The study demonstrates the implementation of Jaya Algorithm (JA) to optimize the Irrigation Pipe Distribution Network (IPDN) for the networks of the Kanhan Branch of Pench project, Maharashtra, India. In the present work, two case studies with their networks of two different sizes are designed using the Critical Path Method (CPM). The pipe diameters thus obtained in CPM are optimized using two optimization techniques, viz. linear programming (LP) and recently developed Jaya Algorithm (JA). JA is a relatively new optimization technique requiring minimum input parameters and are selected based on sensitivity analysis. The comparison of the results using LP and JA exhibits significant reduction in cost of IPDN using newly developed JA. The scope of reduction in the total cost using JA increases with increase in the network area.

  • Implementation of Jaya Algorithm (JA) for optimization of IPDN.

  • Comparison of JA with classic LP, a globally accepted optimization technique.

  • Input parameter selection for the JA is obtained using sensitivity analysis.

  • Significant cost reduction observed for the irrigation network using JA.

  • JA for pipe size optimization of large IPDN could significantly reduce the pipe cost, reducing the total project cost.

Graphical Abstract

Graphical Abstract
CPM

Critical Path Method

EA

Evolutionary Algorithm

FEs

Function evaluations

GA

Genetic Algorithm

HGL

Hydraulic gradient level

HW

Hazen Williams

IPDN

Irrigation pipe distribution networks

JA

Jaya Algorithm

KBC

Kanhan Branch Canal

LP

Linear programming

NLP

Non-linear programming

PSC

Prestressed concrete pipes SA = Sensitivity Analysis

Total cost of the network

and

No. of links and commercial pipes respectively

Unit cost of pipe size b in link a

Hazen-Williams pipe coefficient

Diameter of pipe in mm

Minimum head at node j

Head available at source node O

,

Cost constant

Length of the pipe in meter

Length of pipe size b in link a

Flow through link a in m3/min

and

Two arbitrary numbers in the range of 0–1 for jth variable during ith iteration

Friction slope for pipe size b in link a

Modified value of

Value of jth variable for the best candidate

Value of jth variable for the worst candidate

Water is a vitally important resource required to be managed efficiently for the sustenance of human beings. In a tropical country like India, growing population and industrialization have aggravated water shortage in the agricultural sector. Irrigation in the country is practiced mainly through open canal networks in which the seepage losses are very high. Though the design efficiencies of most of the projects are to the tune of 41–48%, actually it may reduce to 20–35% because of field difficulties or restrictions, which shows the extent of water loss depriving the tail-enders of the benefits of irrigation practices (Satpute et al. 2012). The maintenance cost of the canal system is high as compared to pipe networks. Also, repetitive maintenance is required for the canals, whereas for pipe networks, better control on the functioning of the system can be achieved. As the pipe system may be buried, freedom of network layout is possible along with the solution to the problem of land acquisition as in the case of canal networks. In light of this fact, concrete steps of replacing the open canals with pipe conveyance systems have become a necessity. This method of conveying water would assure water saving, which otherwise percolates in the ground and becomes unavailable when required (Gajghate & Mirajkar 2020). The available water may cultivate more crops per year, leading to higher benefits for the farmers. The rise in income promotes the economic status of the users, leading to society's overall prosperity. However, the initial investment cost of the IPDN is very high compared to the open canals (Sudan & Gupta 2017). The justification for pressing pipe irrigation stands erect because of the long-term advantages of comparing the land acquisition cost, maintenance cost, water losses, public hygiene, and socio-economic factors. The major part of the initial investment of IPDN is the pipe cost. The fact that the pipe cost directly varies with the pipe diameter makes it very important that optimum pipe sizes be selected for both the performance and total project cost while designing any network. Colebrook-White transition formula was used for circular pipe design, which relates Reynolds number and relative roughness with friction loss (Viccione & Tibullo 2012; Praks & Brkic 2020). With the advancement in computer technology, various optimization techniques have been developed for water network optimization. LP was used for the optimization of the water supply system involving two steps. The first step converted the looped system into a branched network, while in the next step, optimization of the branched network, is carried out (Bhave 1983). LP and NLP are used in two stages, with LP in the first stage to determine the minimum cost design for a given flow. In the second stage, non-linear programming (NLP) is used to find the modified flows, which further reduces the cost of the water distribution network (Qiu et al. 2020). Integer linear programming technique was explored for water distribution system optimization (Alperovits & Shamir 1977). For minimizing the total cost of the irrigation pipeline network, a hybrid model including LP and Genetic Algorithms (GA) was developed (Lapo et al. 2016) to check its effectiveness. Other optimization methods that are used in water networks optimization are differential evolution and mixed integer linear programming (Mansouri et al. 2015), GA (Kadu et al. 2008), simulated annealing (Cunha & Sousa 1999), ant colony (Maier et al. 2003) and shuffled frog leaping algorithm (Ensuff & Lansey 2003).

