This article introduces the evaluation of mining conditions under pore aquifer and presents four control techniques on pore water, i.e. retaining safety coal (rock) pillars to resist water, sand, and collapse; draining bottom pore aquifer in Quaternary strata to lower underground water level; presplitting hard overlying rock by blasting to inhibit growths of water-conductive fissures; manually caving the roof strata over the steep sloping coal seam by extruding blast to prevent water-resistant coal pillars from caving. This article is to provide references for countries confronting similar problems and to facilitate international discussions on pore water control.

China has the largest coal output in the world, with an annual production of over 3 billion tons, three times that of the US. According to the ‘BP Statistical Review of World Energy 2010–2014’, China's coal output accounted for nearly half of world production while the US only 10% (Figure 1).
Figure 1

Coal outputs of China and the USA.

Figure 1

Coal outputs of China and the USA.

Close modal

Looking at the distribution of known coal resources in the mainland China, the over 500,000 km2 of coal-bearing area is divided into six regions, namely North China Carboniferous-Permian, northeast and northwest Jurassic, South China late Permian, Tibet-West Yunnan Mesozoic, and Taiwan Paleogene (Fan 2003). The complicated hydrogeological conditions are inherent with as many as 30 common types of water hazards. With over 60 years of research and practice, certain types of water hazards, such as sandstone aquifers in coal seam, have been effectively contained by maturing technologies; while some other types, such as pore water, are frequent causes of water disasters in coalmines. On Dec. 19, 1977, a catastrophic disaster caused by pore water in the Cenozoic Quaternary loose strata in Meihe coalmine, Liaoyuan of Jilin Province, burst out 56,520 m3 of water and sand and killed 64 people (Wu et al. 2013a, 2013b). On May 31, 2001, Shanwan coalmine, in Shendong of northwest coal-bearing region, water-sand bursts from Quaternary pore aquifer silted about 400 m roadway, registering 4,700 m3 of sand and 50 ∼ 60 m3/h max water inrush. The mining area was closed for 20 days and suffered economic losses of over RMB 1.4 million (Gui et al. 2015).

Most of the coal seam in China are covered by thick and giant thick Cenozoic Quaternary loose strata. The north China coal-bearing area, in particular, has overlying Cenozoic Quaternary loose strata of as thick as 250 m to 500 m on top of the coal seam. Generally, loose strata breed multiple layers of pore aquifers, the bottom of which (hereinafter referred as the bottom aquifer) is in direct contact with coal seam. The bottom aquifer is the immediate water menace to coal mining and the main outlet for water-sand bursts (Zhang et al. 2013; Deng et al. 2014; Xu et al. 2015b). In order to prevent water burst from the bottom aquifer in Quaternary loose strata, safety coal (rock) pillars of 80 m are retained as precautions. But these pillars stock substantial tonnage of coal, which is estimated to be in tens of billions.

To ensure safety mining under pore aquifer, China coalmines intensified researches on pore water, one of the major water hazards. The achievements will undoubtedly (Wang et al. 2013; Gui et al. 2015; Xu et al. 2015a; Zhang 2015a) contribute to the global efforts on pore water control.

Water disasters in coalmines border on two factors: water source and conduits. In the scenario of pore water accidents, the water source is in the Quaternary bottom aquifer and the conduits include pre-existing conduits (water-conductive faults, etc.) and man-made conduits (mining-caused rock caving and water-conductive fissures, etc.). The bottom aquifer supplies water, sand, and hydraulic pressure. Pre-existing fissures and mining fissures serve as carriers. Thus, the key to pore water control is to control water source and conduits (Duan 2013; Zhang 2015b; Zhao & Ren 2015).

Pre-mining evaluation shall include the followings to allow for effective pore water control plans.

  1. Hydrogeological properties of Quaternary bottom aquifer, such as replenishment, run-off, drainage, water abundance, waterhead pressure, and physical composition, etc., as well as explicit opinion on the necessity of water recycling.

  2. Lithological properties of weathering bedrock, thickness and degree of weathering.

  3. Lithological properties of overlying rock over mining coal seam and its composition, etc.

  4. Mining techniques and roof management.

At present, the most popular pore water control measures in China coalmines (Gui & Hu 1997; Xu et al. 2010) include the followings:

  • (i) Retaining safety coal (rock) pillars. In the light of the evaluation results, safety coal (rock) pillars of three types, water-resistant, sand-resistant, and anti-collapse, can be retained to contain water-sand bursting into mining workface from Quaternary bottom aquifer and weathering bedrock.

