This paper is about the set-up and start-up of a decentralized anaerobic pilot plant for producing domestic service water from domestic wastewater. The plant consists of a two-stage anaerobic digestion process for degrading organic matter and a third-stage for ammonium removal using the Anammox process. Each reactor was started independently with synthetic wastewater of stage-specific composition. They were then fed incrementally with municipal wastewater (MWW). The average removal efficiency of the two-stage digestion process operated with 100% MWW was 62% with 24-hour retention time. The Anammox stage achieved a maximum ammonium removal efficiency of 95% with 100% MWW, if the NO2-N to NH4-N ratio was set at 1.14. The plant was operated for 200 days. The average removal efficiencies were 81% for COD and 96% for NH4-N, with average treated effluent concentrations of 39 mg-COD/l and 1 mg-NH4-N/l. Thus the self-defined service water limits of 75 mg-COD/l and 10 mg-NH4-N/l were achieved easily.

Effective household water cycles are important for reducing water use and providing potable water. Treating and recycling domestic wastewater for reuse for non-potable domestic purposes like flushing toilets or washing cloths is a promising approach. Up to 60% of household potable supplies can be replaced by non-potable water (Herbst 2008). In this context decentralized systems are required that treat wastewater on site, avoiding both the need to transport water long distances and the related maintenance costs. Decentralized plants should be designed to be space efficient and odourless, as well as easy to use, so that simple operating instructions are sufficient (Herbst 2008; Massoud et al. 2009).

Due to low energy consumption, low sludge production, low space requirements and the production of useable energy as biogas, anaerobic digestion is particularly attractive for organic removal in decentralized wastewater treatment systems (Olsson et al. 2005; Batstone 2006). Depending on whether the process design comprises one- or two- stage operation, and the operating conditions, including temperature and pH, and the reactor types, organic removal efficiency in anaerobic digestion can be between 25 and 90%. Kobayashi et al. (1983), for example, achieved 73% organic removal efficiency for low strength domestic wastewater (288 mg-COD/l) using a lab-scale aerobic filter with a capacity of 11 ml/min. With a 120 liter upflow anaerobic sludge blanket reactor, Barbosa & Sant'Anna (1989) achieved 74% average organic removal treating raw domestic sewage (627 mg-COD/l) with 4 hr HRT. Donoso-Bravo et al. (2009) treated low-strength wastewater (500 mg-COD/l) with a high proportion of particulate organic matter (70%, COD basis) using a two-stage system consisting of anaerobic sequencing batch reactors. 69 and 50% COD removal efficiencies were achieved for organic loading rates of 630 and 1,220 mg-COD/l.

Carbamide, present in domestic wastewater due to urine, requires an additional treatment step after anaerobic digestion to reduce the ammonia concentration. Anaerobic ammonium oxidation (Anammox) is an innovative possibility for ammonia removal, in which it is converted to elementary nitrogen anaerobically by using nitrite (van de Graaf et al. 1996; Ma et al. 2016). Fux et al. (2002) treated wastewater containing about 650 mg-NH4-N/l in a sequencing batch reactor with a capacity of 2 m3. Nitrogen removal efficiencies of 85 to 99% and reduction rates between 1,100 and 1,200 mg-NH4-N/l/d were achieved. Van der Star et al. (2007) successfully started a 70 m3 reactor treating 10,715 mg-NH4-N/l/d using 5 m3 of biomass from an enrichment reactor. Fed with synthetic wastewater (SWW) similar to that used by van De Graaf et al. (1996) at 35°C, the enrichment reactor achieved conversion rates of about 3,000 mg-NH4-N/l/d. Nevertheless, practical application of the Anammox process is still challenging. One big challenge is the slow growth rate of the microorganisms, with a doubling time of 7 to 14 days causing slow start-up (Strous et al. 1998; van der Star et al. 2007; Ali et al. 2015).