Most of the optimization techniques involve a number of input parameters and it is very important to achieve reasonable results. More parameters require extensive trials and tuning, which is time consuming, to evaluate the optimum results. The computation complexity is very high for more extensive networks (Shende & Chau 2019). This fact motivated the authors to carry out the present study of the application of JA for the optimization of IPDN. JA is a recent, simple and powerful global optimization algorithm developed by Rao in 2016. The prime advantage of JA is that it requires only a few control parameters reducing the extensive trials and thus minimizing the computation complexity of the problem. It makes the wide application of JA simple and popular in various fields of engineering and sciences (Pandey 2016; Kumar & Yadav 2018; Rao et al. 2018; Varade & Patel 2018; Paliwal et al. 2020).

The objective of the present study is to design the IPDN diameters using CPM. The layout of the irrigation networks and water requirement (demand) is predefined, and the optimization is oriented to find the minimum cost of IPDN. The factors affecting the layout of the irrigation networks are the geographic proximity, spatial distribution of the customers, water demand and available head. Networks considered for the study are two adjoining distributaries of the Pench Irrigation Project. Bakhari distributary is a 33-pipe network, while Nandgaon distributary is a small five-pipe network. Both the networks are designed for steady-state conditions. As the study area belongs to a semi-arid region and the network will be underground, temperature stresses due to weather conditions changes will not be that significant as far as pipe material is concerned. For the present study, the prestressed concrete (PSC) pipes are used for the design using Hazen-Williams (HW) formula as it develops desired positive pressures. The networks are designed using CPM to obtain the initial design diameters. The optimization of the initially obtained diameters is carried out using LP. A computer model is developed for JA using MATLAB (R2015a) to optimize the obtained designed diameters for IPDN. Finally, a cost comparison of the networks is carried out. Also, sensitivity analysis is carried out to determine the effect of JA's control parameter on the best value of the objective function (cost). Hybrid approach of obtaining diameters using CPM and thereby optimizing the cost using the novel JA is the main aim of the present study. The comparison results indicate that JA can be promisingly applied to real networks for IPDN optimization, thus reducing the network's total cost with lesser efforts.

Study area

The Left Bank Canal (LBC) of the Pench irrigation project, India, consists of four branch canals, viz. Kanhan, Mouda, Ramtek, and Kandri. The average annual rainfall for the study area is 1,150 mm, which occurs from June to September. Minimum or no rain is received during the remaining period. The mean minimum and maximum temperatures are around 12 and 45 °C. The soil found is medium to deep clayey, black cotton soil. The rocky layer is encountered at a depth of 7–8 m, therefore does not hinder the pipe network. The schematic sketch shown in Figure 1 gives an overview of the Pench project and also shows the area selected for the study.

Figure 1

Schematic sketch of Pench Project, Maharashtra, India.

Figure 1

Schematic sketch of Pench Project, Maharashtra, India.

