To address the issue of low accuracy and inefficiency in the traditional parameter calibration methods for the SWMM model, this paper constructs an automatic parameter calibration model based on multi-objective optimisation algorithms. Firstly, the Sobol method and GLUE method are utilised to determine sensitive parameters and their ranges, aiming to narrow down the solution space and expedite the model-solving speed. Secondly, the NSGA-3 multi-objective optimisation algorithm based on the Pareto theory is applied for the optimisation and calibration of sensitive parameter sets. The model is validated in the rainwater drainage system with independent runoff in a residential area in a northwestern city in China. The results show that parameters such as N-Imperv and KSlope are highly sensitive to the model output under the land-use conditions of the study area. The simulation accuracy of the multi-objective continuous optimisation algorithm is significantly better than that of the single-objective genetic algorithm. The simulation results of the SWMM model under multi-objective optimisation demonstrate a certain level of reliability and stability. The research findings can provide technical support for the automatic calibration of SWMM model parameters, accurate model simulation, and application.

  • The study provides a quantitative interpretation of the results of sensitivity parameter screening and ranking for the SWMM model.

  • During the construction of the objective function, the SWMM model system's multi-objective continuous optimisation criteria were adopted.

  • Combining the concepts of uncertainty and optimisation.

The storm water management model (SWMM) developed by the United States Environmental Protection Agency has a wide range of applications in simulating drainage pipe networks, non-point source pollution loads, and other areas (Rossman 2009; Hu et al. 2018). The SWMM has a complex built-in structure, numerous physical parameters, and uncertainty, often resulting in generalised outcomes with many parameters that cannot be obtained through direct measurements (Behrouz et al. 2019). Manually calibrated simulation results often exhibit significant discrepancies when compared with the measured results. Therefore, it is necessary to develop an automatic calibration model that is compatible with the SWMM interface to calibrate the parameters accurately. Previous approaches to parameter calibration in the SWMM primarily relied on single-dimensional calibration, often using manual trial and error methods, single-parameter sensitivity analysis, and comparisons with observable data (Wani et al. 2017). These methods frequently result in poor alignment with real-world conditions and inefficient calibration processes.

Parameter calibration primarily involves adjusting the physical parameters contained within the model to maximise the alignment of the simulation results with real-world conditions (Sun et al. 2013; Hu et al. 2018). In recent years, researchers have extensively applied various optimisation algorithms, such as genetic algorithms and multi-objective particle swarm optimisation, for the calibration of SWMM model parameters. For example, Liong et al. (1995) coupled SWMM with a genetic algorithm using peak flow as the objective function to optimise the eight parameters of a watershed model. This study demonstrated the suitability of genetic algorithms for optimising watershed model parameters. Wang (2010) utilised the particle swarm optimisation algorithm to optimise eight parameters in the hydrological module of the SWMM. They demonstrated that the particle swarm optimisation algorithm can approximate the optimal solution from a multidimensional space. Kang & Lee (2014) combined an adaptive penalty function with a hybrid complex evolution algorithm for SWMM parameter optimisation. The results indicated that constrained intelligent algorithms were more effective in improving simulation accuracy. However, the problem of underfitting (i.e. mismatch between the water level and flow process curves) remains significant. When the model encounters optimisation problems in complex high-dimensional systems, it often exhibits poor convergence and is prone to becoming stuck in local solutions (Kppen & Yoshida 2007). This can result in significant discrepancies between the optimised results and the actual conditions. Furthermore, most calibration methods are based on assumptions that deviate from the reality. For example, the notion of representing the entire rainfall–runoff process of an entire system using the flow process at the discharge outlet of a network is one-sided. The flow process at the discharge outlet should be considered to be independent of the water level at the network nodes and the flow process within the network pipes (Zhou 2018). Therefore, multi-objective continuous optimisation is expected to become the primary trend in the future calibration of drainage network parameters in SWMM. Among multi-objective continuous optimisation algorithms, the NSGA-3 algorithm is an extension of the NSGA-2 algorithm. It introduces a reference point-based sorting method, retains an elite strategy, and emphasises non-dominated relationships among population members. This addresses the convergence and diversity issues faced by traditional multi-objective optimisation algorithms. Consequently, this study employed a fast, non-dominated sorting genetic algorithm with a reference point-based selection operator (NSGA-3) for the multi-objective calibration of urban drainage network models, following a comparative selection of algorithms (Deb & Jain 2014; Jain & Deb 2014).

In this study, sensitive parameters and their value ranges were first determined using the Sobol and generalised likelihood uncertainty estimation (GLUE) methods (Zhao et al. 2009). This was done to narrow the solution space, prevent model distortion owing to extensive parameter ranges, and accelerate the model-solving process. Subsequently, multi-objective calibration using the NSGA-3 algorithm based on Pareto theory was employed to optimise the calibration with three events and three objectives. This approach yields a Pareto-frontier solution set that serves as a set of alternative parameter scenarios. A real rainfall event was selected, and the model was applied to an independent sub-catchment rainwater drainage network system in a city in Northwestern China. Multiple sets of Pareto-frontier solution sets were randomly chosen for model calibration effectiveness testing. A comparative analysis was conducted to assess the differences in the simulation accuracy between single-objective genetic algorithms and multi-objective continuous optimisation algorithms. This study aimed to validate the reliability of the automatic calibration effectiveness of the model, with the goal of providing technical support for the automatic calibration of SWMM model parameters and accurate simulation and application of the model.

With the continuous development of the SWMM and the expanding scope of its applications, the model structure has become increasingly complex, requiring a richer set of parameters, which has led to higher parameter dimensions (Xia et al. 2008). Calibrating all parameters directly can easily lead to a ‘dimensionality curse’ due to the exponential increase in the computational complexity associated with higher-dimensional model solving. To address this, the Sobol method based on variance decomposition is initially employed in this section to examine the sensitivity of the hydrological module parameters in SWMM concerning peak timing, total runoff, and peak flow across varying rainfall intensities. This helps determine the subset of parameters that need to be calibrated. Additionally, parameter value ranges were constrained using the GLUE method. Subsequently, a multi-objective optimisation model was developed using the NSGA-3 algorithm, incorporating the reference point selection operator and Pareto theory (Guo et al. 2012). The NSGA-3 algorithm was applied to address the multi-objective optimisation problem, resulting in the derivation of the Pareto-frontier solution set, offering an alternative parameter set for the model.

Sobol global sensitivity analysis method based on variance decomposition

The parameter sensitivity analysis aims to identify parameters significantly impacting the simulation results of the model, to optimise their values to prevent overfitting of specific hydrological model parameters, and to avoid transforming the optimisation process into a high-dimensional, nonlinear, and difficult-to-solve problem (Nagel et al. 2020).

In the Sobol global sensitivity analysis method, the use of Monte Carlo principles to compute the sensitivity arising from interactions between parameters is widely employed in large nonlinear models in environmental fields, such as water quality analysis simulation program (WASP), topography based hydrological model (TOPMODEL), soil and water assessment tool (SWAT), because of their robustness in producing results (Zhang et al. 2013). The core idea of this method is to decompose the function f(x) into a sum of increasing terms and samples to calculate the total variance of the response of the model to each parameter and the partial variance of each term. The SWMM is a high-dimensional nonlinear model, and it is not possible to directly calculate the variance of the model output results through analytical integration. Therefore, in this study, based on the Monte Carlo concept, numerical integration was employed to calculate the variance in the model output results. When the number of simulation samples reaches a specific value, the computed solutions closely approximate the analytical solutions. In this section, the runoff volume, peak flow, and peak timing are considered as the output variables for the parameter sensitivity analysis.

The specific calculation steps for the Sobol sensitivity indices in the SWMM for this study area are as follows.