Anaerobic digestion and ammonium oxidation were used mostly for highly polluted wastewaters showing good degradation performances (van de Graaf et al. 1996; Kalogo & Verstraete 2001; Fux et al. 2002; Foresti et al. 2006; van der Star et al. 2007). Adaptation of the microorganisms to low concentration wastewaters is an important challenge in making anaerobic processes suitable for domestic wastewater treatment (Ali et al. 2015; Vega De Lille 2015).

This paper is about the set-up and start-up of a decentralized anaerobic pilot plant combining anaerobic digestion and Anammox-based processes to treat low-strength domestic wastewater. An aim of this project was to produce household service water from domestic wastewater. In contrast to potable water, service water is not clearly defined or regulated. In this project the service water generated meets the requirements of the German wastewater regulations (AbwV 2016) and the Bavarian bathing waters regulations (BayBadeGewV 2008). The treated water should also be aesthetically attractive. The maximum permitted concentrations for ammoniacal-nitrogen (NH4-N), total nitrogen and phosphorus are 10, 13 and 1 mg/l, respectively. The organic load represented as the COD should not exceed 75 mg-COD/l. As fecal indicator microbes for polluted wastewater, E.coli and enterococci should not exceed concentrations of 900 cfu (colony-forming units)/100 ml and 330 cfu/100 ml (BayBadeGewV 2008; AbwV 2016).

Pilot plant set-up

The pilot plant for this study consists of three biological stages of which the first two, reactors 1 and 2 (R1 & R2), are anaerobic digesters for organic matter. The third stage – reactor 3 (R3) – contains the Anammox-based process to lower ammonium concentrations. The pilot plant was built in the municipal sewage plant at Erlangen, Germany – see Figure 1 – with a design capacity of 2 m3/d. A space efficient design was realized by integrating the process into two, linked, 20 ft containers. With a total floor area of 28 m2 and ceiling height of 2.50 m the plant can be installed easily in apartment building basements.
Figure 1

Decentralized anaerobic pilot plant for treating domestic wastewater to service water quality. It was constructed in the Erlangen communal sewage plant, Germany. It is integrated in two standard containers connected as a single room; floor area 28 m2 and ceiling height 2.50 m.

Figure 1

Decentralized anaerobic pilot plant for treating domestic wastewater to service water quality. It was constructed in the Erlangen communal sewage plant, Germany. It is integrated in two standard containers connected as a single room; floor area 28 m2 and ceiling height 2.50 m.

Close modal

For cost-effectiveness, all three 1,200-liter reactors are cylindrical tanks made of polyethylene. R1 and R3 were designed as batch stirred tank reactors (BSTR), each 1,300 mm tall and of 1,100 mm diameter, giving a filling height-diameter ratio of one. To suspend the microorganisms and homogenize the reactor medium, an axial flow field is induced by stirring in the BSTR. As a result, the suspended bacteria in R1 and R3 must settle before the effluent is pumped to the next process step, in order to guarantee biomass retention. The BSTR outlets are, therefore, about 200 mm above the reactor bottom, providing a retention volume of approximately 200 liters.

Due to the symbiotic nature of the acetogenic and methanogenic microorganisms, a high bacterial density must be ensured in the reactor. R2 is thus a fixed bed reactor (FBR), 2,100 mm tall and 900 mm in diameter. As support media it contains fully 3-D, permeable, BIO-NET® blocks from Norddeutsche Seekabelwerke GmbH. In the FBR, the bacteria remain attached to the fixed bed and down-stream recirculation through it is essential for good distribution.

The microorganisms used in the process are mesophilic, so the temperature must be maintained at between 30 and 40°C (Grady et al. 2011; Vega De Lille 2015). Thus the wastewater must be heated for good degradation performance. A 1,000-liter buffer tank equipped with a heating cartridge is used for pre-heating. It also facilitates start-up of the three reactors, and offers the possibility of buffering between biological processing and post treatment. It is connected to the collector pipe after the communal sewage plant pre-treatment basins, which remove large particles from the wastewater.