Close modal

Two distributaries of different sizes of the Kanhan Branch Canal (KBC), having different command areas, are considered distinctly for the analysis viz. Bakhari (820 Ha) and Nandgaon distributaries (183 Ha). The irrigation system existing for the study area is the canal system. This canal system is proposed to be replaced with the piped irrigation system. The design and optimization of the developed IPDNs are then carried out. Figure 2 represents the proposed replaced canal system with the pipe network for Bakhari and Nandgaon distributaries, not the scale. Bakhari network is a 33-pipe system with a single source, as shown in Figure 2(a). The off-taking point from KBC is at 990 m. R1 (source) location coordinates are 21.34°N and 79.22°E with a head of 308.98 m. Figure 2(b) represents the Nandgaon distributary, which is proposed to be replaced by a five-pipe network. It is adjoining the Bakhari distributary and takes off from the KBC at 3,750 m. The coordinates of the source, R2, are 21.33°N and 79.22°E, and the head at R2 is 307 m.

Figure 2

Replacement of existing canals (a) Bakhari (b) Nandgaon.

Figure 2

Replacement of existing canals (a) Bakhari (b) Nandgaon.

Close modal

Critical Path Method (CPM)

IPDN design is carried out using CPM. The method involves determining the slope of all the paths connecting the source to each demand node. The path bearing the minimum slope is considered the critical path (Bhave 1978; Bhave & Gupta 2006). The correction obtained is applied to all the heads, and thus head loss is calculated. The pipe diameters in the network are calculated using Equation (1).
(1)
where,
  • = Diameter of pipe in mm for link ;

  • = Friction slope for pipe size b in link ;

  • = Flow through link a in m3/min; and

  • = Hazen-Williams pipe coefficient.

For the present work, the initial diameters are obtained for the Bakhari and Nandgaon networks using CPM, as shown in Tables 1 and 2. The Hazen-Williams pipe coefficient used is 130. The discharge in each pipe as shown in Tables 1 and 2 are used to calculate the diameters. These initial diameters are used as inputs for the model formulation of LP and JA for optimization.

Table 1

Diameters obtained using CPM for Bakhari network

PipeLength (m)Q (m3/min)Head Loss (m)Diameter (mm)PipeLength (m)Q (m3/min)Head Loss (m)Diameter (mm)
50 84.65 0.07 1,121.21 18 990 7.92 2.96 390.67 
1,200 8.46 2.95 416.77 19 680 36.05 0.96 810.71 
685 76.19 0.96 1,077.25 20 610 3.66 2.20 280.36 
825 3.72 2.44 293.65 21 450 3.66 2.09 266.07 
390 72.47 0.55 1,056.96 22 560 28.73 0.79 743.75 
940 3.72 1.84 319.80 23 510 3.66 1.97 276.30 
135 68.75 0.19 1,036.01 24 430 25.07 0.61 706.24 
500 3.00 1.71 262.91 25 510 1.89 2.37 207.06 
155 65.75 0.22 1,018.60 26 340 23.18 0.48 685.52 
10 2,250 5.94 4.49 380.50 27 900 4.72 1.89 345.12 
11 470 59.81 0.66 982.61 28 185 18.46 0.26 628.71 
12 455 3.66 3.27 243.25 29 900 8.32 1.27 464.50 
13 345 56.15 0.49 959.33 30 265 10.14 0.48 475.12 
14 460 3.66 2.96 248.83 31 150 10.14 0.27 475.12 
15 270 52.49 0.38 935.08 32 480 3.36 0.87 312.30 
16 810 8.52 2.96 385.27 33 285 6.78 0.87 366.36 
17 170 43.97 0.24 874.24      
PipeLength (m)Q (m3/min)Head Loss (m)Diameter (mm)PipeLength (m)Q (m3/min)Head Loss (m)Diameter (mm)
50 84.65 0.07 1,121.21 18 990 7.92 2.96 390.67 
1,200 8.46 2.95 416.77 19 680 36.05 0.96 810.71 
685 76.19 0.96 1,077.25 20 610 3.66 2.20 280.36 
825 3.72 2.44 293.65 21 450 3.66 2.09 266.07 
390 72.47 0.55 1,056.96 22 560 28.73 0.79 743.75 
940 3.72 1.84 319.80 23 510 3.66 1.97 276.30 
135 68.75 0.19 1,036.01 24 430 25.07 0.61 706.24 
500 3.00 1.71 262.91 25 510 1.89 2.37 207.06 
155 65.75 0.22 1,018.60 26 340 23.18 0.48 685.52 
10 2,250 5.94 4.49 380.50 27 900 4.72 1.89 345.12 
11 470 59.81 0.66 982.61 28 185 18.46 0.26 628.71 
12 455 3.66 3.27 243.25 29 900 8.32 1.27 464.50 
13 345 56.15 0.49 959.33 30 265 10.14 0.48 475.12 
14 460 3.66 2.96 248.83 31 150 10.14 0.27 475.12 
15 270 52.49 0.38 935.08 32 480 3.36 0.87 312.30 
16 810 8.52 2.96 385.27 33 285 6.78 0.87 366.36 
17 170 43.97 0.24 874.24      
Table 2