  • (ii) Draining pore aquifer. Based on the analysis of Quaternary bottom aquifer, draining plan shall evaluate drainage effectiveness and adopt the proper type of safety coal (rock) pillar accordingly.

  • (iii) Improving mining techniques and roof management (such as fill mining, presplitting blast, etc.) to avoid water-sand bursting into mining workface from Quaternary bottom aquifer and weathering bedrock.

Retaining safety coal (rock) pillars

There are three types of safety coal (rock) pillars for mining under pore aquifers: water-resistant, sand-resistant, and anti-collapse (Liu et al. 2006; Cao et al. 2008), as shown in Figure 2.
  1. Water-resistant coal (rock) pillars. If the bottom aquifer of Quaternary loose strata has high water abundance and refills sufficiently or when there is a demand to recycle underground water, water-resistant coal (rock) pillars must be retained at a height by HwHf + S. Hf represents the maximum height of the water-flowing fractured zone. S represents the thickness of the protective strata (usually 2–4 times of mining thickness (MCI 2000; Shang et al. 2015), as shown in Figure 2(a).

  2. Sand-resistant coal (rock) pillars. If the bottom aquifer of Quaternary strata has low water abundance and refills insufficiently or when there is no demand as to recycle underground water, sand-resistant coal (rock) pillars can be retained at a height by HsHc + S. Hc represents the maximum height of the caving zone as in Figure 2(b). Its role is to allow the water-flowing fractured zone to partially implicate bottom aquifer while keep caving zone away from it, so as to prevent the sand bursting from bottom aquifer into mining panel.

  3. Anti-collapse coal (rock) pillars. If the bottom aquifer of Quaternary loose strata has poor water abundance with static reserve (i.e. without extra water supply), anti-collapse coal (rock) pillars can be retained at a height by Hcf. This will allow the water-flowing fractured zone to implicate bottom aquifer and the caving zone to approach it as well (Figure 2(c)). Its height Hcf is commensurate to the maximum height Hc of the caving zone.

Figure 2

Types of safety coal (rock) pillars.

Figure 2

Types of safety coal (rock) pillars.

Close modal

Draining quaternary bottom aquifer

Water-sand inrush under pore aquifer is closely correlated with the water pressure in the aquifer. Therefore, using draining techniques to manually lower water level and depressurize pore aquifer is adopted in many coalmines across China.
  1. Case on pre-mining draining. The workface No. 20601 of Daliuta coalmine, Shendong of northwest coal-bearing region, had a dimension of 220 m in width and 2,800 m in length. The bedrock over the 2−2 coal seam had a thickness of 35–45 m. Hydrogeological analysis showed that the coal seam was in close vicinity of the Quaternary pore aquifer which was rated with medium to high water abundance. Water inrush, if were to happen, was estimated at 400 ∼ 600 m3/h. The geological and hydrogeological conditions were prone to inducing water-sand accidents (Li 2004; Du et al. 2013). Countering the natural perils, proactively deployed 2 drainage holes in workface, 8 drainage holes in roadway, 3 observation holes and 1 forced draining hole. Before mining, manual draining was conducted on the pore aquifer for 74 days, resulting in an average water level decrease of 6.3 m and a max of 9.4 m. Total water discharge was as high as 210,000 m3. On Aug. 13, 1995, after test mining on the workface, the first manual caving incurred water inrush of 28 m3/h and maximized at 50.18 m3/h on the Aug. 18. No further water-sand inrush accident.

  2. Case on concurrent mining and draining. In the north China coal-bearing region, the No. 810 mining panel, in Luling coalmine of Huaibei, had a coal reserve of over 5 million tons under the threat of Quaternary pore water. Hydrogeological prospecting concluded that the bottom aquifer was predominated with static water and could be drained up. To this end, a number of drilling sites were arranged along the ventilation roadway, mechanical roadway, and open-off cut (Figure 3). Each site was organized with 3 draining holes (Figure 4) to extract water from Quaternary pore aquifer during mining (Tu et al. 2004; Chen et al. 2014; Gui et al. 2015).

Figure 3

Draining sites in workface No. 8101, Luling coalmine.

Figure 3

Draining sites in workface No. 8101, Luling coalmine.

Close modal
Figure 4

Plan of end holes in relation to bottom aquifer in workface No. 8101, Luling coalmine.