From the influent sampling point, 1 m3 per charge of wastewater is pumped to the buffer tank to be heated to 35 °C (process operating temperature). Subsequently, it is transferred to the two-stage organic digestion phase, with hydrolysis and acidogenesis in R1, and acetogenesis and methanogenesis in R2, and thence to R3, where the Anammox process occurs. Finally the treated wastewater is transferred for post-treatment consisting of two slow-sand filters and one activated carbon adsorber, to augment the service water quality by removing suspended solids, microorganisms and residual pollutants like phosphorus. The plant layout is shown in Figure 2.
Figure 2

Process and instrumentation scheme of the plant.

Figure 2

Process and instrumentation scheme of the plant.

Close modal

Plant start-up and testing

On start-up, the reactors were operated separately, initially, to facilitate microorganism adaptation to their new environments. Then, R1 and R2 were linked by replacing the municipal wastewater (MWW) supplemented with additional organic acids at the outlet from R1. Finally R3 was linked in by substituting the artificial wastewater with the effluent from R2.

R1 and R2 were each inoculated with 60 liters of seeding sludge from a two-stage anaerobic digester in Obermichelsbach (Germany), where vegetable waste products like sugar beet residues are degraded and used for sustainable energy production. Both reactors were fed from the start with mechanically pretreated MWW. Degrading predominantly short chain organic acids by acetogenesis and methanogenesis, R2 needed additional substrate until it was connected to the hydrolytic and acidogenic process (phase I). As suggested by Kuba et al. (1990) and Vega De Lille (2015), acetic, propionic and butyric acids were added to R2 in the ratio 2:1:1. As MWW was used from the start, trace elements were not needed. After adaptation, the connection of R1 and R2 was carried out stepwise (phase II). R2's initial influent was 1,000 liters of fresh MWW supplemented with organic acids–as above–it was replaced by 30, 50 and finally 100% effluent from R1. When reactor connection was complete, no additional substrate was required (phase III).

The pH also affects degradation by microorganisms. Lab-scale studies showed that adjusting the pH to the microorganisms' optimum value affects the intermediate products to improve degradation performance. In hydrolysis and acidogenesis the optimum pH is between 4.5 and 6, whereas for acetogenesis and methanogenesis the optimum is around 6.8 to 7.8 (Grepmeier 2002; Vega De Lille 2015). The pH in the pilot-plant was set at the start of each batch in phases I and II to 5.5 in R1 and 7.5 in R2. In R1 it was adjusted by adding approximately 200 ml of hydrochloric acid (15% v/v), in R2 about 700 ml of caustic soda (15 v/v) were added. Daily operation of pilot-scale treatment involves high consumption of auxiliary materials. For cost-effectiveness, degradation performance was determined without pH adjustment from phase III of the start-up onward.

The Anammox-based process in R3 was inoculated with 60 liters of seeding sludge from a de-ammonification (DEMON) reactor in Fulda Gläserzell (Germany). In phase I, SWW, comprising 1,000 liters of tap water mixed with ammonium sulfate (40 mg-NH4-N/l) and sodium nitrite (50 mg-NO2-N/l) was introduced. This was followed by stepwise adaptation to organically degraded MWW from R2 at MWW:SWW ratios of 20:80 (phase II), 50:50 (phase III), and 80:20 (phase IV). In phase V the feed to R3 was 100% MWW. Anammox bacteria are mesophilic and the optimum temperature for them is between 30 and 40°C (van de Graaf et al. 1996; Strous et al. 1998). Further studies, however, demonstrated good degradation at temperatures around 18 to 20°C (Isaka et al. 2007). For this study the temperature in R3 was held between 28 and 35 °C. The pH range for Anammox bacteria is between 6.7 and 8.3 (Strous et al. 1998; Wesoly 2009). As the process step in R2 is in the same pH, no pH adjustment or control is needed.

Once the three reactors had been connected, the pilot plant was tested for 200 days using mechanically pretreated MWW.

Analytics

Both online and offline measurements were carried out to analyze degradation performance. The fluid temperature in all reactors and the buffer tank was monitored online with Pt100 SITRANS TH400 temperature sensors from Siemens AG, Munich, Germany. As noted, fluid temperature is adjusted only once, in the buffer tank, to 35°C. Thereafter it decreases with time in the process units at an average of 1.125°C/hr.