Diameters obtained using CPM for Nandgaon network

PipeLength (m)Q (m3/min)Head Loss (m)Diameter (mm)
40 60 51.12 0.01 1,434.83 
41 630 38.22 0.06 1,441.21 
42 1,110 32.28 0.09 1,397.05 
43 1,200 12.9 0.11 961.50 
44 1,020 5.94 0.09 721.78 
PipeLength (m)Q (m3/min)Head Loss (m)Diameter (mm)
40 60 51.12 0.01 1,434.83 
41 630 38.22 0.06 1,441.21 
42 1,110 32.28 0.09 1,397.05 
43 1,200 12.9 0.11 961.50 
44 1,020 5.94 0.09 721.78 

Linear programming (LP)

LP is an old but effective method for optimization. A globally optimal solution can be reached for the branched water networks using LP. It can solve problems that are simple as well as complex in nature. For the present work, the optimization of the total cost of the two networks (Bakhari and Nandgaon) is carried out using LP with the constraints of minimum head loss and length of each pipe as variable.

The optimization problem is formulated to minimize the total cost of the network without violating the head constraints. A single pipe is divided into two parts to utilize two different diameters for the same pipe. The reference diameters used for these two diameters (one on the higher side and the other on the lower side) are the diameters obtained using the CPM.

The minimization function is formulated as per Equation (2). with the assumption that discrete pipe sizes available () are, = 1, …., B, decreasing in diameter from largest to smallest (Bhave & Gupta 2004). The parameters used for formulation is defined with subsequent equations.
(2)
where,
  • – Total cost of the network;

  • and B – No. of links and commercial pipes, respectively;

  • – Unit cost of pipe size b in link ; and

  • – Length of pipe size b in link .

The cost of each pipe is given by Equation (3).
(3)
where,
  • – Diameter of pipe in mm;

  • – Length of the pipe in meter; and

  • ,m – Cost constant.

The constraints are as follows:

Since summation of lengths of pipes in each link must be equal to the length of the link as shown in Equation (4).
(4)
For = 1, … …, A
The head loss along path Pj from source node O to any demand node j must not exceed the permissible head loss (Ho-Hjmin). Mathematically, it is expressed as:
(5)
For all the paths Pj, j = 1, … …., N
At the same time, all the variables must be positive and hence can be stated in the formulation as:
(6)
For = 1, … …, A; = 1, … …. B

where,

  • – Head available at source node O;

  • – Minimum head at node j;

  • – Friction slope for the pipe size b in link ;

  • = 2.215 × 1012;

  • P – 1.85; and

  • r – 4.87.

In the present study, cost of pipe diameter for each pipe and optimized length of each pipe is considered to calculate the total cost of the network. Tables 3 and 4 show each pipe length's division in two parts to achieve the optimized pipe sizes to minimize the total cost for the Bakhari and Nandgaon networks.