  • (1)
    The Latin hypercube sampling (LHS) method was used to perform two independent samplings within the parameter space, resulting in samples and , as shown in the following equation:
    (1)
    where the base sample size N was set to 5,000, and the number of SWMM model parameters p was 19. Building upon Equation (1), additional 19 new sample matrices, denoted as through , are obtained through a resampling process, where the first column of comes from the first column of , and the p-th column of comes from the column of .
    (2)
  • (2)

    The 21 sample matrices obtained in Step 1, including and , are used to generate 105,000 parameter sets. These parameter sets were then input into the SWMM for simulation calculations, and the objective function values for the output variables were computed.

  • (3)
    The objective function values obtained in step 2 are substituted into the following equations to calculate the sensitivity indices for each parameter X.
    (3)
    (4)
    (5)
    (6)
    (7)
    (8)
    where is the first-order global sensitivity index for the i-th parameter, is the variance caused by the joint effect of parameters other than on the model output results, and is the estimated value. The Sobol method assumes that the SWMM model can be represented in the form of function, where can be viewed as a discrete point in the rp dimension, and u represents the objective function value output by the model. Table 2 lists the main parameters of SWMM.
  • (4)

    The sensitivities of the model parameters were ranked based on the numerical values of . Because Monte Carlo numerical integration is used for the calculations, whether is greater than zero can serve as a criterion for determining the sensitivity of the parameters (Saltelli 2002; Nossent et al. 2011).

Sobol global sensitivity analysis method based on variance decomposition

To avoid excessive model distortion and maintain the parameters within their original physical meanings during calibration, it is essential to constrain the parameters to a specific range. This not only limits the parameter search space but also enhances the optimisation efficiency of multi-objective algorithms (Ragab et al. 2020). To achieve this, the GLUE method was introduced to determine the range of values for sensitive parameters in the SWMM model (Dai & Li 2020). The idea of this method is to use the parameter ranges provided in <the SWMM User Manual> as prior distributions for the sensitive parameters to be calibrated. This was performed using random sampling to create parameter sets, which were then used for the model simulations. Furthermore, a likelihood function was defined, and the likelihood values were calculated based on a comparison between the simulated results from each parameter set and the observed values. Likelihood values are assigned to each parameter set. When the likelihood values were used to represent the calibration probability, a threshold was empirically set, and only parameter sets with likelihood values exceeding this threshold were retained for further use in the model. Finally, a scatter plot was generated to illustrate the correspondence between the parameter values and likelihood values under a specific rainfall intensity, helping to determine the range of values for the sensitive parameters.

In this study, the Nash–Sutcliffe efficiency coefficient (NS) was selected as the likelihood function, as shown in the following equation:
(9)
where t is the time of the simulated flow sequence; is the simulated flow sequence; is the observed flow sequence; and is the mean value of the observed flow sequence.
MATLAB was used to call the core code dynamic link library (DLL) provided by the SWMM model, creating a MATLAB interface for the simulation calculations. Based on the fundamental concept of the algorithm described earlier, a specific workflow is illustrated in Figure 1.
Figure 1

GLUE method applied to SWMM.

Figure 1

GLUE method applied to SWMM.

Close modal

The NSGA-3 multi-objective optimisation algorithm is based on the Pareto theory

Owing to the inherent limitations of manual parameter tuning and single-objective drainage network optimisation algorithms, such as simple genetic and particle swarm optimisation algorithms, the parameter-calibrated models generated using these methods often exhibit poor agreement with real-world data (Wang & Zhou 2009). In this study, a multi-objective combinatorial optimisation was performed. The convergence of the multi-objective optimisation algorithm NSGA-2 tends to be less effective when dealing with three or more objective functions, making it prone to becoming trapped in local solutions (Kppen & Yoshida 2007). To address this issue, this study considers the use of a fast, non-dominated sorting genetic algorithm with a reference point-based selection operator, known as NSGA-3, to solve the multi-objective calibration problem of urban drainage network models.

The NSGA-3 algorithm shares a close resemblance with the popular NSGA-2 algorithm in its overall algorithmic framework (mainly including fast, non-dominated sorting, crowding distance, and crowding distance calculation operators, as well as elite strategy, among others (Chen et al. 2008; Zhou et al. 2019)). However, the NSGA-2 mechanism for maintaining population diversity using a crowding distance operator has certain limitations. In response, NSGA-3 introduces a reference point-based selection operator to replace the crowding distance operator. The core idea of the reference point-based selection operator can be summarised as follows: using a four partitions method as an example to divide three objective functions, a schematic diagram of the reference point distribution is shown in Figure 2. Reference vectors were constructed for the obtained reference points (the reference vector is the line connecting a reference point to the origin). Subsequently, all the vectors were traversed for each individual in the population, and the distance from each population member to the nearest reference point was determined using the formula for the distance from a point to a vector. Simultaneously, the reference point information and the corresponding shortest distance were recorded. In this process, the distance from each population member to the reference point vector is described using perpendicular distance, replacing the crowding distance operator. This is illustrated in Figure 2. Finally, subpopulation selection was performed, and the reference points were removed to complete the construction of the new parent population.
Figure 2

Reference point distribution of three targets and four equal parts.

Figure 2

Reference point distribution of three targets and four equal parts.

Close modal
To validate convergence performance in high-dimensional multi-objective problems using the NSGA-3 algorithm, this study adhered to methods outlined in the literature (Deb et al. 2002; Zitzler et al. 2014). The NSGA-3, particle swarm optimisation algorithm, BrogMOEA multi-objective evolutionary algorithm, and NSGA-2 algorithm were used to optimise and solve the Deb Thiele Laumanns Zitzler 2 (DTLZ2) standard test function with three objectives and 30 independent variables. The hypervolume metric was used to evaluate the solution quality during the iterative process of different optimisation algorithms. A comparative graph showing the changes in the hypervolume metric for the solution set of each algorithm during the iterations is shown in Figure 3.
Figure 3

The vertical distance between the individual and the reference point vector.

Figure 3

The vertical distance between the individual and the reference point vector.

Close modal

The distributions of the Pareto solutions obtained using each algorithm were compared with the corresponding standard Pareto front. The NSGA-3 algorithm exhibits some advantages in terms of solution-set convergence, uniformity, and coverage. The changes in the hypervolume metric indicate that as the number of iterations increases, the hypervolume value corresponding to the NSGA-3 algorithm continues to rise and eventually stabilises. In contrast, the particle swarm optimisation, BrogMOEA, and NSGA-2 algorithms all have slower hypervolume values and longer times to reach stability, with less desirable convergence characteristics.

Construction of a multi-objective optimisation model for parameter automatic calibration