The pH was monitored in all reactors with pHD-S sc Digital Differential pH-sensors from Hach Lange GmbH, Düsseldorf, Germany. Degradation by the Anammox-based process (R3) was analyzed with a 3798-S sc Digital inductive conductivity sensor from Hach Lange GmbH (Düsseldorf, Germany).

To characterize the organic load in the water, the COD was measured offline using a QuickTOC® analyzer from LAR AG, Berlin, Germany.

Nitrogen removal was characterized using various parameters, including the concentrations of ammoniacal-nitrogen (NH4-N), nitrite-nitrogen (NO2-N) and nitrate-nitrogen (NO3-N). The determinations were done with photometric-based analytical test kits from Merck Chemicals GmbH (article-no. NH4-N: 1.00683.0001, NO2-N: 1.14776.0001 and NO3-N: 1.14773.0001).

Two-stage organic digestion start-up

The degradation performance over 24 hr retention time of the two-stage organic digestion during start-up is presented in Figure 3. The supplementary organic acids used during adaptation (phase I), led to higher initial COD concentration in the medium than is usually found in domestic wastewater. Starting with 900 mg-COD/l in batch 1, the total COD removal in 24 hr was about 280 mg-COD/l/d, which corresponds to a removal efficiency of 31%. In batch 2, the removal efficiency increased to 49%, having 699 mg-COD/l in the influent and a total removal of 343 mg-COD/l/d. The 598 mg-COD/l at the start of batch 3 showed total COD-removal of 316 mg-COD/l/d, representing 53% efficiency.
Figure 3

COD removal and removal efficiency with 24-hour retention time, during anaerobic digestion process start-up. Start-up is sub-divided into three phases: (I) microorganism adaptation, (II) connection of R1 and R2, (III) operation of fully connected two-stage anaerobic digestion.

Figure 3

COD removal and removal efficiency with 24-hour retention time, during anaerobic digestion process start-up. Start-up is sub-divided into three phases: (I) microorganism adaptation, (II) connection of R1 and R2, (III) operation of fully connected two-stage anaerobic digestion.

Close modal

In phase II, the SWW was replaced stepwise with effluent from R1 at 30 (batch 4), 50 (batch 5), and 100% (batch 6). With an influent COD concentration of 343 mg-COD/l and COD removal rate of 141 mg-COD/l/d, removal efficiency of 71% was achieved in batch 4. In batch 5 the COD removal efficiency was 47%, with a starting concentration of 566 mg-COD/l and removal rate of 258 mg-COD/l/d. When the connection of R1 and R2 was accomplished (batch 6), the degradation removed around 410 mg-COD/l/d, with an influent COD concentration of 562 mg-COD/l, resulting in 71% removal efficiency. Thus, while the micro-organic environmental conditions changed, the average removal efficiency in phase II was about 63%.

When R1 and R2 were fully connected, organic acid supplementation ceased (phase III). Although the influent COD concentrations – average 305 mg-COD/l – were lower than in the two previous phases, the COD removal efficiency remained the same at around 62%. With a total COD removal rate of 198 mg-COD/l/d, an average effluent concentration of 112 mg-COD/l was achieved.

Finally, it was shown that start-up of the two-stage anaerobic digestion process was successful at a temperature range between 33.7 and 37.5°C, without the need for specific pH control. The pilot plant achieved COD removal efficiencies of 62% on average. Comparable results (69 and 50%) were achieved by Donoso-Bravo et al. (2009) in a similar lab scale plant, even though higher COD influent concentrations of about 500 mg-COD/l were involved. While the pilot plant's average COD removal rate is lower than the results presented in literature (Donoso-Bravo et al. 2009), the target service water quality of 75 mg-COD/l was almost achieved, even during start-up.

