The SHAFDAN is the largest wastewater treatment plant in Israel and currently treats 360,000 m3/day of municipal wastewater, about 92% of its treatment capacity. Waste sludge from the plant is discharged to the Mediterranean Sea through a marine outfall. The SHAFDAN is committed to ending the disposal of its sludge to the sea by the end of 2016 by providing a land-based biosolids management program that produces a Class A biosolids for agricultural use. In order to implement this strategy, a number of large-scale construction projects were undertaken. These projects include a new sludge thickening and dewatering facility, updated headworks, a new primary treatment facility, and a new 3-stage thermophilic anaerobic digestion facility. The total capital cost of these projects is estimated to be US $300 million. This paper describes the principal components of these projects and their design parameters.
INTRODUCTION
As the plant is approaching its design capacity (the plant is currently at about 92% of its treatment capacity), SHAFDAN had chosen to add a primary treatment stage to reduce the organic loading to the secondary treatment process as part of the plant expansion.
In accordance with a decision taken several years ago, SHAFDAN is also committed to developing a land-based biosolids management program, producing a Class A biosolids product for agricultural use by the end of 2016. In order to implement this strategy, the following facilities were designed and constructed:
Project I: thickening and dewatering facility (US $30,000,000)
Project II: new headworks facility and new primary treatment facility to replace the old inefficient facilities (US $70,000,000)
Project III: three-stage thermophilic anaerobic digestion facility (US $200,000,000)
These 3 projects are among the world's largest of their kind. Project I have been completed and have been in operation for 3 years. Project II is now in the commissioning phase. Project III will be commissioned in early 2016.
EXPANSION AND UPGRADE–BASIC DESIGN DATA
Table 1 summarizes the major design parameters for the three projects mentioned above.
SHAFDAN upgrade and expansion: major design parameters
Parameter . | Unit . | Value . |
---|---|---|
Design Year | year | 2030 |
Average Annual Flow | m3/d | 500,000 |
Peak Hour Flow | m3/sec | 12 |
BOD Load | t/d | 200 |
TSS Load | t/d | 200 |
Primary Sludge – max. month | m3/d | 2,500 |
Primary Sludge – max. month | t/d | 110 |
WAS – max. month | m3/d | 24,300 |
WAS – max. month | t/d | 170 |
Parameter . | Unit . | Value . |
---|---|---|
Design Year | year | 2030 |
Average Annual Flow | m3/d | 500,000 |
Peak Hour Flow | m3/sec | 12 |
BOD Load | t/d | 200 |
TSS Load | t/d | 200 |
Primary Sludge – max. month | m3/d | 2,500 |
Primary Sludge – max. month | t/d | 110 |
WAS – max. month | m3/d | 24,300 |
WAS – max. month | t/d | 170 |
Project I: thickening and dewatering facility
As the first stage in the implementation to discontinue the discharge of sludge to the sea, a thickening and dewatering facility was constructed and has been in operation for several years.
WAS thickening
WAS thickening: major design parameters (max. month)
Parameter . | Unit . | Value . |
---|---|---|
Solids feed rate | t/d | 170 |
WAS solids concentration | % | 0.7 |
WAS feed rate | m3/d | 24,300 |
Thickened WAS solids concentration | % | 5 |
Thickened WAS flow | m3/d | 3,400 |
Thickener type and make | GBT | EMO; 3.5-m belt width |
Installed machines | No. | 11 (including standby) |
Parameter . | Unit . | Value . |
---|---|---|
Solids feed rate | t/d | 170 |
WAS solids concentration | % | 0.7 |
WAS feed rate | m3/d | 24,300 |
Thickened WAS solids concentration | % | 5 |
Thickened WAS flow | m3/d | 3,400 |
Thickener type and make | GBT | EMO; 3.5-m belt width |
Installed machines | No. | 11 (including standby) |
Digested sludge dewatering
The sludge dewatering design parameters are presented in Table 3.
