With the continuous increase in environmental requirements and regulations for wastewater treatment a lot of wastewater treatment plants in Austria had to be extended. Extension of the plant requires in general an additional area, which is not always available. This study shows the extension of the WWTP Hard Hofsteig and doubling its capacity by using the Hybrid concept, which is a special two stage activated sludge process for extensive nutrient removal. The plant was extended from 170,000 PE to 270,000 PE without changing the footprint of the plant and the extension costs could be kept very low. Operational data shows that by operating the plant in the two stage Hybrid mode the energy balance of the plant can be improved.
INTRODUCTION
Because of a demand for more efficient wastewater treatment processes, a lot of wastewater treatment plants (WWTP) built in the 1970s and 1980s had to be upgraded and extended for complete nutrient removal. Apart from the fact that extension of the WWTPs requires an additional area, which is not always available, it is also associated with considerable investments.
The Hard-Hofsteig WWTP is situated in the Austrian province of Vorarlberg near Lake Constance. Catchment area of Hofsteig WWTP covers the municipalities of Bildstein, Fußach, Gaißau, Hard, Höchst, Lauterach, Lustenau and Wolfurt. Some of these communities have textile, metal and food industry, which contribute to a high organic pollution of the wastewater.
At that time, biological stage of the WWTP1 was out of operation.
The HYBRID® concept consists of high loaded first stage and a low loaded second stage, with a combination of sludge cycles, to enable nitrogen removal (Matsché & Winkler 2014; Winkler et al. 2008). This two stage activated sludge process combines the advantages of single and two stage activated sludge plants achieving extensive nutrient removal. Main advantages of this concept are a small space demand, robustness against substantial load variations, high operational flexibility, and high potential of integrating the existing plant structures into an extension concept in case of upgrading the nutrient removal. The first stage is a high loaded activated sludge process, with a low sludge age of 1–3 days and a volumetric loading of 3–5 kg BOD5kg/m3,d. This results in a high excess sludge production, with low oxygen demand. Subsequently, this excess sludge provides a good substrate for anaerobic digestion and boosts biogas production, while the energy demand for aeration in the first stage can be kept low.
The second stage is a low loaded activated process with an SRT over ten days for secured nitrification and volumetric loading of 0.05–015 kg BOD5/m3,d. For denitrification, a side stream of high loaded sludge from the first stage (sludge-circle 1, Figure 3) is transferred into the second stage as carbon source for denitrification.
Excess sludge of the second stage is transferred into the first stage through the sludge-circle 2, transferring the nitrifying sludge into the first stage, which is operated at an SRT which is too short to maintain the autotrophic bacteria growth. Due to the high loading in the first stage, the nitrate produced is immediately denitrified by high loaded sludge. It can be estimated that the first stage can yield up to 40% of total nitrogen removal capacity of the plant.
Total nitrogen removal of the whole process can be further improved by recycling treated effluent into the first stage.
For the first high loaded stage of the Hybrid plant, the original biological stage with a volume of 5,600 m3 which was not operated was partially used: 4,200 m3 for the high loaded aeration tank and 1,400 m3 for engine room and intermediate pumping station. 50% of the final sedimentation tank (3,000 m3) of WWTP 1 was used as an intermediate sedimentation tank.
As the low loaded stage of the Hybrid plant, the existing biological stage of the WWTP2 was used. Final sedimentation of new Hybrid plant consists of 3,000 m3 volume of WWTP1 and 9,000 m3 volume of WWTP2.
Table 1 gives an overview of the two extensions to WWTP Hard-Hofsteig.