Anammox-based third stage start-up

The degradation performance of the Anammox process, with six hours' retention time during start-up, is shown in Figure 4. Feeding 100% SWW (phase (I)) resulted in an average ammonium degradation rate of 155 mg-NH4-N/l/d, with removal efficiencies between 90 and 80%. The average effluent ammoniacal-nitrogen concentration during adaptation was around 7.7 mg-NH4-N/l. In phase II, when the influent SWW:MWW ratio was 80:20%, initial ammonia concentrations were about 40 mg-NH4-N/l. Removal efficiency was between 67 and 72%, yielding an average effluent concentration of 12 mg-NH4-N/l at an average degradation rate of 113 mg-NH4-N/l/d. Increasing the influent MWW:SWW ratio to 50:50 (phase III) then 80:20 (phase IV), lowered the removal efficiencies from 72 to 47%, while the initial ammoniacal-nitrogen concentrations increased from 40 to 82.4 mg-NH4-N/l. The average treated effluent concentrations were 20 mg-NH4-N/l and 40 mg-NH4-N/l in phases III and IV, giving degradation rates of about 158 and 150 mg-NH4-N/l/d, respectively. Feeding 100% MWW (phase V) raised the ammonium concentration to 82 mg-NH4-N/l, while the removal efficiency stayed between 38 and 50%, and the average effluent concentration was about 42 mg-NH4-N/l. The average ammonium degradation rate was thus about 141 mg-NH4-N/l/d.
Figure 4

Ammonium degradation and removal efficiency with 6-hour retention time during Anammox process start-up for treating organically degraded MWW. Start-up is sub-divided into six phases, as noted in the text.

Figure 4

Ammonium degradation and removal efficiency with 6-hour retention time during Anammox process start-up for treating organically degraded MWW. Start-up is sub-divided into six phases, as noted in the text.

Close modal

It is thought that the fall in ammonium removal efficiency in phases III to V arose from inappropriate nitrite-nitrogen (NO2-N) and ammoniacal-nitrogen (NH4-N) ratios. The ratio of NO2-N/NH4-N, as recommended in the literature, should be between 1.15 and 1.3 (van de Graaf et al. 1996; van der Star et al. 2007; Ali & Okabe 2015) After raising the nitrite concentration to give an NO2-N/NH4-N ratio in the range 1.15 to 1.3, removal efficiency increased to 84.1, 95.0 and then 97.2% (phase VI), with an average ammonium degradation rate of 189 mg-NH4-N/l/d.

In order to avoid both excess substrate supply and substrate limitation when treating organically pre-treated MWW, the substrate/feed ratio had to be further modified. Thus different initial NO2-N/NH4-N ratios were tested over the hydraulic retention time. The steadiest values occurred with an initial ratio of 1.14 (see Figure 5, batch 16).
Figure 5

Determination of optimal initial substrate/feed ratio of NO2-N/NH4-N for 6-hour retention time in the Anammox MWW-treatment process.

Figure 5

Determination of optimal initial substrate/feed ratio of NO2-N/NH4-N for 6-hour retention time in the Anammox MWW-treatment process.

Close modal

The Anammox-based process was started successfully within four weeks for treating domestic wastewater at temperatures between 28 and 35°C, and with pH in the range 7.1 to 8.2. Average ammoniacal-nitrogen removal efficiency of 92% was achieved for ammonium-poor wastewater by the end of the start-up. Comparable values of 85 to 99% are reported in the literature for ammonium-rich wastewater (Fux et al. 2002).While the pilot plant's average ammoniacal-nitrogen removal rate was relatively low compared to the results achieved by Fux et al. (2002), the self-defined service water quality limit of 10 mg-NH4-N/l had already been reached during start-up.

Decentralized pilot plant degradation performance

After start-up, pilot plant operation was studied for 200 days. Figures 6 and 7 show the average COD and NH4-N concentrations in the influent MWW, after anaerobic digestion (R2 outlet) and the Anammox-based process (R3 outlet). The average removal efficiencies of COD and NH4-N are also shown for the anaerobic digestion and Anammox-based process steps.
Figure 6

Average organic degradation performance of the pilot plant treating MWW during 200 days of operation. Average COD concentrations for the influent MWW, the effluent from R2 and the effluent from R3 are all shown, as are the COD removal efficiency for R1 + R2 and the Anammox-based process (R3).

