Table 3

Estimated investment and yearly cost for drilling and development of wells and complete reconstruction of spring catchments in Aleksinac municipality

WorksInvestment cost (EUR)Yearly costa (EUR/Year)
Well 
 Well drilling and development (200 m well with steel casing and 50 m of screen) 31,000 1,250 
 Pumping equipment with 4 in. pump – delivery up to 7 l/s and head up to 60 m 9,150 460 
 Well house/shaft 4,300 300 
 Electro installations 10,450 730 
 Reservoir (30 m316,500 420 
Total for 7 wells 499,800 22,120 
Spring catchment 
 Catchment construction 9,050 400 
 Pipeline and electro installation 1,500 110 
 Reservoir (10 m37,000 175 
Total for 5 spring catchments 87,750 3,425 
WorksInvestment cost (EUR)Yearly costa (EUR/Year)
Well 
 Well drilling and development (200 m well with steel casing and 50 m of screen) 31,000 1,250 
 Pumping equipment with 4 in. pump – delivery up to 7 l/s and head up to 60 m 9,150 460 
 Well house/shaft 4,300 300 
 Electro installations 10,450 730 
 Reservoir (30 m316,500 420 
Total for 7 wells 499,800 22,120 
Spring catchment 
 Catchment construction 9,050 400 
 Pipeline and electro installation 1,500 110 
 Reservoir (10 m37,000 175 
Total for 5 spring catchments 87,750 3,425 

aAmortization 2–4%; maintenance 1–2%, other costs 1%.