Digested sludge dewatering: major design parameters (max. month)
Parameter . | Unit . | Value . |
---|---|---|
Solid feed rate – Conc. | t/d–% | 170–2.9 |
Digested sludge feed rate | m3/d | 5,900 |
Solid concentration in dewatered sludge cake | % | 20–25 |
Dewatered sludge cake mass | t/d | 850–680 |
Centrifuges type and make | Decanter | Alfa Laval Aldec G2–120 |
Installed machines | No. | 6 (including standby) |
Parameter . | Unit . | Value . |
---|---|---|
Solid feed rate – Conc. | t/d–% | 170–2.9 |
Digested sludge feed rate | m3/d | 5,900 |
Solid concentration in dewatered sludge cake | % | 20–25 |
Dewatered sludge cake mass | t/d | 850–680 |
Centrifuges type and make | Decanter | Alfa Laval Aldec G2–120 |
Installed machines | No. | 6 (including standby) |
Dewatered sludge cake pumping
The dewatered sludge cake, at 20 to 25% solids concentration, is pumped by special high-pressure PC pumps (one pump per decanter) to a nearby truck loading facility through 300 mm diameter, 120 m long discharge pipes (one pipe per pump). The maximum discharge pressure in the system is 36 bars. In the event that excessive pressure is developed and detected, lubrication pumps automatically reduce the pressure to normal values. The dewatered sludge pumping design parameters are presented in Table 4.
Dewatered sludge pumps: major design parameters (max. month)
Parameter . | Unit . | Value . |
---|---|---|
Dewatered sludge feed rate (per pump) | m3/hr. | 10 to 15 |
Dewatered sludge solids concentration | % | 20 to 25 |
Type and make | PC | Seepex THE 70-48 |
Installed machines | No. | 6 |
Parameter . | Unit . | Value . |
---|---|---|
Dewatered sludge feed rate (per pump) | m3/hr. | 10 to 15 |
Dewatered sludge solids concentration | % | 20 to 25 |
Type and make | PC | Seepex THE 70-48 |
Installed machines | No. | 6 |
Project II: new headworks and primary clarifiers
Diversion chamber and new sewer aqueduct
The influent sewer consists of 2 pipes, each of 2.7 m internal diameter, pre-fabricated in segments, and based on special pile foundations.
Headworks
The headworks design parameters are presented in Table 5.
Headworks: major design parameters
Parameter . | Unit . | Value . |
---|---|---|
Design Peak Hour Flow | m3/sec | 12 |
Very coarse screens | ||
Installed units | No. | 4 |
Design flow through each | m3/sec | 4 |
Channel width | M | 3.2 |
Screen opening | mm | 100 |
Screenings conveyance | Belt conveyor | |
Type and make | rake screen | Huber Rake Max |
Coarse screens | ||
Installed units | No. | 4 |
Design flow through each | m3/sec | 4 |
Channel width | m | 3.2 |
Screen opening | Mm | 20 |
Screenings conveyance | Screw conveyor | |
Type and make | rake screen | Huber Rake Max |
Fine screens | ||
Installed units | No. | 6 |
Design flow through each | m3/sec | 2.4 |
Channel width | M | 2.4 |
Screen opening | mm | 6 (perforated plate) |
Screenings conveyance | Water trough, chopping, pumping | |
Type and make | Perforated | Huber EscaMax |
Grit traps | ||
Installed units | No. | 8 |
Design flow through each | m3/sec | 2.7 |
Chamber diameter | m | 7 |
Grit conveyance | Slurry pumping | |
Type and make | vortex | Jones & Atwood |
Parameter . | Unit . | Value . |
---|---|---|