Table 3

Length of pipes for Bakhari

PipeI Part of PipeII Part of PipeTotal Length of Pipe (m)PipeI Part of PipeII Part of PipeTotal Length of Pipe (m)
L11 L12 50 18 L181 L182 990 
L21 L22 1,200 19 L191 L192 680 
L31 L32 685 20 L201 L202 610 
L41 L42 825 21 L211 L212 450 
L51 L52 390 22 L221 L222 560 
L61 L62 940 23 L231 L232 510 
L71 L72 135 24 L241 L242 430 
L81 L82 500 25 L251 L252 510 
L91 L92 155 26 L261 L262 340 
10 L101 L102 2,250 27 L271 L272 900 
11 L111 L112 470 28 L281 L282 185 
12 L121 L122 455 29 L291 L292 900 
13 L131 L132 345 30 L301 L302 265 
14 L141 L142 460 31 L311 L312 150 
15 L151 L152 270 32 L321 L322 480 
16 L161 L162 810 33 L331 L332 285 
17 L171 L172 170     
PipeI Part of PipeII Part of PipeTotal Length of Pipe (m)PipeI Part of PipeII Part of PipeTotal Length of Pipe (m)
L11 L12 50 18 L181 L182 990 
L21 L22 1,200 19 L191 L192 680 
L31 L32 685 20 L201 L202 610 
L41 L42 825 21 L211 L212 450 
L51 L52 390 22 L221 L222 560 
L61 L62 940 23 L231 L232 510 
L71 L72 135 24 L241 L242 430 
L81 L82 500 25 L251 L252 510 
L91 L92 155 26 L261 L262 340 
10 L101 L102 2,250 27 L271 L272 900 
11 L111 L112 470 28 L281 L282 185 
12 L121 L122 455 29 L291 L292 900 
13 L131 L132 345 30 L301 L302 265 
14 L141 L142 460 31 L311 L312 150 
15 L151 L152 270 32 L321 L322 480 
16 L161 L162 810 33 L331 L332 285 
17 L171 L172 170     
Table 4

Lengths of pipes for Nandgaon

PipeI Part of PipeII Part of PipeTotal Length of Pipe (m)
L401 L402 60 
L411 L412 630 
L421 L422 1,110 
L431 L432 1,200 
L441 L442 1,020 
PipeI Part of PipeII Part of PipeTotal Length of Pipe (m)
L401 L402 60 
L411 L412 630 
L421 L422 1,110 
L431 L432 1,200 
L441 L442 1,020 
JA is a very recent, simple, and powerful global optimization algorithm developed by Rao in 2016. The minimization and maximization functions can be very well dealt with using JA as it is independent of the nature of the objective function. Its ability to explore and exploit its capacities using lesser function evaluations makes it more popular (Das et al. 2017). The prime advantage of JA is that it requires only a few control parameters (common for most of the algorithms), as the number of generations and population size. This attribute of JA decreases the complication of tuning of the other parameters (algorithm-specific parameters), as in the case of other evolutionary algorithms, making it an algorithm-specific, parameter-less algorithm (Rao 2016). JA is a metaheuristic optimization technique having a simple approach of revision of the variable value until the optimal solution is reached. The two random numbers provide a larger search space as one number is associated with the best solution, and the other one is associated with the worst solution. JA can thus be considered as a stochastic optimization algorithm. Constraints are applied as penalty functions; hence, the convergence to the optimal solution is not affected by more number of constraints.

The penalty is additive for the minimization problem, whereas for the maximization problem, it is subtractive. Thus, a modified function value is obtained. Further processing of the function is carried out using the best and the worst values of the reformed function. Rejection of the solution containing the violation is achieved as the penalty function's formulation is done accordingly. The maximum number of generations is already set initially as the termination criteria. As soon as the termination criteria are reached, the model stops processing, and results are provided.

Working of JA

Let the objective function to be minimized (or maximized) is f(x) with m design variables and n candidate solutions (population size, k = 1, 2, …..n) at any iteration i.
(7)
where,
  • = minimum value of the variable ;

  • = arbitrary number in the range of 0–1; and

  • = maximum value of the variable .