On the one hand, with the improvement of measurement technologies and the emergence of water level monitoring devices such as ISCO ultrasonic flowmeters and ultrasonic level sensors (Wang et al. 2019), it has become easier to measure pipeline flow and water levels at nodes (utility holes) that were previously challenging to observe. However, the construction of intelligent drainage network monitoring and forecasting systems has placed higher demands on the accurate simulation and forecasting of pipeline flows (Creaco et al. 2019; Riaño-Briceño et al. 2016). Therefore, using highly generalised regional outflow rates to calibrate the SWMM does not meet the accuracy requirements, resulting in some discrepancies between the simulation results and actual measurements. To achieve precise simulation and forecasting of water flow in the network and node water levels, in the process of model quantification construction, the objective functions of the SWMM model are transformed into the form as shown in the following equation:
(10)
where X is the set of p SWMM model parameters, and Y is the scalar output of the model (objective function values). For dynamic simulations of the SWMM, the model output does not refer to the entire time series of the simulation results. Instead, it is represented by scalar values obtained by converting the simulation results into objective function values. In this study, the root mean square error (RMSE) was selected as the objective function for the SWMM model output results. Taking the objective function L as an example, the calculation of the RMSE is shown in the following equation:
(11)
where is the simulated value of objective L at time i and is the observed value of objective L at time i.
To avoid the problem of dimensionality in optimisation owing to a large number of variables and to consider the operational efficiency of the model, this study used the flow rates at the outfalls, flow rates in selected key pipes (typically chosen from the main roads, featuring large diameters, long lengths, rapid runoff response, and significant flow variations), and water levels at selected key nodes (typically chosen at pipe junctions, along critical pipes, and nodes with considerable water level variations) as target variables for constructing the objective functions. Among these, the selection of key nodes and pipes for validation was more reflective of the parameter calibration effectiveness for sub-catchment areas relative to the outfall flow rates. This is because the flow simulation conditions at the nodes and pipes can, to some extent, better represent the calibration effect of the parameters in sub-catchment areas. Owing to the extensive nature of the drainage network, outfall flow rates may exhibit complementary flows from different sub-catchment areas. Furthermore, if the simulation performances of the pipes and nodes are reasonable, it can be inferred that the outfall flow rates have a high level of fit. The errors in the unselected nodes and pipes have a slight impact on the accuracy of the system. However, if all the pipes and nodes are included in the calibration, the optimisation equation will be highly dimensional, leading to decreased efficiency. Although the precision improves when considering the overall system error, this comes at the cost of reduced efficiency. Therefore, the selection of key pipes and nodes strikes a balance between efficiency and precision. The RMSE was used as the objective function for the three variables mentioned earlier, as shown in the following equations:
(12)
(13)
(14)
where NODE represents the number of observed water level measurements; CONDUIT represents the number of observed pipe flow measurements; represents the observation time for the k-th rainfall event; represents the simulated flow rate at outfall (outlet) at time i during the k-th rainfall event ; represents the observed flow rate at the outfall (outlet) at time i during the k-th rainfall event ; represents the simulated water level at junction ‘node’ at time i during the k-th rainfall event (m); represents the simulated flow rate in pipe ‘conduct’ at time i during the k-th rainfall event ; represents the actual flow rate in pipe ‘conduct’ at time i during the k-th rainfall event .
Based on the results obtained in sections 1.1 and 1.2, the SWMM multi-objective optimisation parameter solution set, which is a collection of various sensitive parameters, can be represented in the form of the following equation:
(15)
where x represents the sensitive parameters of the model determined in section 1.1, and the value range determined in section 1.2 serves as a constraint in the multi-objective parameter optimisation mathematical model.
The steps for solving the multi-objective optimisation model for the SWMM parameters are shown in Figure 4.
Figure 4

Implementation scheme.

Figure 4

Implementation scheme.

Close modal

Construction of a multi-objective optimisation model for parameter automatic calibration

The selected study area is an independent sub-catchment rainwater drainage network system in a city in northwest China. Figure 5 shows a high-definition satellite image of the drainage sub-area in this region outlined in the yellow box, which is the case study area for this paper.
Figure 5

The research area.

Figure 5

The research area.

Close modal
The study area is located in the New City District of X City, in a flat plain region with a slope ranging from 0.2 to 0.4%. The total area of this sub-catchment is 0.122 km2. It is relatively developed, with 0.022 km2 of greenspace and 0. 1 km2 of rooftops and paved roads. Paved roads are primarily constructed using concrete. The overall greenspace ratio was 18%. There are three main types of land uses in this area: green spaces, paved roads, and building rooftops. In SWMM modelling, the same TAG attribute was assigned to sub-catchment areas of the same land type to facilitate uniform calibration of the relevant parameters. The existing land cover and drainage networks in this area are depicted in Figure 6.
Figure 6

Underlying surface of the research area (a) and current conduit network situation (b).

Figure 6

Underlying surface of the research area (a) and current conduit network situation (b).

Close modal
During the abstraction of the drainage network in the study area, the main pipes on the primary roads, characterised by their large diameters and long lengths, were considered the primary components of the entire drainage network system. Some connecting pipes, branch pipes, and associated elements such as utility holes and rain grates were also abstracted. Based on the geographic information system (GIS) data of the drainage network and the digital elevation model (DEM) elevation information of the study area, the abstracted model comprised 96 nodes, including 94 utility holes and two outfalls. It includes 95 pipes and 50 sub-catchment areas. The abstracted drainage network in the SWMM is shown in Figure 7.
Figure 7

Generalised conduit network and catchments of the research area in SWMM.

Figure 7

Generalised conduit network and catchments of the research area in SWMM.

Close modal

Parameter sensitivity analysis

To avoid the randomness associated with analysing a single rainfall event and ensure the robustness of the results, three short-duration rainfall events observed in the study area in July and August 2019 (with different rainfall intensities, as shown in Table 1) were used as boundary conditions for the model inputs. The sensitivities of the hydrological and hydraulic parameters (listed in Table 2) in the SWMM model for three different levels of rainfall events were assessed with respect to three main categories of output variables: sensitivity indices for runoff volume, peak flow, and peak timing. The sensitivity analysis method described in section 1.1 was used to calculate the first-order sensitivity and total-order sensitivity of various key parameters under Rain1, Rain2, and Rain3 rainfall conditions. The calculation results are listed in Table 3 (owing to space limitations, this paper only presents the results for Rain1).

Table 1

Sensitivity analysis of selected rainfall

Rainfall codeRainfall dateDuration of rainfall (min)Recording interval (min)Peak intensity (mm/5 min)Total rainfall (mm)Rainfall category
Rain1 14 Jul 2019 32 6.5 10.8 Heavy 
Rain2 30 Jul 2019 125 3.2 21.6 Moderate 
Rain3 21 Aug 2019 115 1.1 18.7 Light 
Rainfall codeRainfall dateDuration of rainfall (min)Recording interval (min)Peak intensity (mm/5 min)Total rainfall (mm)Rainfall category
Rain1 14 Jul 2019 32 6.5 10.8 Heavy 
Rain2 30 Jul 2019 125 3.2 21.6 Moderate 
Rain3 21 Aug 2019 115 1.1 18.7 Light 
Table 2

The main parameters and physical meaning of the SWMM model

Parameter codeParameter namePhysical significanceParameter codeParameter namePhysical significance
N-Imperv Manning's coefficient for impervious area 11 N-pev Manning's coefficient for permeable 
 Sub-watershed slope ratio factor 12 Dstore-Perv Storage depth in the permeable portion of the sub-watershed depressions (mm) 
 Sub-watershed width ratio factor 13 Percent routed Flow exchange ratio between permeable and impermeable areas 
S-Imperv Impervious area storage capacity (mm) 14 S-per Permeable area storage capacity (mm) 
Max rate Initial infiltration rate (mm/h) 15 Manning-N Manning's coefficient for pipes 
Min rate Steady-state infiltration rate (mm/h) 16 %Slope Average slope of the sub-watershed 
Con-Mann1 Manning's roughness coefficient for concrete pipe section 17 Exponent Index characterising the functional relationship between water depth or head and flow velocity 
Decay Percolation attenuation coefficient 18 Initial depth Initial water depth at the node at the beginning of the simulation (mm) 
Pct-Zero Percentage of impervious area without depressions 19 Drytime Time required for soil to become dry after wetting 
10 %Imperv-A Percentage of root impermeability … … … 
Parameter codeParameter namePhysical significanceParameter codeParameter namePhysical significance
N-Imperv Manning's coefficient for impervious area 11 N-pev Manning's coefficient for permeable 
 Sub-watershed slope ratio factor 12 Dstore-Perv Storage depth in the permeable portion of the sub-watershed depressions (mm) 
 Sub-watershed width ratio factor 13 Percent routed Flow exchange ratio between permeable and impermeable areas 
S-Imperv Impervious area storage capacity (mm) 14 S-per Permeable area storage capacity (mm) 
Max rate Initial infiltration rate (mm/h) 15 Manning-N Manning's coefficient for pipes 
Min rate Steady-state infiltration rate (mm/h) 16 %Slope Average slope of the sub-watershed 
Con-Mann1 Manning's roughness coefficient for concrete pipe section 17 Exponent Index characterising the functional relationship between water depth or head and flow velocity 
Decay Percolation attenuation coefficient 18 Initial depth Initial water depth at the node at the beginning of the simulation (mm) 
Pct-Zero Percentage of impervious area without depressions 19 Drytime Time required for soil to become dry after wetting 
10 %Imperv-A Percentage of root impermeability … … … 
Table 3