Figure 6

Average organic degradation performance of the pilot plant treating MWW during 200 days of operation. Average COD concentrations for the influent MWW, the effluent from R2 and the effluent from R3 are all shown, as are the COD removal efficiency for R1 + R2 and the Anammox-based process (R3).

Close modal
Figure 7

Average ammonium degradation performance of the pilot plant treating MWW during 200 days of operation. The average NH4-N concentrations for the influent MWW, for the effluent from R2, and that from R3 are all shown. The combined NH4-N removal efficiency for R1 + R2 and R3 is also shown.

Figure 7

Average ammonium degradation performance of the pilot plant treating MWW during 200 days of operation. The average NH4-N concentrations for the influent MWW, for the effluent from R2, and that from R3 are all shown. The combined NH4-N removal efficiency for R1 + R2 and R3 is also shown.

Close modal

With an average initial COD concentration of about 212 mg-COD/l in MWW, two-stage anaerobic digestion reduced the COD concentration to 85 mg-COD/l, an average COD removal efficiency of 60%. R3 removed another 21% of COD, giving an average effluent COD of 39 mg-COD/l. Total COD removal efficiency of the three-stage plant during 200 days of operation was about 81%. The first two stages could not meet the self-defined service water limit of 75 mg-COD/l on their own. With the Anammox-based reactor downstream, however, the limit was always achieved.

NH4-N concentrations in the influent MWW were 46 mg-NH4-N/l on average. During anaerobic digestion the ammoniacal-nitrogen concentration rose on average to 50 mg-NH4-N/l, which can be explained by the hydrolysis of protein-rich wastewaters (Grepmeier 2002). In the Anammox-based stage, however, it decreased, on average, to 1 mg-NH4-N/l. This represents an ammonium removal efficiency of about 96% with six hours' retention time, and the self-defined limit of 10 mg-NH4-N/l was undershot substantially.

This paper is a description of the successful start-up of a decentralized anaerobic pilot plant for treating domestic wastewater to service water standards. At first, all reactors were operated separately to facilitate microorganism adaptation to the new environments.

The initial, two-stage anaerobic digestion was operated in a temperature range of 33.7 to 37.5°C, without pH-control. Even in this phase, an average COD removal efficiency of 62% was achieved, reducing the average influent COD concentration of 305 mg-COD/l to 112 mg-COD/l. Average COD removal efficiencies of 60% in the subsequent, 200-day, operational testing phase show that the process was stabilized successfully. While achieving an effluent COD concentration of approximately 85 mg-COD/l, the two-stage treatment could not satisfy the self-defined service water quality limit of 75 mg-COD/l on its own. With treatment by the Anammox-based reactor downstream, however, the limit was undershot (39 mg-COD/l).

Ammoniacal-nitrogen removal efficiencies in the Anammox process were between 90 and 79.8%, during feeding with 100% SWW. Substrate limitation led to low removal efficiencies during adjustment to MWW. The optimum NO2-N/NH4-N ratio for the Anammox-stage of the pilot plant was determined as 1.14 and the nitrite feed was adapted to this. Subsequently, ammonium removal in 100% MWW was about 95% and the self-defined limit for service water of 10 mg-NH4-N/l was achieved with a retention time of six hours. With an average removal efficiency of about 96% during the subsequent 200 days of operation, it is safe to say that the Anammox-process was stabilized successfully.

The authors acknowledge gratefully the Hans-Sauer Foundation for financial support for setting-up and starting-up the pilot plant; the communal sewage plant in Erlangen, Germany, for their help, and SIEMENS AG, Germany, Schraml GmbH, WEBFactory GmbH, ZWT Wasser- und Abwassertechnik GmbH, Maschinenbau Biermann GmbH, Albert Handtmann Armaturenfabrik GmbH & Co, and Norddeutsche Seekabelwerke GmbH for the support and equipment provided. H. Kang is also thanked for her reliable contribution to the work during the start-up phase.