Let the candidate ‘best’ attain the best value of f(x) (i.e. f(x)best) and the candidate ‘worst’ attain the worst value of f(x) (i.e. f(x)worst) in the whole candidate solutions. If is the value of jth variable for kth candidate during ith iteration, then in Equation (7) is modified to according to Equation (8).
(8)
where,
  • = value of jth variable for the best candidate;

  • = value of jth variable for the worst candidate;

  • = modified value of ; and

  • and = two arbitrary numbers in the range of 0–1 for jth variable during ith iteration.

Equation (8) gives the upgraded value of the variables, which contains two arbitrary numbers, and . These two numbers play a vital role in the up-grading of the variables, improving the fitness function. The arbitrary number is linked to a term representing the gap between the present value and the best value of the variable for a particular iteration. Thus, the term shows the inclination to move closer to the best solution. Similarly, is linked to a term representing the gap between the present value and the worst value of the variable for a particular iteration. Hence, the term shows the inclination of the solution to depart from the worst solution. It shows that the algorithm tends to get nearer to success (i.e., approaching the best solution) and attempts to avoid failure (i.e., departing from the worst solution). Hence, it is named Jaya (meaning victory in Sanskrit). The value of is adopted only if it gives a better function value. The function value is compared with the modified value, and if found to be better than the previous value, then the modified value of replaces the previous value, and the process is continued till the final termination criteria are satisfied. The arbitrary numbers and facilitates an adequate search space, while () term enhances the algorithm's exploration ability. The flow chart depicting the working of JA can be referred from (Rao 2016). In the present study, the single pipe length for two different diameters is the design variable (m), and the number of candidate solutions (population size) considered is 50 for maximum function evaluations (FE) of 1000. Each set of population is evaluated 10 times.

The effect of the input parameters on the output values is studied using sensitivity analysis (SA) (Renault 2000). SA provides a clear idea for the selection of parameters to obtain the desired output. In optimization formulation, the input parameters are very important to achieve reasonable conclusions. Various algorithms have been used to optimize the parameters and to enhance the performance and descent ability (Deng et al. 2020a, 2020b; Song et al. 2020). In the present study, a newly developed JA is used for the optimization of IPDN. The input parameters required are the population size and FEs to obtain the best value of the objective function. FEs are the product of population size and generations and signify the actual number of times for which the objective function value is evaluated. Population size defines the extent of search space; hence is a crucial parameter for Evolutionary Algorithm (EA) performance. The number of possible combinations of the variables increases with the larger population size. More combinations lead to increased computational time without any assurance of significant improvement in the optimal value. Therefore, the selection of particular population size has to be done with proper analysis. Hence, for the current study, SA is carried out for Bakhari network, in which three population sizes are selected, and its effect is analyzed on the best value of the objective function, which is the cost in this case. The three population sizes selected are 10, 50, and 100 for the maximum FEs of 1000, which is kept constant for all three population sizes. For each population size, 10 runs are carried out before reporting the final optimal values. The variation of the best value of the objective function (cost of the network) with the population size is shown in Figure 3.

Figure 3

Variation of best value of total cost of the network with population size.

Figure 3

Variation of best value of total cost of the network with population size.

Close modal

The number of trials with a different number of the population reveals that more population size takes away from the best solution while lower population size approaches towards the desired solution that is the minimum cost. On analysis, as shown in Figure 3, it is observed that the best value of objective function lies in a particular band ranging from 78.50 to 82.00 Million Rupees (1.06–1.11 Million $). Since the best value of the objective function is found out at the population size of 50, there is little possibility of lying of the optimal solution in the population size more than 100. Hence, the analysis is stopped at the population size of 100. Thus, the optimal solution is reported as the value obtained with the population size of 50 in the sixth run having the maximum FEs as 1000.