Sensitivity calculation results of parameters of Rain1 rainfall condition

Sensitivity orderTotal runoff
Peak flow
Peak time
Parameter nameParameter nameParameter name
N-Imperv 0.642 0.713 N-Imperv 0.511 0.681 N-Imperv 0.573 0.611 
 0.254 0.362  0.432 0.523  0.511 0.593 
 0.020 0.105  0.411 0.519  0.492 0.532 
S-Imperv 0.011 0.081 Min rate 0.343 0.429 Con-Mann1 0.436 0.497 
Max rate 0.002 0.073 Con-Mann1 0.201 0.389 S-Imperv 0.329 0.411 
Con-Mann1 −0.002 0.033 S-Imperv 0.104 0.198 Min rate 0.204 0.367 
Min rate −0.004 0.044 %Imperv-B 0.050 0.102 Pct-Zero 0.122 0.254 
… … … … … … … … … … 
15 Pct-Zero −0.011 0.065 Decay −0.004 0.091 Max Rate −0.006 0.052 
… … … … … … … … … … 
19 %Imperv-B −0.020 0.066 Min rate −0.015 0.052 Decay −0.018 0.043 
Sensitivity orderTotal runoff
Peak flow
Peak time
Parameter nameParameter nameParameter name
N-Imperv 0.642 0.713 N-Imperv 0.511 0.681 N-Imperv 0.573 0.611 
 0.254 0.362  0.432 0.523  0.511 0.593 
 0.020 0.105  0.411 0.519  0.492 0.532 
S-Imperv 0.011 0.081 Min rate 0.343 0.429 Con-Mann1 0.436 0.497 
Max rate 0.002 0.073 Con-Mann1 0.201 0.389 S-Imperv 0.329 0.411 
Con-Mann1 −0.002 0.033 S-Imperv 0.104 0.198 Min rate 0.204 0.367 
Min rate −0.004 0.044 %Imperv-B 0.050 0.102 Pct-Zero 0.122 0.254 
… … … … … … … … … … 
15 Pct-Zero −0.011 0.065 Decay −0.004 0.091 Max Rate −0.006 0.052 
… … … … … … … … … … 
19 %Imperv-B −0.020 0.066 Min rate −0.015 0.052 Decay −0.018 0.043 

Under Rain1, for runoff volume, the top four sensitivity-ranked parameters were N-Imperv, , , and S-Imperv, with N-Imperv having a significantly higher sensitivity index than the others, indicating that variations in N-Imperv have a more significant impact on the variance of the model results. In contrast, the other parameters have a more negligible influence. For the peak flow, the most highly ranked sensitivity parameters were N-Imperv, , , and max rate. Regarding the peak timing, the sensitivity analysis results were similar to those of the peak flow, with the top four parameters being N-Imperv, , , and Con-Mann1.

The simulation results indicated that rainfall intensity has a significant impact on the sensitivity of the SWMM model parameters. Under heavy rainfall conditions, exemplified by Rain1 and Rain2, parameters related to infiltration-excess runoff, notably N-Imperv, exhibited sensitivity. In contrast, under lower rainfall conditions, such as Rain3, the S-Imperv became a sensitive parameter. In cases of lower rainfall intensity, the depressed storage of the impervious area could hold a certain amount of rainfall, resulting in less surface runoff. However, as the rainfall intensity increases, these depression areas may quickly fill up, and changes in their values have a relatively minor impact on the overall surface runoff. Therefore, parameters such as N-Imperv exhibit sensitivity. The sensitivity analysis results for Rain2 and Rain3 are listed in Table 4.

Table 4

Sensitivity calculation results of parameters of Rain2 and Rain3 rainfall condition

Sensitivity orderTotal runoff
Peak flow
Peak time
Parameter nameParameter nameParameter name
Rain2 N-Imperv 0.623 0.701 N-Imperv 0.505 0.678 N-Imperv 0.579 0.623 
 0.212 0.287  0.432 0.523  0.523 0.567 
 0.023 0.121  0.410 0.512  0.467 0.556 
S-Imperv 0.013 0.072 Min rate 0.323 0.443 Con-Mann1 0.423 0.445 
… … … … … … … … … … 
Rain3 S-Imperv 0.645 0.781 S-Imperv 0.513 0.669 S-Imperv 0.536 0.697 
N-Imperv 0.452 0.523 N-Imperv 0.321 0.481 N-Imperv 0.473 0.511 
 0.276 0.378  0.232 0.323  0.489 0.502 
 0.017 0.123  0.389 0.398  0.192 0.232 
… … … … … … … … … … 
Sensitivity orderTotal runoff
Peak flow
Peak time
Parameter nameParameter nameParameter name
Rain2 N-Imperv 0.623 0.701 N-Imperv 0.505 0.678 N-Imperv 0.579 0.623 
 0.212 0.287  0.432 0.523  0.523 0.567 
 0.023 0.121  0.410 0.512  0.467 0.556 
S-Imperv 0.013 0.072 Min rate 0.323 0.443 Con-Mann1 0.423 0.445 
… … … … … … … … … … 
Rain3 S-Imperv 0.645 0.781 S-Imperv 0.513 0.669 S-Imperv 0.536 0.697 
N-Imperv 0.452 0.523 N-Imperv 0.321 0.481 N-Imperv 0.473 0.511 
 0.276 0.378  0.232 0.323  0.489 0.502 
 0.017 0.123  0.389 0.398  0.192 0.232 
… … … … … … … … … … 

In conclusion, to enhance the efficiency of this parameter calibration method, the selection of the top 10 sensitivity-ranked parameters under three different rainfall scenarios with varying intensities was made for optimisation, as indicated in Table 5. Additionally, MATLAB was employed to call the DLL of the SWMM model, facilitating the screening of sensitive parameters affecting total runoff, peak flow, and peak time. Owing to space constraints, this study provides an example using Rain1 to illustrate the main sensitive parameters and their first-order sensitivity and total-order sensitivity , as depicted in Figure 8.
Table 5

Sensitivity calculation results of parameters of Rain2 and Rain3 rainfall condition

Parameter codeParameter namePhysical significanceUser manual reference value rangeParameter codeParameter namePhysical significanceUser manual reference value range
N-Imperv Manning's roughness coefficient for impervious area (0.01,0.05) Min rate Steady-state infiltration rate (mm·h−1(7.6,15.2) 
 Sub-basin slope proportion factor (0.67,1.67) Con-Mann1 Manning's roughness coefficient for the concrete pipe section (0.011,0.017) 
 Sub-watershed width ratio factor (0.6,1.2) Decay Percolation attenuation coefficient (2,7) 
S-Imperv Impervious area detention capacity (mm) (0.18,2.54) Pct-Zero Percentage of non-depressed impervious area (10,35) 
Max rate Initial infiltration rate (mm·h−1(50.8,101.6) 10 %Imperv-A Percentage of roof impermeability (90,100) 
Parameter codeParameter namePhysical significanceUser manual reference value rangeParameter codeParameter namePhysical significanceUser manual reference value range
N-Imperv Manning's roughness coefficient for impervious area (0.01,0.05) Min rate Steady-state infiltration rate (mm·h−1(7.6,15.2) 
 Sub-basin slope proportion factor (0.67,1.67) Con-Mann1 Manning's roughness coefficient for the concrete pipe section (0.011,0.017) 
 Sub-watershed width ratio factor (0.6,1.2) Decay Percolation attenuation coefficient (2,7) 
S-Imperv Impervious area detention capacity (mm) (0.18,2.54) Pct-Zero Percentage of non-depressed impervious area (10,35) 
Max rate Initial infiltration rate (mm·h−1(50.8,101.6) 10 %Imperv-A Percentage of roof impermeability (90,100) 
Figure 8

Result of sensitivity calculation (rain1). (a) Total runoff flow, (b) peak flow, and (c) peak time.