Figure 4

Plan of end holes in relation to bottom aquifer in workface No. 8101, Luling coalmine.

Close modal

Technical parameters as follows:

  1. Draining site: L × W × H = 4 m × 3 m × 3 m, at an interval spacing of 50 m and supported by U-sized steel structure;

  2. Draining hole diameter: φ75 mm

  3. Elevation of draining hole: 50–60°

  4. End hole locations (Figure 4): the end holes corresponding to the three draining holes in each site are located in the following fashion: 1# inside the workface, 2# outside the workface, 3# right above the roadway.

  5. Drilling depth: 20–40 m as end holes reach mid-way inside the bottom aquifer.

The No. 810 mining panel, taking example after No. 8101 workface (Figure 3), set up 18 drilling sites and 54 draining holes. In 3-month time, total water discharge amounted to 3,000 m3, leaving bottom aquifer almost drained up. In later mining operation, there were occasional sand bursts locally but didn't escalate into major water-sand accidents.

Inhibiting growths of water-conductive fissures by presplitting blast

When mining under pore aquifers, pore water would not evolve into a water disaster if the water-resistant coal (rock) pillars are high enough that the water-flowing fractured zone cannot reach the aquifer. But there have been exceptions. Qidong coalmine in Huaibei of Anhui Province of north china coal-accumulation zone went into production in Nov. 2001 with a test mining on the first mining panel 3222 on Nov. 5. As mining proceeded to 42 m, the pore water in the bottom aquifer of Quaternary loose strata rushed out and continuously grew up to 1,520 m3/h within one day. The entire coalmine was flooded and cost hundreds of millions of economic losses. For panel 3222, the water-resistant coal (rock) pillars were designed for a height of 65 m, whereas the actual height (Hw') was 70 m as verified afterwards by drilling results.

Follow-up tests and studies revealed that the cause of the accident was the special structure of the rock strata over the roof coal seam. The overlying rock strata, 70 m in thickness, were composed of multiple layers of medium and fine grained sandstones, the two of which were of similar hardness. The water-flowing fractures caused by mining extended upwards so high (Zhang et al. 2014; Guo 2015; Song 2015) as to implicate the pore aquifer in the bottom aquifer of Quaternary loose strata (Figure 5), thus giving rise to the severe water accident.
Figure 5

Upward movement of mining fractures in overlying hard rock strata.

Figure 5

Upward movement of mining fractures in overlying hard rock strata.

Close modal
Generally, the mining fractures in soft rock strata extend upwards only by small margins. Hard as the rock strata in Qidong coalmine, it is necessary to precondition the rock strata before mining. By presplitting (Xu et al. 2004; Wu et al. 2013b) the first layer of hard rock stratum, which is the closest to coal seam (Figure 6), and creating a man-made soft rock stratum, the upward extension can be contained and the fractures cannot reach the bottom aquifer of Quaternary loose strata. This technique produces favourable results with low cost and low technical difficulties. Its application is being popularized in other coalmines under similar conditions.
Figure 6

Inhibiting upward extension of mining fractures by presplitting.

Figure 6

Inhibiting upward extension of mining fractures by presplitting.

Close modal

Manual caving by extruding blast

Goaf space formed by mining steep sloping coal seam, as roof rock cannot be caved while being mined (Figure 7(a)), can only be refilled by caving the coal seam stocked in water-resistant coal pillars. Such caving (Figure 7(b)), if not controlled properly, may cause water-sand inrush from the overhead pore aquifer, resulting in water-sand inrush accidents and even geological disasters at ground level, such as subsidence (Deng et al. 2013; Yan et al. 2015).
Figure 7

Water-sand inrush accident caused by water-resistant coal pillar caving.

Figure 7

Water-sand inrush accident caused by water-resistant coal pillar caving.

Close modal

To proactively control water-resistant coal pillar caving, manual caving by extruding blast (Shen & Wen 2000) is applied in some coalmines and has harvested favourable results in practice. This technique is to blast the overhead rock and sever or shatter the rock to fill the goaf space, so as to prevent water-resistant coal pillars caving.

