.
&
Abdulhussein
I. A.
2022
An investigating of the impact of bed flume discordance on the weir-gate hydraulic structure
.
HighTech and Innovation Journal
3
(
3
),
341
355
.
Sharafat
A.
,
Tanoli
W. A.
,
Raptis
G.
&
Seo
J.
2019
Controlled blasting in underground construction: a case study of a tunnel plug demolition in the Neelum Jhelum hydroelectric project
.
Tunnelling and Underground Space Technology
93
,
103098
.
Van Kien
D.
,
Ngoc Anh
D.
&
Ngoc Thai
D.
2022
Numerical simulation of the stability of rock mass around large underground cavern
.
Civil Engineering Journal
8
(
1
),
81
91
.
Wang
Y.
,
Yu
X.
,
Qin
H.
,
Cheng
N.
&
Yu
C.
2022
Analysis of pressure surges for water filling in deep stormwater storage tunnels with entrapped air-pocket using a VOF model
.
AQUA – Water Infrastructure, Ecosystems and Society
71
(
9
),
992
1001
.
Xie
L.
,
Yang
S.
,
Gu
J.
,
Zhang
Q.
,
Lu
W.
,
Jing
H.
&
Wang
Z.
2019
JHR constitutive model for rock under dynamic loads
.
Computers and Geotechnics
108
,
161
172
.
Yang
D.
,
Zhao
Y.
,
Ning
Z.
,
Lv
Z.
&
Luo
H.
2018
Application and development of an environmentally friendly blast hole plug for underground coal mines
.
Shock and Vibration
2018,
1
12
.
Zhai
G.
,
Zhou
T.
,
Ma
Z.
,
Ren
N.
,
Chen
J.
&
Teh
H. M.
2021
Comparison of impulsive wave forces on a semi-submerged platform deck, with and without columns and considering air compressibility effects, under regular wave actions
.
Engineering Applications of Computational Fluid Mechanics
15
(
1
),
1932
1953
.
Zhang
X.
,
Zhang
J.
,
Chen
S.
&
He
W.
2020
Water hammer pressure calculation and protection measures for rock plug blasting engineering
.
Advances in Science and Technology of Water Resources
40
(
4
),
27
32
.
(In Chinese)
.
Zhang
X.
,
Chen
S.
,
Xu
T.
&
Zhang
J.
2022
Experimental study on pressure characteristics of direct water hammer in the viscoelastic pipeline
.
AQUA – Water Infrastructure, Ecosystems and Society
71
(
4
),
563
576
.
Zhao
G.
,
Wu
X.
,
Zhou
X.
,
Li
W.
,
Hu
Y.
&
Wu
C.
2016
Key technology and application of rock plug drilling blasting under deep water condition
.
Engineering Blasting
22
(
5
),
13
17
.
(In Chinese)
.
Zhou
L.
,
Liu
D.
,
Karney
B.
&
Zhang
Q.
2011
Influence of entrapped air pockets on hydraulic transients in water pipelines
.
Journal of Hydraulic Engineering
137
(
12
),
1686
1692
.
Zhou
L.
,
Wang
H.
,
Karney
B.
,
Liu
D.
,
Wang
P.
&
Guo
S.
2018
Dynamic behavior of entrapped air pocket in a water filling pipeline
.
Journal of Hydraulic Engineering
144
(
8
),
04018045
.
This is an Open Access article distributed under the terms of the Creative Commons Attribution Licence (CC BY-NC-ND 4.0), which permits copying and redistribution for non-commercial purposes with no derivatives, provided the original work is properly cited (http://creativecommons.org/licenses/by-nc-nd/4.0/).