Figure 8

Result of sensitivity calculation (rain1). (a) Total runoff flow, (b) peak flow, and (c) peak time.

Close modal

The results indicate that land use in the study area has a particular influence on parameter sensitivity. In this area, rooftops and hardened surfaces account for 82% of the total construction area, resulting in a high proportion of impermeable surfaces, making N-Imperv highly sensitive. For permeable areas, the max rate, min rate, and decay parameters in the Horton infiltration model were also considered sensitive. This is because, during heavy rainfall, the runoff rate significantly exceeds the infiltration rate in permeable areas, leading to surface runoff. Sensitive parameters for total runoff and peak flow showed a certain degree of similarity, suggesting that these parameters are correlated with their impacts on peak flow and total runoff in the SWMM model. Con-Mann1 consistently exhibited high sensitivity in the simulation process, particularly in relation to the peak time. This was because the roughness of the conduits affected the flow velocity within the pipes, thereby influencing the peak time.

Comparing the first-order sensitivity and total-order sensitivity of the sensitive parameters, it is observed that some parameters have significantly higher total-order sensitivity than first-order sensitivity, as seen with Con-Mann1 for peak flow. This suggests that this parameter interacts with other parameters during the simulation process, leading to increased variance in the results. Owing to the complexity of the natural environment in the study area, it is often challenging to calibrate the parameters precisely. Instead, parameter estimation relies on a comparison of field monitoring data with historical data, and some hydrological and hydraulic parameters in the SWMM exhibit complementarity or correlation. This can lead to the ‘different parameters, same effect’ issue during model calibration. Therefore, the GLUE method is required to determine the range of values for the parameters within the parameter set.

Parameter range determination

In section 2.2, the parameter set is to be optimised, and the corresponding ranges of the parameter values are determined. However, for some parameters, the ranges were relatively wide. If these wide ranges were directly used as the upper and lower bounds in the multi-objective optimisation model, it would result in an ample search space for the parameter set solutions, which would negatively impact the efficiency of the multi-objective optimisation algorithm. Therefore, this study employed the GLUE method to refine the parameter ranges for individual parameters within the set further. As described in section 1.2, the SWMM, which is provided to users as a DLL, is used. Random sampling was applied to extract the sets of model parameters for the simulation. Scatter plots were created for each parameter against the likelihood values based on the simulation results from the model. The computational results are shown in Figure 9.
Figure 9

Schematic diagram of likelihood calculation value (rain1).

Figure 9

Schematic diagram of likelihood calculation value (rain1).

Close modal

Through the analysis of the scatter plots showing the correspondence between model-sensitive parameter values and likelihood values in Figure 9, it can be observed that except for and , which exhibit significant differences in NS values across different value ranges, the NS values of the other eight sensitive parameters do not show a distinct trend of concentration. During the simulation, the prior distributions of the selected sensitive parameters were assumed to be uniform. However, from the posterior distributions, it is evident that except for and , the remaining parameters do not exhibit regions of high NS concentration. This suggests the presence of the ‘different parameters, same effect’ phenomenon, meaning that the impact on the actual simulation results is not solely due to individual parameters but rather a combination of multiple parameters.

Based on the calculations mentioned earlier, the parameter ranges with likelihood values greater than 0.8 were selected as the upper and lower bounds for the constraints of the multi-objective optimisation model. Narrowing the parameter space improved the efficiency of the algorithm. The selected sensitivity intervals for the optimisation parameter sets are listed in Table 6.

Table 6

Determine the range of parameter (rain1)

Parameter codeParameter namePhysical significanceSensitivity range
N-Imperv Manning's roughness coefficient for impervious area (0.02, 0.07) 
 Sub-watershed slope ratio factor (0.7, 1.2) 
 Sub-watershed width ratio factor (0.7, 0.9) 
S-Imperv Impervious area detention capacity(mm) (0.5, 1.85) 
Max rate Initial infiltration rate (mm·h−1(50.8, 101.6) 
Min rate Steady-state infiltration rate(mm·h−1(7.6, 15.2) 
Con-Mann1 Manning's roughness coefficient for the concrete pipe section (0.013, 0.017) 
Decay Infiltration attenuation coefficient (2, 7) 
Pct-Zero Percentage of non-depressed impervious area (20, 35) 
10 %Imperv-A Roof impermeable percentage (92, 100) 
Parameter codeParameter namePhysical significanceSensitivity range
N-Imperv Manning's roughness coefficient for impervious area (0.02, 0.07) 
 Sub-watershed slope ratio factor (0.7, 1.2) 
 Sub-watershed width ratio factor (0.7, 0.9) 
S-Imperv Impervious area detention capacity(mm) (0.5, 1.85) 
Max rate Initial infiltration rate (mm·h−1(50.8, 101.6) 
Min rate Steady-state infiltration rate(mm·h−1(7.6, 15.2) 
Con-Mann1 Manning's roughness coefficient for the concrete pipe section (0.013, 0.017) 
Decay Infiltration attenuation coefficient (2, 7) 
Pct-Zero Percentage of non-depressed impervious area (20, 35) 
10 %Imperv-A Roof impermeable percentage (92, 100) 

Construction and solution of multi-objective parameter calibration model

By employing the NSGA-3 algorithm introduced in section 1.3, this study resolved the multi-objective optimisation model for the SWMM parameters. Regarding the basic parameter settings for the NSGA-3 algorithm in this study, it was assumed that the maximum number of iterations = 200, population size N = 100, number of decision variables (optimisation parameter set) m = 100, number of objective functions n = 3, mutation parameter = 20, crossover parameter = 20, mutation probability , and crossover probability = 0.62. The model variables included the flow in all conduit segments, water levels at the nodes, and flow at the outfall. The estimated total runtime exceeds 48 h. To enhance model efficiency and narrow the parameter search space, this study focused on the main drainage conduit segments, nodes, and outfalls within the entire network for simulation. Rain1, Rain2, and Rain3 were used as inputs to cover rainfall events at three distinct levels. For objective function one (Equation (12)), flows at outfalls O_1 and O_2 were selected as variables. Water levels at nodes J_3, J_12, J_21, J_94, and J_43 constituted variables for objective function two (Equation (13)). Lastly, flows in conduit segments C_4, C_12, C_27, C_39, and C_75 were chosen as variables for objective function three (Equation (14)). The distribution of the Pareto-optimal frontier solutions obtained using the NSGA-3 algorithm is shown in Figure 10, and the corresponding optimised parameter values are listed in Table 7.
Table 7

Optimisation parameter set

Parameter codeParameter nameNon-dominated set 1Non-dominated set 2Non-dominated set 3Non-dominated set 43
N-Imperv 0.3552 0.3721 0.2985 … 0.2979 
 1.0324 1.0029 0.9945 … 0.9887 
 0.7689 0.8734 0.8856 … 0.8563 
S-Imperv 2.0032 1.8763 1.9873 … 2.0198 
Max rate 63.6739 68.4283 71.3276 … 73.2816 
Min rate 9.8932 10.3672 11.6729 … 12.3678 
Con-Mann1 0.0178 0.0192 0.0210 … 0.0203 
Decay 4.2673 4.1368 4.0389 … 4.0541 
Pct-Zero 11.6734 19.3673 17.3682 … 22.3636 
10 %Imperv-A 96.9 94.5 95.0 … 91.7 
Parameter codeParameter nameNon-dominated set 1Non-dominated set 2Non-dominated set 3Non-dominated set 43
N-Imperv 0.3552 0.3721 0.2985 … 0.2979 
 1.0324 1.0029 0.9945 … 0.9887 
 0.7689 0.8734 0.8856 … 0.8563 
S-Imperv 2.0032 1.8763 1.9873 … 2.0198 
Max rate 63.6739 68.4283 71.3276 … 73.2816 
Min rate 9.8932 10.3672 11.6729 … 12.3678 
Con-Mann1 0.0178 0.0192 0.0210 … 0.0203 
Decay 4.2673 4.1368 4.0389 … 4.0541 
Pct-Zero 11.6734 19.3673 17.3682 … 22.3636 
10 %Imperv-A 96.9 94.5 95.0 … 91.7 
Figure 10

Solution distribution of Pareto-optimal frontier distribution.