In an ideal scenario, the goaf space is filled up with rocks produced by manual caving right before the water-resistant coal pillars cave in. In practice, however, due to gravity and stress concentrated on the pillars, the coal pillars would fall by parts before manual caving, which would take up the space allowed for blast caving. Therefore, it is necessary to excavate a rock roadway parallel to the high roadways (ventilation or mechanical roadways) at a distance of 8–10 m. Between the two roadways, create one cross hole every 15 m by blasting (Figure 7(c)) (Shen & Wen 2000). Extruding blast is mostly conducted in the cross holes (Figure 8) (Shen & Wen 2000). The tremendous impact generated by explosion extrudes the loose parts inside the goaf, which will recede or consolidate to stop the water-resistant coal pillars from sliding downward, thereby avoiding water-sand inrush from the pore aquifer. Using multi-row blast holes at millisecond intervals will generate more powerful force.
Figure 8

Extruding blast.

Figure 8

Extruding blast.

Close modal

Based on above analysis, conclusions can be drawn as follows:

  1. In pore water accidents, the inrush water-sand and hydraulic pressure are sourced from pore aquifer through pre-existing and mining fissures as the inrush conduits. Therefore, the key to tackling pore water hazard is to control the water source and inrush conduits.

  2. With accurate evaluation of mining condition, main techniques to contain pore water hazard include:

    • (i) Retaining safety coal (rock) pillars of verifiable heights to separate Quaternary bottom aquifer from mining workface. The pillars can resist water and sand and prevent collapse.

    • (ii) Draining Quaternary bottom aquifer before mining or during mining to lower waterhead level and decrease hydraulic pressure.

    • (iii) Presplitting hard overlying rock by blasting to inhibit growths of water-conductive fissures.

    • (iv) For mining steep sloping coal seam, manual caving by extruding blast to prevent coal pillar caving and water-sand inrush accidents.

This work was supported by the National Natural Science Foundation of China (41373095) and Anhui Science and Technology Breakthrough Project (1501zc04048).