The three phases of the extension of WWTP Hard-Hofsteig
. | Original Plant WWTP1 Start-Up 1974 . | 1st Extension WWTP2 Start-Up 1997 . | 2nd Extension WWTP3 Start-Up 2015 . |
---|---|---|---|
Load | 80,000 PE | 138,000 PE | 270,000 PE |
Primary Sedimentation | 1,300 m3 | 630 m3 | 630 m3 |
Biological stage original plant (Stage 1 Hybrid plant) | |||
Aeration Tank | 5,600 m3 | Not operated | 4,200 m3 |
Settling Tank | 6,000 m3 | Not operated | 3,000 m3 |
Biological Stage 1st extension (Stage 2 Hybrid plant) | |||
Aeration Tank | 17,000 m3 | 17,000 m3 | |
Settling Tank (2 circular tanks) | 9,000 m3 | 9,000 m3 | |
Settling Tank (2 rectangular tanks) | 3,000 m3 | ||
SBR tank for sludge liquor treatment | 630 m3 | 630 m3 | |
Specific volume of Aeration Tank | 70 L/PE | 123 L/PE | 78 L/PE |
Only C Removal | CNP Removal | CNP Removal |
. | Original Plant WWTP1 Start-Up 1974 . | 1st Extension WWTP2 Start-Up 1997 . | 2nd Extension WWTP3 Start-Up 2015 . |
---|---|---|---|
Load | 80,000 PE | 138,000 PE | 270,000 PE |
Primary Sedimentation | 1,300 m3 | 630 m3 | 630 m3 |
Biological stage original plant (Stage 1 Hybrid plant) | |||
Aeration Tank | 5,600 m3 | Not operated | 4,200 m3 |
Settling Tank | 6,000 m3 | Not operated | 3,000 m3 |
Biological Stage 1st extension (Stage 2 Hybrid plant) | |||
Aeration Tank | 17,000 m3 | 17,000 m3 | |
Settling Tank (2 circular tanks) | 9,000 m3 | 9,000 m3 | |
Settling Tank (2 rectangular tanks) | 3,000 m3 | ||
SBR tank for sludge liquor treatment | 630 m3 | 630 m3 | |
Specific volume of Aeration Tank | 70 L/PE | 123 L/PE | 78 L/PE |
Only C Removal | CNP Removal | CNP Removal |
RESULTS AND DISCUSSION
The planning of enlargement started during the year 2010 and construction of the plant was finished by the end of 2014. During the planning and construction period, some enterprises which were major contributors to the pollution load of the plant were closed down, thus certain load reductions occurred. During the years 2012 and 2013, peak loads were below 160,000 PE, but during 2014 they reached 200,000 PE.
The comparison of the design and operational data (Table 2) shows that the WWTP3 is significantly underloaded and has considerable reserves, which enables start-up of new industrial enterprises in the future.
Comparison of design and operational data for WWTP2 and WWTP3
. | Design Data . | Operational data . | ||||
---|---|---|---|---|---|---|
WWTP2 | WWTP3 | WWTP2a | WWTP2b | |||
BOD5 60 g/PE,d | 138,000 | 270,000 | 139.311 | 123,428 | ||
Flow m3/d | 29,000 | 29,000 | 20,088 | 22,004 | ||
BOD5 kg/d | 8,288 | 16,298 | 7,146 | 7,406 | ||
COD kg/d | 14,400 | 32,596 | 16,717 | 15,055 | ||
TN kg/d | 1,271 | 1,800 | 1,054 | 1,014 | ||
TP kg/d | 289 | 318 | 265 | 120 | ||
First Stage | Second Stage | First Stage | Second Stage | |||
Volumetric Loading kgBOD5/m3,d | 0.33 | 3.4 | 0.11 | 0.27 | 1.23 | 0.09 |
MLSS g/l | 3.4 | 2 | 2 | 3.5 | 1.6 | 2.9 |
Sludge Age d | 14.4 | 0.44 | 31.2 | 15 | 3 | 33 |
. | Design Data . | Operational data . | ||||
---|---|---|---|---|---|---|
WWTP2 | WWTP3 | WWTP2a | WWTP2b | |||
BOD5 60 g/PE,d | 138,000 | 270,000 | 139.311 | 123,428 | ||
Flow m3/d | 29,000 | 29,000 | 20,088 | 22,004 | ||
BOD5 kg/d | 8,288 | 16,298 | 7,146 | 7,406 | ||
COD kg/d | 14,400 | 32,596 | 16,717 | 15,055 | ||
TN kg/d | 1,271 | 1,800 | 1,054 | 1,014 | ||
TP kg/d | 289 | 318 | 265 | 120 | ||
First Stage | Second Stage | First Stage | Second Stage | |||
Volumetric Loading kgBOD5/m3,d | 0.33 | 3.4 | 0.11 | 0.27 | 1.23 | 0.09 |
MLSS g/l | 3.4 | 2 | 2 | 3.5 | 1.6 | 2.9 |
Sludge Age d | 14.4 | 0.44 | 31.2 | 15 | 3 | 33 |
aOperational Data 01.01.2014–15.11.2014.
bOperational Data 15.11.2014–30.06.2015.
Meanwhile, the operation of the plant has been changed by operating only one of two trains. This resulted in a significant increase of volumetric load of the first stage and approaching conditions according to the design of the process.
Plant performance
For acclimated activated sludge and temperatures lower than 25°C, nitrification is complete and nitrite concentrations are lower than 0.1 mg/l. However, in transient conditions, e.g. start-up, NO2-N, concentrations of 5–20 mg/l are possible at low NH4-N concentrations (Metcalf & Eddy 2014).
Discharge of the effluent into Lake Constance is subject to very strict regulations. Effluent limits and the performance of WWTP2 and WWTP3 are shown in Table 3.