Figure 10

Solution distribution of Pareto-optimal frontier distribution.

Close modal

Model validation

To validate the parameter calibration results, the optimised parameter sets were used in the SWMM to obtain simulated results for all hydrological and hydraulic elements, including the water levels at all nodes and flow rates in the pipes. The reliability of the model was tested under different rainfall scenarios, specifically heavy rain (24-h rainfall between 50.0 and 99.9 mm), moderate rain (24-h rainfall between 10.0 and 24.9 mm), and light rain (24-h rainfall less than 10 mm). The parameters were calibrated using Rain1, Rain2, and Rain3, and the model performance was evaluated.

Furthermore, to assess the reliability of the parameter calibration, a focus was placed on calibrating the water levels at the nodes and the flow rates in the pipes. Nodes J_44 and C_27 were selected for validation. The measured and simulated values for the pipe and node conditions during a specific rainfall event (Rain4) were compared. Rain4 occurred on 16 September 2019 with a rainfall duration of 55 min, total rainfall of 16.3 mm, and heavy rainfall intensity. The comparisons are shown in Figures 11 and 12.
Figure 11

Comparison between simulated node J_44 stage hydrograph and actual measured value (with overflow phenomenon).

Figure 11

Comparison between simulated node J_44 stage hydrograph and actual measured value (with overflow phenomenon).

Close modal
Figure 12

Comparison between simulated conduit C_27 hydrograph and actual measured value.

Figure 12

Comparison between simulated conduit C_27 hydrograph and actual measured value.

Close modal
From Figures 11 and 12, it can be observed that when selecting the non-dominated set 4, the simulated values for nodes J_44 and C_27 closely matched the measured values. To objectively evaluate the simulation performance of the model, the runoff volume objective function uses the modified Nash–Sutcliffe efficiency (M-NSE) coefficient, which is a commonly used metric to assess model performance quantitatively. The M-NSE indicates how closely the simulated results, as plotted in the QQ diagram against the 1:1 line, match the observed values, providing an overall reflection of the fitting performance. A value closer to 1 indicates a better model performance. Taking the water level at the nodes as an example, the corresponding formula is given by the following equation.
(16)
where is the observed average water level at the node (m).

The closer the value of M-NSE is to 1, the more reliable and valuable the model. Typically, when M-NSE > 0.75, the simulated values of the model are considered to have a high level of agreement with the observed values when using the optimised parameter set, which can be used for practical engineering purposes (Servat & Dezetter 1991).

Based on the results of the model, under the Rain4 rainfall event (date: 16 September 2019, rainfall duration: 55 min, total rainfall: 16.3 mm, rainfall intensity: heavy rain), using the parameters calibrated with Rain1 (date: 14 July 2019, rainfall duration: 32 min, total rainfall: 10.8 mm, rainfall intensity: heavy rain), the M-NSE values for the J_44 water level process are all above 0.80, and the M-NSE values for the C_27 pipe flow process are also above 0.78, indicating ideal simulation performance. When the model was inputted with rainfall of other intensities (moderate rain and light rain), the M-NSE values for the J_44 water level process were all above 0.82, and the M-NSE values for the C_27 pipe flow process were also above 0.79, indicating excellent model verification results (the verification process is not detailed here because of space limitations). In summary, under this optimal parameter set, the simulation results of the model were reasonably reliable and could be applied in practical engineering.

Compared to single-objective optimisation

To verify whether multi-objective continuous optimisation provides improvements compared to simple genetic alogrithm and single-objective optimisation algorithms (SGA and SOA) were employed for the same verification rainfall event described in section 2.5. In these tests, the three original objectives were linearly weighted (weights of 0.33, 0.33, and 0.34) and treated as a single objective for optimisation. The results are shown in Figure 13. A comparison of the three algorithms showed that multi-objective optimisation algorithms can provide a broader strategy selection space than single-objective optimisation algorithms. Depending on the requirements of the decision maker, any non-dominated solution can be chosen as the preferred solution strategy.
Figure 13

Comparison between single-objective optimisation and multi-objective optimisation.

Figure 13

Comparison between single-objective optimisation and multi-objective optimisation.

Close modal

During the optimisation process using SGA, the basic parameters were set as follows: population size of 350, number of iterations as 100, crossover probability of 0.7, mutation probability of 0.15, and the constraint conditions were based on the parameter ranges determined in section 2.3. The optimal parameter set based on the SGA was obtained through simulations, as listed in Table 8.

Table 8

Optimised parameter set of SGA

Parameter codeParameter nameSGA optimisation valueParameter codeParameter nameSGA optimisation value
N-Imperv 0.0382 Min rate 9.3947 
 0.9732 Con-Mann1 0.0140 
 0.8293 Decay 4.3281 
S-Imperv 1.5732 Pct-Zero 30.2811 
Max rate 90.8753 10 %Imperv-A 97.5266 
Parameter codeParameter nameSGA optimisation valueParameter codeParameter nameSGA optimisation value
N-Imperv 0.0382 Min rate 9.3947 
 0.9732 Con-Mann1 0.0140 
 0.8293 Decay 4.3281 
S-Imperv 1.5732 Pct-Zero 30.2811 
Max rate 90.8753 10 %Imperv-A 97.5266 

Using this optimised parameter set for the model simulations and selecting the same pipe C_27 as in the model validation described in section 2.5, the simulated results were compared with the actual measurements, as shown in Figure 14. The M-NSE coefficient (Equation (16)) was used to evaluate the simulation performance of the three optimisation algorithms quantitatively, and the simulation results are shown in Figure 15: The M-NSE for the pipe C_27 flow process was found to be 0.73. It is generally considered that the M-NSE > 0.75 can be used for practical engineering applications. Comparing all non-dominated sets with the single-objective optimisation results, it can be seen that the NSGA-3 algorithm obtained non-dominant sets with an average pipe flow M-NSE higher than 90.7 and 66.6% of SGA and SOA methods, respectively. For the outfall flow M-NSE, the NSGA-3 algorithm outperformed the SGA method in 86% of the non-dominant solutions, and all non-dominant solutions were higher than those of the SOA method. In terms of the node water level M-NSE, the non-dominant solutions obtained by the NSGA-3 algorithm were superior to those of the SGA and SOA methods. In conclusion, the multi-objective continuous optimisation algorithm outperformed the single-objective optimisation algorithms in the parameter calibration of the SWMM pipe network.
Figure 14

Comparison between simulated conduit C_27 hydrograph and actual measured value based on SGA.

Figure 14

Comparison between simulated conduit C_27 hydrograph and actual measured value based on SGA.

Close modal
Figure 15

Comparison of average M-NSE values of NSGA-3, SGA, and SOA optimisation parameter groups (pipeline flow, outlet flow, and node water level).

Figure 15

Comparison of average M-NSE values of NSGA-3, SGA, and SOA optimisation parameter groups (pipeline flow, outlet flow, and node water level).