Design Peak Hour Flow | m3/sec | 12 |
Very coarse screens | ||
Installed units | No. | 4 |
Design flow through each | m3/sec | 4 |
Channel width | M | 3.2 |
Screen opening | mm | 100 |
Screenings conveyance | Belt conveyor | |
Type and make | rake screen | Huber Rake Max |
Coarse screens | ||
Installed units | No. | 4 |
Design flow through each | m3/sec | 4 |
Channel width | m | 3.2 |
Screen opening | Mm | 20 |
Screenings conveyance | Screw conveyor | |
Type and make | rake screen | Huber Rake Max |
Fine screens | ||
Installed units | No. | 6 |
Design flow through each | m3/sec | 2.4 |
Channel width | M | 2.4 |
Screen opening | mm | 6 (perforated plate) |
Screenings conveyance | Water trough, chopping, pumping | |
Type and make | Perforated | Huber EscaMax |
Grit traps | ||
Installed units | No. | 8 |
Design flow through each | m3/sec | 2.7 |
Chamber diameter | m | 7 |
Grit conveyance | Slurry pumping | |
Type and make | vortex | Jones & Atwood |
Primary clarifiers
Primary clarifiers: major design parameters
Parameter . | Unit . | Value . |
---|---|---|
Design peak hour flow | m3/sec | 12 |
Number of clarifiers | No. | 20 (19 + 1 standby) |
Clarifier tankage description | ||
Length | m | 45 |
Width | m | 12 |
SWD | m | 3.5 to 4 |
Floor slope | % | 1 |
Area – per clarifier | m2 | 540 |
Total area | m2 | 10,800 |
Sludge hoppers per tank | No. | 4 |
Collector type and make | Chain and flights | Finnchain |
Design parameters | ||
Average overflow rate | m3/m2/day | 46 |
Max. overflow rate | m3/m2/hr. | 4.0 |
Performance – max. month | ||
TSS removal efficiency | % | 52 to 55 |
BOD removal efficiency | % | 35 |
Primary sludge-dry matter | kg/day | 110,000 |
Primary sludge-flow | m3/day | 2,500 |
Sludge pumping | ||
No. of units – total | No. | 20 |
Type and capacity | PC, 14 l/sec, VFD | |
Scum removal | ||
Scum collection system | Elec. operated slotted pipe. Scum screening-compactor | |
Scum compaction |
Parameter . | Unit . | Value . |
---|---|---|
Design peak hour flow | m3/sec | 12 |
Number of clarifiers | No. | 20 (19 + 1 standby) |
Clarifier tankage description | ||
Length | m | 45 |
Width | m | 12 |
SWD | m | 3.5 to 4 |
Floor slope | % | 1 |
Area – per clarifier | m2 | 540 |
Total area | m2 | 10,800 |
Sludge hoppers per tank | No. | 4 |
Collector type and make | Chain and flights | Finnchain |
Design parameters | ||
Average overflow rate | m3/m2/day | 46 |
Max. overflow rate | m3/m2/hr. | 4.0 |
Performance – max. month | ||
TSS removal efficiency | % | 52 to 55 |
BOD removal efficiency | % | 35 |
Primary sludge-dry matter | kg/day | 110,000 |
Primary sludge-flow | m3/day | 2,500 |
Sludge pumping | ||
No. of units – total | No. | 20 |
Type and capacity | PC, 14 l/sec, VFD | |
Scum removal | ||
Scum collection system | Elec. operated slotted pipe. Scum screening-compactor | |
Scum compaction |
Project III: thermophilic anaerobic digestion facility
The digesters facility consists of:
8 sludge screens; 6 various sludge tanks
8 pumped-mixed thermophilic digesters
Heat-exchangers and cooling systems
Gas treatment facilities; 5 waste gas burners
Membrane holding tank
8 co-generation unit
The anaerobic digester design parameters are presented in Table 7.