Cao
A. Y.
Dou
L. M.
Chen
G. X.
Gong
S. Y.
Wang
Y. G.
Li
Z. H.
2008
Focal mechanism caused by fracture or burst of a coal pillar
.
Journal of China University of Mining & Technology
18
(
2
),
153
158
.
Deng
Z. X.
Li
Z. J.
Qin
Y. W.
2013
Study on preventing top coal layer caving due to advancing in the steep and very soft coal seam
.
Hydraulic Coal Mining & Pipeline Transportation
(
3
),
12
13
.
Deng
Q. H.
Cao
J. Y.
Zhang
L. P.
Lin
Y. X.
Zhang
D. D.
2014
The Bayesian discrimination model for sources of mine water inrush based on principal components analysis
.
Hydrogeology & Engineering Geology
41
(
6
),
20
24
.
Du
F.
Bai
H. B.
Huang
H. F.
Jiang
G. H.
2013
Mechanical analysis of periodic weighting of main roof in longwall top coal caving face with thin bedrock roof
.
Journal of China University of Mining &Technology
42
(
3
),
362
369
.
Duan
J. J.
2013
The predictive parsing of the development height of seam mining crack zone based RFPA2D
.
Journal of Hebei University of Engineering (Natural Science Edition)
30
(
2
),
76
83
.
Fan
T. J.
2003
A Comprehensive Guidebook to Water Control in Coalmines
.
Jilin Audio-Visual Press
,
Jilin
,
China
, pp.
3
31
.
Gui
H. R.
Hu
Y. B.
1997
Calculation Methods of Stress Analysis for Reasonable Retainment of Water-Resisting Coal (Rock) Pillars
.
China Coal Industry Publishing Home
,
Beijing
,
China
, pp.
50
80
.
Gui
H. R.
Chen
L. W.
Song
X. M.
Tu
M.
Qin
Y.
2015
Research on Water and Sand Control for Coalmining in the Shallow Part of Areas Covered by Thick Loose-Bed
.
China University of Mining and Technology Press
,
Xuzhou
,
China
, pp.
8
12
,
306–320
.
Guo
Z.
2015
Causes of support crushing and water inrush at 7121 working face in Qidong coalmine and its control
.
China Coal
41
(
2
),
96
97
.
Li
L.
2004
Water hazard control in Shendong coal mining area
.
Coal Geology & Exploration
32
(
4
),
128
130
.
Liu
Y. J.
Mao
S. J.
Yao
J. M.
Jiang
Y. F.
2006
Research on 3d modeling and visualization of coal pillars for surface protection
.
Journal of China University of Mining & Technology
16
(
3
),
254
257
.
MCI (Ministry of Coal Industry)
2000
Protocols for Coal Pillar Retainment in Major Roadways and Compressed Coal Mining Under Buildings, Water Bodies, and Railways
.
China Coal Industry Publishing Home
,
Beijing
,
China
, pp.
225
240
.
Shang
Q.
Zhang
H. W.
Li
N.
Guo
F. P.
2015
Methods to retain safety coal (rock) pillars under thin bedrock in giant thick loose strata
.
Energy Technology and Management
40
(
2
),
114
116
.
Shen
B. H.
Wen
X. K.
2000
Research on water-resistant coal pillar caving control when mining steep sloping coal seam under water bodies
.
Coal Mining Technology
(
1
),
44
46
.
Song
M. K.
2015
Study on Development Law of Coal Seam Mining ‘Infiltration Zone’ of Qidong Coalmine near the Unconsolidated Layer
.
Anhui University of Science and Technology
,
Huainan
,
China
, pp.
35
66
.
Tu
M.
Gui
H. R.
Li
M. H.
Li
W.
2004
Testing study on mining of waterproof coal pillars in thick loose bed and thick coal seam under ultrathin overlying strata
.
Chinese Journal of Rock Mechanics and Engineering
23
(
20
),
3494
3497
.
Wang
X. W.
Sui
W. H.
Dong
Q. H.
Hu
W. W.
Gu
S. X.
2013
Closure effect of mining-induced fractures under sand aquifer and prediction of overburden failure due to re-mining
.
Journal of China Coal Society
38
(
10
),
1728
1734
.
Wu
Q.
Zhao
S. Q.
Dong
S. N.
Li
J. S.
2013a
Handbook to Coalmine Water Control
.
China Coal Industry Publishing Home
,
Beijing
,
China
, pp.
28
40
.
Wu
Z. D.
Xue
A. M.
Cao
D. T.
2013b
Contact algorithm of 3d mechanical finite element modeling for separation of overburden layers and its application
.
Journal of Geomechanics
19
(
3
),
325
333
.
Xu
J. L.
Qian
M. G.
Jin
H. W.
2004
Study and application of bed separation distribution and development in the process of strata movement
.
Chinese Journal of Geotechnical Engineering
26
(
5
),
632
636
.
Xu
P.
Zhou
Y. J.
Zhang
M. X.
Li
J. W.
Cao
Z. Z.
2015a
Fracture development of overlying strata by backfill mining under thick alluvium and thin bedrock
.
Journal of Mining & Safety Engineering
32
(
4
),
617
622
.
Xu
Y. C.
Zhang
Q.
Xie
J. G.
Dong
J. P.
2015b
Water inrush analysis of 7199 fully mechanized working face in xuzhuang coal mine
.
Journal of Liaoning Technical University (Natural Science)
34
(
2
),
145
149
.
Xu
Z. M.
Sun
Y. J.
Dong
Q. H.
Zhang
G. W.
Li
S.
2010
Predicting the height of water-flow fractured zone during coal mining under the Xiaolangdi Reservoir
.
Mining Science and Technology (China)
20
(
3
),
434
438
.
Yan
Y. G.
Dai
H. Y.
Wang
Z. W.
Zhu
G. W.
Chen
H. Z.
Xu
C.
2015
Study on failure characteristics and normal height of caving zone due to steep seam mining
.
Coal Science and Technology
43
(
4
),
23
26
.
Zhang
Y. J.
2015a
Technology of dewatering and controlling for high strength of mining under deep composite water in Mengxi
.
Metal Mine
44
(
4
),
74
78
.
Zhang
Z. X.
2015b
Analysis on mining technology condition of coal resource in Anjiazhuang field of lintai mining area
.
Coal Engineering
47
(
3
),
11
16
.
Zhang
X. M.
Jia
K. M.
Jiang
Z. S.
2013
Study on prevention method and analysis of water inrush source in construction mine
.
Coal Science and Technology
41
(
8
),
106
109
.
Zhang
H. W.
Zhu
Z. J.
Huo
L. J.
Chen
Y.
Huo
B. J.
2014
Overburden failure height of superhigh seam by fully mechanized caving method
.
Journal of China Coal Society
39
(
5
),
816
821
.
Zhao
D.
Ren
Q. C.
2015
Hydrogeological condition and mine filling condition analyses in Jixian-Dongying mining area
.
Coal Geology of China
27
(
12
),
60
62
.