Close modal

The novelty of the method

This study proposes a parameter optimisation and calibration method for the SWMM model and applies it to the hydrological parameter optimisation of an independent sub-catchment stormwater drainage pipe network system in a residential area of a northwest city. The simulation results demonstrate good performance. The design of the parameter calibration method proposed in this study has the following innovative points, providing new ideas for parameter calibration of related hydrological models in the future:

  • (1)

    This study provides a quantitative interpretation of the results of sensitivity parameter screening and ranking of the SWMM model. The premise of the parameter calibration is to determine the sensitive parameters in the study area. The core task was to qualitatively or quantitatively evaluate the impact of changes in the model input parameters on the output results. Many scholars have conducted sensitivity analyses of SWMM parameters, but most of them use qualitative methods (Sun et al. 2014; Akdoğan & Güven 2016; Tsai et al. 2017; Swathi et al. 2019). The calculation results can only be used for screening and ranking sensitivity parameters and cannot provide quantitative explanations for the results. In this study, considering the range of values for various parameters in the SWMM, a quantitative analysis of the sensitivity of the SWMM model parameters in the study area was conducted using the Sobol method based on variance decomposition. This method calculates the effect of each parameter on the variance in the model output results and assesses the sensitivity of each parameter.

  • (2)

    During the construction of the objective function, the multi-objective continuous optimisation criteria of the SWMM model system were adopted. Typically, researchers and engineers base the determination of the objective function for parameter calibration optimisation on the belief that the effluent flow hydrograph at the end of the pipe network system can fully represent the entire rainfall–runoff process of the pipe network system (Behrouz et al. 2019; Gao et al. 2023). However, when the effluent flow hydrograph is accurately fitted, the water level at the nodes and flow in the pipe segments of the drainage pipe network system may not necessarily match the observed data. This implied that the effluent flow, node water level, and pipe network flow processes were mutually independent. The starting point of this study was based on the assumption of the mutual independence of these processes. Each process was separately summarised as an objective function, and the final three-objective mathematical model was optimised and solved.

  • (3)

    By combining the concepts of uncertainty and optimisation, this study integrates the uncertainty of the model with the optimisation of a multi-objective mathematical model based on the obtained posterior distribution. Two completely different approaches have emerged for the optimisation and calibration of hydrological model parameters. On one hand, there is the uncertainty approach, which stems from the uncertainty of the model itself. However, there is an optimisation approach based on the optimal objective function of the model. The former considers that the parameter values of the model are uncertain but follow a particular distribution, which can be determined through uncertainty methods, such as Bayesian theory, to obtain the posterior distribution of parameter sets (Chillkoti et al. 2018). The latter assumes that the specific parameter set for the model in a particular case study area is deterministic with only one true parameter set. Even if it cannot be directly obtained through measurements, it can be calibrated using automatic optimisation algorithms. Based on the uncertainty approach, this study used the generalised likelihood uncertainty estimation (GLUE) method to obtain the posterior distribution of the parameter sets. On this basis, a multi-objective optimisation algorithm was employed to obtain the Pareto-front solution set. Although optimisation algorithms were used in this study, the obtained solutions lie on the Pareto front, combining the concepts of uncertainty and optimisation to obtain the optimisation solution of the multi-objective mathematical model based on the obtained posterior distribution.

This study proposes an automatic calibration method for the SWMM model parameters. Sensitivity analysis of the parameters in the study area was conducted using the Sobol method, which is based on quantitative analysis. This involves identifying sensitive parameters, determining their sensitivity ranges, and utilising the NSGA-3 multi-objective optimisation algorithm to perform optimal calibration. The method is based on a multi-objective continuous optimisation criterion that combines the concepts of uncertainty and optimisation.

To verify the effectiveness of the calibration method, numerical experiments were conducted using an independent rainwater drainage network system in a residential area of a city in northwest China. The simulation results were in line with the expectations. To further test the performance of the algorithm, the proposed SWMM parameter multi-objective calibration method was compared with a single-objective genetic algorithm calibration method in terms of simulation accuracy. Under specific optimisation parameter settings, it was found that the simulation accuracy of the multi-objective continuous optimisation algorithm was significantly better than that of the single-objective genetic algorithm. The research findings can provide technical support for the automatic calibration of the SWMM model parameters and the accurate simulation and application of the model.

Regarding the multi-objective continuous optimisation calibration of the SWMM model parameters, the selection of monitoring points in the objective function requires further consideration. This study only selected nodes at the intersections of the main streets, where the inflow was relatively large, as monitoring points for water levels. Subsequent research should propose a systematic and optimised scheme for the arrangement of monitoring points and choose the optimal number and locations more scientifically and economically.

This work was supported by the National Key Research and Development Program Projects for the 14th Five-Year Plan (2021YFC3200200), National Natural Science Foundation Projects (52025093, 51979284), and Free Exploration Project of the State Key Laboratory of Watershed Water Cycle Simulation and Regulation (SKL2022TS01).

The authors have no relevant financial or non-financial interests to disclose.

T. W. conceptualized the whole article, developed the methodology, investigated the work, arranged the software, rendered support in data curation, and wrote the original draft preparation; L. Z. arranged the software, visualized the project, wrote the review, and edited the article; J. Z. investigated the work and arranged the software; L. W. supervised the work, wrote the review and edited the article; Y. Z. wrote the review and edited the article; K. L. wrote the review and edited the article.

All relevant data are included in the paper or its Supplementary Information.

The authors declare there is no conflict.