AbwV
2016
Verordnung über Anforderungen an das Einleiten von Abwasser in Gewässer, Abwasserverordnung – AbwV (Regulations About the Discharge of Wastewater to Surface Waters – Wastewater Regulations), 17.6.2004 I 1108, 2625
.
Federal Ministry of Justice and Consumer Protection
,
Berlin
,
Germany
.
Ali
M.
Okabe
S.
2015
Anammox-based technologies for nitrogen removal: advances in process start-up and remaining issues
.
Chemosphere
141
,
144
153
.
doi: http://dx.doi.org/10.1016/j.chemosphere.2015.06.094
.
Ali
M.
Oshiki
M.
Rathnayake
L.
Ishii
S.
Satoh
H.
Okabe
S.
2015
Rapid and successful start-up of anammox process by immobilizing the minimal quantity of biomass in PVA-SA gel beads
.
Water Res.
79
,
147
157
.
doi: http://dx.doi.org/10.1016/j.watres.2015.04.024
.
Barbosa
R. A.
Sant'Anna
G. L. J.
1989
Treatment of raw domestic sewage in an UASB reactor
.
Water Research
23
,
1483
1490
.
doi: http://dx.doi.org/10.1016/j.cej.2016.03.148
.
Batstone
D. J.
2006
Mathematical modelling of anaerobic reactors treating domestic wastewater
.
Rev. Environ. Sci. Biotechnol.
5
,
57
71
.
doi: http://dx.doi.org/10.1007/s11157-005-7191-z
.
BayBadeGewV
2008
BayBadeGewV: Verordnung über die Qualität und die Bewirtschaftung der Badegewässer, Bayerische Badegewässerverordnung – BayBadeGewV (Regulations about quality and cultivation of bathing waters – Bavarian bathing water regulations), 15.02.2008 (GVBl S. 54) BayRS 753-1-17-U (§§ 1–14) – citizen service, BayRS 753-1-17-U
.
Bavarian State Ministry of the Environment and Consumer Protection
,
Munich
,
Germany
.
Donoso-Bravo
A.
Ruiz-Filippi
G.
Chamy
R.
2009
Anaerobic treatment of low-strength wastewater with a high fraction of particulate matter in an unconventional two-phase ASBRs system
.
Biochem. Eng. J.
43
,
297
302
.
doi: http://dx.doi.org/10.1016/j.bej.2008.10.011
.
Foresti
E.
Zaiat
M.
Vallero
M.
2006
Anaerobic processes as the core technology for sustainable domestic wastewater treatment: consolidated applications, new trends, perspectives, and challenges
.
Rev. Environ. Sci. Biotechnol.
5
,
3
19
.
doi: http://dx.doi.org/10.1007/s11157-005-4630-9
.
Fux
C.
Boehler
M.
Huber
P.
Brunner
I.
Siegrist
H.
2002
Biological treatment of ammonium-rich wastewater by partial nitritation and subsequent anaerobic ammonium oxidation (anammox) in a pilot plant
.
J. Biotechnol.
99
,
295
306
.
doi: http://dx.doi.org/10.1016/S0168-1656(02)00220-1
.
Grady
C. P. L.
Daigger
G. T.
Love
N. G.
Filipe
C. D. M.
2011
Biological Wastewater Treatment
, 3rd edn.
CRC Press & IWA Publishing
,
SC, USA
.
Grepmeier
M.
2002
Experimentelle Untersuchungen an einer zweistufigen fuzzy-geregelten anaeroben Abwasserreinigungsanlage mit neuartigem Festbettmaterial (Experimental study of a two-stage, fuzzy-control, anaerobic wastewater treatment plant with novel, fixed-bed material). PhD Thesis
,
TUM School of Life Sciences Weihenstephan, Technical University of Munich
,
Munich
,
Germany
.
Herbst
H. B.
2008
