Ongoing hydropower projects along Teesta river basin (as of 28.07.2019).

Project nameLocationInstalled capacity (MW)Latest status/Remark
Bakchachu North Sikkim 40 Project under survey and investigation by Sanvijay Power and Allied Industries Ltd 
Bhasmey East Sikkim 51 Project under construction by Gati Infrastructures Ltd. As per MoU, date of commissioning was December 2013. Project progress is around 28% 
Chuzachen East Sikkim 99 Project under construction by Gati Infrastructures Ltd. As per MoU, date of commissioning was June 2013 
Dikchu North/East Sikkim 96 Project under construction by Sneha Kinetic Power Projects Ltd. As per MoU, date of commissioning was December 2013 and project declared COD on March 2017 
Jorethang South Sikkim 96 Project under construction by DANS Energy Pvt Ltd. As per MoU, date of commissioning was June 2013 and project declared COD on September 2017 
Paanan North Sikkim 300 Project under construction by Himagiri Hydro Energy Pvt Ltd. As per MoU, date of commissioning was September 2013 and only preliminary construction works started 
Rahi Kyoung North Sikkim 26 Project under survey and investigation by Sikkim Engineering Pvt Ltd. DPR is under preparation. Public hearing has been concluded by SPCB 
Ramman III West Bengal 120 Project under construction by NTPC 
Ranjit II West Sikkim 66 Project under construction by Sikkim Hydro Ventures Ltd. As per MoU, date of commissioning was May 2013. Project progress is around 12% 
Ranjit IV West Sikkim 120 Project under construction by Jal Power Corporation Ltd. As per MoU, date of commissioning was July 2015. Project progress is around 49% 
Ronginichu East Sikkim 96 Project under construction by Madhya Bharati Power Corpora. As per MoU, date of commissioning was December 2013. Project progress is around 64% 
Tashiding West Sikkim 99 Project under construction by Shiga Energy Pvt Ltd. As per MoU, date of commissioning was September 2015. Project declared COD on September 2017 
Teesta Stage III North Sikkim 1,200 Project under construction by Teesta Urja Limited. As per MoU, date of commissioning was December 2013 and project declared COD on February 2017 
Teesta Stage IV North Sikkim 520 Project under construction by NHPC. Only preliminary construction works started. First stage environment clearance is obtained 
Teesta Stage VI North/ South Sikkim 500 Project under construction by Lanco Energy Pvt Ltd. As per MoU, date of commissioning was July 2013. Project progress is around 48% 
Project nameLocationInstalled capacity (MW)Latest status/Remark
Bakchachu North Sikkim 40 Project under survey and investigation by Sanvijay Power and Allied Industries Ltd 
Bhasmey East Sikkim 51 Project under construction by Gati Infrastructures Ltd. As per MoU, date of commissioning was December 2013. Project progress is around 28% 
Chuzachen East Sikkim 99 Project under construction by Gati Infrastructures Ltd. As per MoU, date of commissioning was June 2013 
Dikchu North/East Sikkim 96 Project under construction by Sneha Kinetic Power Projects Ltd. As per MoU, date of commissioning was December 2013 and project declared COD on March 2017 
Jorethang South Sikkim 96 Project under construction by DANS Energy Pvt Ltd. As per MoU, date of commissioning was June 2013 and project declared COD on September 2017 
Paanan North Sikkim 300 Project under construction by Himagiri Hydro Energy Pvt Ltd. As per MoU, date of commissioning was September 2013 and only preliminary construction works started 
Rahi Kyoung North Sikkim 26 Project under survey and investigation by Sikkim Engineering Pvt Ltd. DPR is under preparation. Public hearing has been concluded by SPCB 
Ramman III West Bengal 120 Project under construction by NTPC 
Ranjit II West Sikkim 66 Project under construction by Sikkim Hydro Ventures Ltd. As per MoU, date of commissioning was May 2013. Project progress is around 12% 
Ranjit IV West Sikkim 120 Project under construction by Jal Power Corporation Ltd. As per MoU, date of commissioning was July 2015. Project progress is around 49% 
Ronginichu East Sikkim 96 Project under construction by Madhya Bharati Power Corpora. As per MoU, date of commissioning was December 2013. Project progress is around 64% 
Tashiding West Sikkim 99 Project under construction by Shiga Energy Pvt Ltd. As per MoU, date of commissioning was September 2015. Project declared COD on September 2017 
Teesta Stage III North Sikkim 1,200 Project under construction by Teesta Urja Limited. As per MoU, date of commissioning was December 2013 and project declared COD on February 2017 
Teesta Stage IV North Sikkim 520 Project under construction by NHPC. Only preliminary construction works started. First stage environment clearance is obtained 
Teesta Stage VI North/ South Sikkim 500 Project under construction by Lanco Energy Pvt Ltd. As per MoU, date of commissioning was July 2013. Project progress is around 48% 

Sources: CEA (2016), EDPS (2019), NHPC (2019), NTPC (2019).

COD, Commercial operation date; DPR, detailed project report; SPCB, State Pollution Control Board; MoU, memorandum of understanding.