Akdoğan
Z.
&
Güven
B.
2016
Assessing the sensitivity of SWMM to variations in hydrological and hydraulic parameters: A case study for the city of Istanbul
.
Global NEST Journal
18
(
4
),
831
841
.
https://doi.org/10.30955/gnj.001717
.
Behrouz
M. S.
,
Zhu
Z. D.
,
Matott
L. S.
&
Rabideau
A. J.
2019
A new tool for automatic calibration of the Storm Water Management Model (SWMM)
.
Journal of Hydrology
2019
,
124436
.
https://doi.org/1-0.1016/j.jhydrol.2019.124436
.
Chen
T. F.
,
Zhang
W. C.
&
Bo
w.
2008
Multi-objective calibration with predictive uncertainty analysis for conceptual hydrological models
.
Bulletin of Soil and Water Conservation
(
03
),
107
112
.
https://doi.org/10.13961/j.cnki.stbctb.2008.03.004
.
Chillkoti
V.
,
Bolisetti
T.
&
Balachandar
R.
2018
Multi-objective autocalibration of SWAT model for improved low flow performance for a small snowfed catchment
.
Hydrological Sciences Journal
.
https://doi.org/10.1080/0-2626667.2018.1505047
.
Creaco
E.
,
Campisano
A.
,
Fontana
N.
,
Marini
G.
,
Page
P. R.
&
Walski
T.
2019
Real time control of water distribution networks: A state-of-the-art review
.
Water Research
161
(
SEP.15
),
517
530
.
https://doi.org/10.1016/j.wtres.2019.0-6.025
.
Dai
W. J.
&
Li
J. Y.
2020
Analysis and application of parameter uncertainty of urban storm water model
.
China Water & Wastewater
36
(
03
),
109
113
.
https://doi.org/10.19853/j.zgjsps.1000-4602.2020.03.019
.
Deb
K.
&
Jain
H.
2014
An evolutionary many-objective optimization algorithm using reference-point-based nondominated sorting approach, part I: Solving problems with box constraints
.
IEEE Transactions on Evolutionary Computation
18
(
4
),
577
601
.
https://doi.org/10.1109/TEVC.2013.2-281535
.
Deb
K.
,
Thiele
L.
,
Laumanns
M.
&
Zitzler
E.
2002
Scalable multi-objective optimization test problems[C]//Evolutionary Computation, 2002. CEC'02. Proceedings of the 2002 Congress on IEEE, pp. 825–830. https://doi.org/10.1109/CEC.2002.1007032
.
Gao
J. W.
,
Liang
J.
,
Lu
Y.
,
Zhou
R. L.
&
Lu
X.
2023
Automatic SWMM parameter calibration method based on the differential evolution and Bayesian optimization algorithm
.
Water
15
(
20
),
3582
.
https://doi.org/10.3390/w15203582
.
Guo
J.
,
Zhou
J. Z.
,
Zhou
C.
,
Wang
G. Q.
&
Zhang
Y. C.
2012
Multi-objective optimization for conceptual hydrological models
.
Advances in Water Science
23
(
04
),
447
456
.
https://doi.org/10.14042/j.cnki.32.1309.2012.04.019
.
Hu
Q. F.
,
Zhang
J. Y.
,
Wang
Y. T.
,
Huang
Y.
,
Liu
Y.
&
Ling
L. J.
2018
A review of urbanization impact on precipitation
.
Advances in Water Science
29
(
1
),
138
150
.
https://doi.org/10.14042/j.cnki.32.1-309.2018.01.016
.
Kang
T.
&
Lee
S.
2014
Modification of the SCE-UA to include constraints by embedding an adaptive penalty function and application: Application approach
.
Water Resources Management
28
(
8
),
2145
2159
.
https://doi.org/10.1007/s11269-014-0602-6
.
Kppen
M.
&
Yoshida
K.
2007
Substitute distance assignments in NSGA-II for handling many-objective optimization problems
. In:
International Conference on Evolutionary Multi-Criterion Optimization
.
Springer-Verlag
.
https://doi.org/10.1007/978-3-540-70928-2_55
.
Liong
S. Y.
,
Chan
W. T.
&
Shreeram
J.
1995
Peak-flow forecasting with genetic algorithm and SWMM
.
Journal of Hydraulic Engineering
121
(
8
),
613
617
.
https://doi.org/10.1061/(ASCE)07339429(1995)1-21:8(613)
.
Nagel
J. B.
,
Rieckermann
J.
&
Sudret
B.
2020
Principal component analysis and sparse polynomial chaos expansions for global sensitivity analysis and model calibration: Application to urban drainage simulation
.
Reliability Engineering & System Safety
195
,
1
38
.
https://doi.org/10.1016/j.ress.2019.106737
.
Nossent
J.
,
Elsen
P.
&
Bauwens
W.
2011
Sobol’ sensitivity analysis of a complex environmental model
.
Environmental Modelling and Software
26
(
12
),
1515
1525
.
https://doi.org/10.1016/j.evsoft.2011.0-8.010
.
Riaño-Briceño
G.
,
Barreiro-Gomez
J.
,
Ramirez-Jaime
A.
,
Quijano
N.
&
Ocampo-Martinez
C.
2016
MatSWMM – an open-source toolbox for designing real-time control of urban drainage systems
. Environmental Modelling & Software
83
,
143
154
.
https://doi.org/10.1016/j.envsoft.2016.05.009
.
Rossman
L. A.
2009
Storm Water Management Model User's Manual
.
Saltelli
A.
2002
Sensitivity analysis for importance assessment
.
Risk Analysis
22
(
3
),
579
590
.
https://doi.org/10.1111/0272-4332.00040
.
Servat
E.
&
Dezetter
A.
1991
Selection of calibration objective functions in the context of rainfall-runoff modelling in a Sudanese savannah area
.
International Association of Scientific Hydrology Bulletin
36
(
4
),
307
330
.
https://doi.org/10.1080/02626669109492517
.
Sun
D. Y.
,
Jin
Y. Z.
,
Hu
X. Q.
,
Wang
J. D.
,
Cheng
Y. F.
&
Lu
S. C.
2013
Potential of rainwater resources utilization for main cities in loess plateau of Gansu Province
.
Bulletin of Soil and Water Conservation
33
(
05
),
215
218 + 284
.
https://doi.org/10.13961/j.cnki.stbctb.2013.05.011
.
Sun
N.
,
Bongghi
H.
&
Myrna
H.
2014
Assessment of the SWMM model uncertainties within the generalized likelihood un-certainty estimation (GLUE) framework for a high-resolution urban sewershed
.
Hydrological Processes
28
(
6
),
3018
3034
.
https://doi.org/10.1002/hyp.9869
.
Swathi
V.
,
Srinivasa Raju
K.
,
Varma
M. R. R.
&
Sai Veena
S.
2019
Automatic calibration of SWMM using NSGA-III and the effects of delineation scale on an urban catchment
.
Journal of Hydroinformatics
21
(
5
),
781
797
.
https://doi.org/10.2166/hydr-o.2019.033
.
Tsai
L. Y.
,
Chen
C. F.
,
Fan
C. H.
&
Lin
J. Y.
2017
Using the HSPF and SWMM models in a high pervious watershed and estimating their parameter sensitivity
.
Water
9
(
10
),
780
.
https://doi.org/10.3390/w-9100780
.
Wang
L.
2010
The Research on Urban Drainage Network Inundation Evaluation and Control Based on Modeling Technology
.
Beijing University of Technology
,
Beijing
.
Wang
L.
&
Zhou
Y. W.
2009
Study on PSO multi-objective calibration of SWMM
.
China Water & Wastewater
25
(
05
),
70
74
.
Wang
F. F.
,
Zeng
Y.
,
Zhang
Z. K.
,
Zhang
J. K.
,
Yang
G. B.
&
Qian
J.
2019
Influencing factors and correction analysis of large diameter ultrasonic flow measurement error
.
Chinese Journal of Scientific Instrument
40
(
03
),
146
153
.
https://doi.org/10.19650/j.cnki.cjsi.J1804388
.
Wang
F. F.
,
Zeng
Y.
,
Zhang
Z. K.
,
Zhang
J. K.
,
Yang
G. B.
&
Qian
J.
2020
Application of Generalized Likelihood Uncertainty Estimation (GLUE) at different temporal scales to reduce the uncertainty level in modelled river flows
. Hydrological Sciences Journal
65
(
11
),
1856
1871
.
https://doi.org/10.1080/02626667.2020.1764961
.
Wani
O.
,
Scheidegger
A.
,
Carbajal
J.
,
Rieckermann
J.
&
Blumensaat
F.
2017
Parameter estimation of hydrologic models using a likelihood function for censored and binary observations
.
Water Research
2017
,
290
.
https://doi.org/10.1016/j.watres.2017.05.038
.
Xia
J. D.
,
Wu
F. Q.
&
Yao
Z. H.
2008
Error analysis of distributed hydrological model
.
Bulletin of Soil and Water Conservation
(
04
),
105
110
.
https://doi.org/10.13961/j.cnki.stbctb.2008.04.002
.
Zhang
C.
,
Chu
J.
&
Fu
G.
2013
Sobol's sensitivity analysis for a distributed hydrological model of Yichun River Basin, China
.
Journal of Hydrology
480
,
58
68
.
https://doi.org/10.1016/j.jhdrol.2012.12.0-05
.
Zhao
D. Q.
,
Wang
H. Z.
,
Chen
J. N.
&
Wang
H. C.
2009
Parameters uncertainty analysis of urban rainfall-runoff simulation
.
Advances in Water Science
20
(
01
),
45
51
.
https://doi.org/10.14042/j.cnki.32.1309.20-09.01.012
.
Zhou
Y. F.
2018
Sensitive Parameters Identification and Multi-Objective Optimization Calibration of SWMM Drainage Pipe Network Model
.
Zhejiang University
,
Hangzhou
.
Zhou
Y. F.
,
Zhou
Y. C.
,
Zheng
C. H.
,
Wong
X. M.
,
Ma
X. Y.
&
Liu
J. Q.
2019
Sensitivity analysis of parameters of storm water management model with Sobol method
.
Journal of Zhejiang University (Engineering Science)
53
(
02
),
347
354
.
https://doi.org/10.3785/j.issn.1008-973X.2019.02.018
.
Zitzler
E.
,
Deb
K.
&
Thiele
L.
2014
Comparison of multi-objective evolutionary algorithms: Empirical results
.
Evolutionary Computation
8
(
2
),
173
195
.
https://doi.org/10.1162/106365600568202
.
This is an Open Access article distributed under the terms of the Creative Commons Attribution Licence (CC BY 4.0), which permits copying, adaptation and redistribution, provided the original work is properly cited (http://creativecommons.org/licenses/by/4.0/).