Bewertung zentraler und dezentraler Abwasserinfrastruktursysteme (Evaluation of centralized and decentralized wastewater infrastructure systems). PhD Thesis
,
Faculty of Civil Engineering, RWTH Aachen University
,
Aachen
,
Germany
.
Isaka
K.
Sumino
T.
Tsuneda
S.
2007
High nitrogen removal performance at moderately low temperature utilizing anaerobic ammonium oxidation reactions
.
J. Biosci. Bioeng.
103
,
486
490
.
doi: http://dx.doi.org/10.1263/jbb.103.486
.
Kalogo
Y.
Verstraete
W.
2001
Potentials of anaerobic treatment of domestic sewage under temperate climate conditions
. In:
Decentralised Sanitation and Reuse: Concepts, Systems and Implementation
.
IWA Publishing
,
London
, pp.
181
204
.
Kobayashi
H. A.
Stenstrom
M. K.
Mah
R. A.
1983
Treatment of low strength domestic wastewater using the anaerobic filter
.
Water Res.
17
,
903
909
.
doi: http://dx.doi.org/10.1016/0043-1354(83)90164-1
.
Kuba
T.
Furumai
H.
Kusuda
T.
1990
A kinetic study on methanogenesis by attached biomass in a fluidized bed
.
Water Res.
24
,
1365
1372
.
doi: http://dx.doi.org/10.1016/0043-1354(90)90155-Y
.
Ma
B.
Wang
S.
Cao
S.
Miao
Y.
Jia
F.
Du
R.
Peng
Y.
2016
Biological nitrogen removal from sewage via anammox: recent advances
.
Bioresour. Technol.
200
,
981
990
.
doi: http://dx.doi.org/10.1016/j.biortech.2015.10.074
.
Massoud
M. A.
Tarhini
A.
Nasr
J. A.
2009
Decentralized approaches to wastewater treatment and management: applicability in developing countries
.
J. Environ. Manage.
90
,
652
659
.
doi: http://dx.doi.org/10.1016/j.jenvman.2008.07.001
.
Olsson
G.
Nielsen
M.
Yuan
Z.
Lynggaard-Jensen
A.
Steyer
J.-P.
2005
Instrumentation, Control and Automation in Wastewater Systems
.
IWA Publishing
,
London
.
Strous
M.
Heijnen
J. J.
Kuenen
J. G.
Jetten
M. S. M.
1998
The sequencing batch reactor as a powerful tool for the study of slowly growing anaerobic ammonium-oxidizing microorganisms
.
Appl. Microbiol. Biotechnol.
50
,
589
596
.
doi: http://dx.doi.org/10.1007/s002530051340
.
van de Graaf
A. A.
de Bruijn
P.
Robertson
L. A.
Jetten
M. S. M.
Kuenen
J. G.
1996
Autotrophic growth of anaerobic ammonium-oxidizing micro-organisms in a fluidized bed reactor
.
Microbiology
142
,
2187
2196
.
doi: http://dx.doi.org/10.1099/13500872-142-8-2187
.
van der Star
W. R. L.
Abma
W. R.
Blommers
D.
Mulder
J.-W.
Tokutomi
T.
Strous
M.
Picioreanu
C.
van Loosdrecht
M. C. M.
2007
Startup of reactors for anoxic ammonium oxidation: experiences from the first full-scale anammox reactor in Rotterdam
.
Water Res.
41
,
4149
4163
.
doi: http://dx.doi.org/10.1016/j.watres.2007.03.044
.
Vega De Lille
M. I.-C.
2015
Modeling, Simulation and Control of Biotechnological Processes in Decentralized Anaerobic Treatment of Domestic Wastewater. PhD Thesis
,
Faculty of Engineering, Friedrich-Alexander-University Erlangen-Nuremberg
,
Erlangen
,
Germany
.
Wesoly
I.
2009
Betriebsstrategien für den Anammox Prozess in Sequencing Batch Reaktoren (operational strategies for the anammox process in sequencing batch reactors). PhD Thesis
,
School VI Planning Building Environment, Technical University of Berlin
,
Berlin
,
Germany
.