Table 4

Cost in USD for 100,000 m3/day capacity plant

Cost componentFOROLPRO
Equipment + material + membrane $ 40,866,655.8 $ 36,813,500 $ 30,500,000 
Construction $ 37,874,492.2 $ 83,886,500 $ 69,500,000 
Total cost $ 78,741,148 $ 120,700,000 $ 100,000,000 
Cost componentFOROLPRO
Equipment + material + membrane $ 40,866,655.8 $ 36,813,500 $ 30,500,000 
Construction $ 37,874,492.2 $ 83,886,500 $ 69,500,000 
Total cost $ 78,741,148 $ 120,700,000 $ 100,000,000 