Anaerobic digesters: major design parameters (max. month)
Parameter . | Unit . | Value . |
---|---|---|
Blended sludge | ||
Flow | m3/d | 5,900 |
TSS load | kg/d | 280,000 |
VSS load | kg/d | 220,000 |
Solids concentration | % | 4.7 |
Sludge screening | ||
Number | No. | 8 |
Max. flow per unit | m3/hr. | 68 |
Screening opening | mm | 5 |
Thermophilic digesters | ||
Number (Stage 1/2/3) | No. | 6/1/1 |
Volume (each) | m3 | 13,200 |
Volume (total) | m3 | 105,800 |
Inner diameter | m | 34 |
SWD | m | 14.4 |
Operating temp. | C | 57 |
HRT | days | 18 |
Mixing system | Pumped mixing | |
Mixing pumps number | No. | 24 (16 + 8 standby) |
VSS reduction | % | ≥ 50% |
Biogas production | m3/day | 114,000 |
Biogas storage and treatment | ||
Gas storage type | Dual membrane | |
Storage effective volume | m3 | 4,300 |
Treat. for H2S removal | Biological (H2S ≤ 50 ppm) | |
Burners, number–capacity | No.–m3/hr. | 5–6,300 |
Burner type | Enclosed stack | |
Co-generation | ||
Number of units | No. | 8 (7 operating, 1 in service) |
Electrical output–each | kW | 1,400 |
Electrical output–total | kW | 9,800 |
Thermal output–each | kW | 1,400 |
Thermal output–total | kW | 9,800 |
Package | Containerized | |
Type and Make | CHP | Jenbacher JMC420 |
Siloxane removal | Activated carbon |
Parameter . | Unit . | Value . |
---|---|---|
Blended sludge | ||
Flow | m3/d | 5,900 |
TSS load | kg/d | 280,000 |
VSS load | kg/d | 220,000 |
Solids concentration | % | 4.7 |
Sludge screening | ||
Number | No. | 8 |
Max. flow per unit | m3/hr. | 68 |
Screening opening | mm | 5 |
Thermophilic digesters | ||
Number (Stage 1/2/3) | No. | 6/1/1 |
Volume (each) | m3 | 13,200 |
Volume (total) | m3 | 105,800 |
Inner diameter | m | 34 |
SWD | m | 14.4 |
Operating temp. | C | 57 |
HRT | days | 18 |
Mixing system | Pumped mixing | |
Mixing pumps number | No. | 24 (16 + 8 standby) |
VSS reduction | % | ≥ 50% |
Biogas production | m3/day | 114,000 |
Biogas storage and treatment | ||
Gas storage type | Dual membrane | |
Storage effective volume | m3 | 4,300 |
Treat. for H2S removal | Biological (H2S ≤ 50 ppm) | |
Burners, number–capacity | No.–m3/hr. | 5–6,300 |
Burner type | Enclosed stack | |
Co-generation | ||
Number of units | No. | 8 (7 operating, 1 in service) |
Electrical output–each | kW | 1,400 |
Electrical output–total | kW | 9,800 |
Thermal output–each | kW | 1,400 |
Thermal output–total | kW | 9,800 |
Package | Containerized | |
Type and Make | CHP | Jenbacher JMC420 |
Siloxane removal | Activated carbon |
CONCLUSIONS
The SHAFDAN has been upgraded during the last 8 years to provide a biosolids management program producing Class A biosolids. Three major projects are involved in this plan: Project I – new sludge thickening and dewatering facility; Project II – new headworks facility and new primary clarifiers which provide a necessary treatment stage for a future expansion of the plant treatment capacity; Project III – a 3-stage thermophilic digestion facility. The total construction cost of these projects is approximately 300 million US dollars. These projects will provide the SHAFDAN with a state-of-the-art, long-term, land-based biosolids management system producing Class A biosolids.
As the plant is approaching its design capacity, the SHAFDAN is now preparing for the expansion of the liquid stream capacity to 500,000 m3/day. This expansion, planned for the next 10 years, involves a construction of new BNR bioreactors and final clarifiers as well as side-stream treatment of the dewatering centrate to reduce the nutrient return load to the secondary treatment process.