Effluent limits and treatment efficiency of WWTP2 and WWTP3
. | WWTP2 . | WWTP3 . | WWTP2/ WWTP3 . | WWTP2a . | WWTP3b . |
---|---|---|---|---|---|
. | Influent mg/l . | Effluent Limits mg/l (Catchment Lake Constance) . | Removal Efficiency . | ||
BOD5 | 362 | 348 | 15 | 98% | 99% |
COD | 849 | 719 | 60 | 96% | 97% |
TN | 52 | 48 | >70%c | ∼80% | ∼70% |
NH4-N | 31 | 31 | 5 | 95% | 96% |
TP | 13.2 | 6 | 0.5 | 97% | 93% |
. | WWTP2 . | WWTP3 . | WWTP2/ WWTP3 . | WWTP2a . | WWTP3b . |
---|---|---|---|---|---|
. | Influent mg/l . | Effluent Limits mg/l (Catchment Lake Constance) . | Removal Efficiency . | ||
BOD5 | 362 | 348 | 15 | 98% | 99% |
COD | 849 | 719 | 60 | 96% | 97% |
TN | 52 | 48 | >70%c | ∼80% | ∼70% |
NH4-N | 31 | 31 | 5 | 95% | 96% |
TP | 13.2 | 6 | 0.5 | 97% | 93% |
aOperational Data 01.01.2014–31.10.2014.
bOperational Data 01.01.2015–30.06.2014.
cThe annual average for wastewater T > 12°C.
It can be seen in Table 3 that the ratio of TKN/COD is relatively low, probably due to industrial contributions (0.063 in 2014 and 0.067 in 2015). However, there are several Hybrid plants in Austria which receive only domestic wastewater and obtain up to 85% nitrogen removal, as well.
Due to reduced organic load in the influent, the loading of the WWTP3 first stage was significantly lower than the design load, which resulted in a higher BOD5 removal and lower denitrification capacity in the second stage.
COD balance
Out of the data presented in Figure 7, the assumed advantages of the two stage Hybrid process can be confirmed. Surplus sludge production is increased by 27%, energy consumption in the aeration tanks is reduced by 25% and biogas production is increased by 15%.
Specific energy demand for aeration and specific biogas production before and after the enlargement are summarized in Table 4, and they clearly indicate the advantages of the Hybrid process.
Specific biogas production and oxygen demand of WWTP2 and WWPT3
. | WWTP2 . | WWTP3 . |
---|---|---|
Oxygen demand kgO2/kgCOD | 1 | 0.75 |
Specific biogas production l/PE,d | 18 | 21 |
. | WWTP2 . | WWTP3 . |
---|---|---|
Oxygen demand kgO2/kgCOD | 1 | 0.75 |
Specific biogas production l/PE,d | 18 | 21 |
Sludge characteristics
The first stage of the Hybrid plant is highly loaded and usually characterized with a very low sludge volume index (SVI). Previous experiences have shown that properties of sludge from the high loaded stage essentially determine the properties of second stage sludge and that the SVI of the second stage is low, as well (Winkler et al., 2004).
Cost savings
In case of WWTP Hard-Hofsteig, specific construction costs of plant enlargement were extremely low. Bearing in mind that the capacity of the plant was extended from 138,000 PE to 270,000 PE and that construction costs were approx. 6.25 million €, specific costs per inhabitant amounted to as low as 47 €/PE, which is extremely favourable as compared to a one stage plant. According to the benchmarking project of ÖWAV (Österreichischer Wasser und Abfallwirtschaftsverband) published in report End Report Part A 2012, construction costs of a conventional single stage plant for nutrient removal were 160 €/PE, which is 70% higher than construction costs of the Hard-Hofsteig plant.
CONCLUSIONS
With application of the Hybrid concept to the WWTP Hard-Hofsteig, the treatment capacity could be significantly increased, without using an additional area to the original footprint. Since no additional space was available at the location of the treatment plant, the Hybrid concept was the only alternative for the enlargement. However, the need for the enlargement can only be implemented in the future, when the load increases further due to economic development.
As predicted, energy demand for aeration has decreased significantly and was only 75% as compared to the previous single stage operation.
Due to a higher surplus sludge production in the first stage, biogas production has increased by 15%. However, specific biogas production of 21 L/PE,d is comparatively low, since the organic load of the plant was only 50% of the design load.
The reduced load to the plant has also a negative influence on the SVI, which is normally bellow 120 ml/g in more than 10 existing plants in Austria, operated as Hybrid.
Maximum usage of the existing tank volumes and low specific volume demand of the Hybrid process resulted in extremely low construction costs, which were below 50 €/PE.