The design of the Bakhari and Nandgaon networks is carried out using CPM. The initial diameters resulted from CPM are optimized using LP and JA. The optimization of both the networks is carried out to optimize the diameters and minimize the total pipe cost. LINGO 17.0 solver is used to carry out the LP optimization, whereas the code is developed in MATLAB (R2015a) for JA optimization. The costs are calculated for optimized pipe diameters from both approaches. In the model development of LP, two diameters are considered, one on either side of the obtained designed diameter from CPM to reach the most optimized values. The number of pipes in the Bakhari network is 33. Each pipe is divided into two parts; thus, two variable diameters are obtained for two different lengths. For example, the total length of pipe 2 for the Bakhari network is 1,200 m. It is divided into two parts, viz. L21 and L22. Thus, two variables are generated for a single pipe. Therefore for 33 pipes of the Bakhari network, 66 variables are generated, and similarly, for the Nandgaon network, 10 variables are generated. The first part of the pipe represents the diameter on the higher side of the designed diameter available commercially. The second part represents the diameter on the lower side of the designed diameter. The number of constraints is 135 for Bakhari network, whereas, for the Nandgaon network, it is 21. The results for the optimized diameters and total costs for Bakhari and Nandgaon networks using LP and JA are explained in the following subsections. For the diameter optimization using JA, the code is developed in MATLAB (R2015a). The code is developed to find out the first part of the pipe only; hence the number of variables for the Bakhari distributary is 33 and that for Nandgaon is 5, thus, simplifying the code compared to LP. The second part of the pipe can be calculated, as the pipe's total length is already known.

The optimized diameters and the total cost for the Bakhari network using LP and JA are shown in Table 5. The estimation of total network cost is done using the rates (Chief Engineer 2012) according to the pipe diameters obtained from CPM and the obtained lengths from LP and JA in the networks. In Table 5, column 1 and column 5 represent the two parts (Part I and Part II) of a single link. Column 2 and column 6 represent the pipe diameters adopted for the I and II parts of the pipe length. Column 3 and column 4 represent the optimized lengths obtained for the I part of pipe length using LP and JA, respectively. Similarly, column 7 and column 8 show the optimized lengths obtained for the II part of pipe length using LP and JA, respectively. Column 9 and column 10 show the total cost of the pipes (Part I and Part II) obtained using LP and JA, respectively. To calculate the total cost, rates of the different sizes of the commercially available pipes (Chief Engineer 2012) as shown in Table A of Appendix I are used. The PSC pipes available in the markets are used as per their prices to calculate the total cost. Table 5 shows that using LP optimization, for eight pipes (L11, L111, L171, L191, L241, L291, L301, L311), the first part of the length is completely eliminated, thereby eliminating diameter leads to cutting down the cost of the network. For 10 pipes (L32, L42, L52, L72, L82, L92, L152, L222, L262, L282), the second part is zero depicts that the diameter on the higher side is required for the entire length of these 10 pipes. For the rest of the 15 pipes, the cost is shared by both the sizes of pipes.

Table 5

Optimized diameters and total cost for Bakhari using LP and JA

Link/PipeLPJALink/PipeLPJATotal Cost
DiameterLengthLengthDiameterLengthLength(M. Rs.)
(mm)(m)(m)(mm)(m)(m)LPJA
1 2 3 4 5 6 7 8 9 10 
L11 1,150 0.00 0.00 L12 1,100 50.00 50.00 0.60 0.60 
L21 450 503.58 0.00 L22 400 696.42 1,200.00 4.20 4.09 
L31 1,100 685.00 0.00 L32 1,050 0.00 685.00 8.26 7.73 
L41 315 825.00 5.55 L42 300 0.00 819.45 2.53 2.29 
L51 1,100 390.00 0.00 L52 1,050 0.00 390.00 4.70 4.40 
L61 350 345.97 0.00 L62 315 594.03 940.00 2.89 2.88 
L71 1,050 135.00 0.00 L72 1,000 0.00 135.00 1.52 1.31 
L81 315 500.00 0.00 L82 300 0.00 500.00 1.53 1.39 
L91 1,050 155.00 0.00 L92 1,000 0.00 155.00 1.75 1.51 
L101 400 1,415.50 0.00 L102 350 834.50 2,250.00 7.42 7.00 
L111 1,050 0.00 0.00 L112 1,000 470.00 470.00 4.58 4.58 
L121 350 413.30 0.00 L122 200 41.70 455.00 1.34 0.55 
L131 1,000 334.98 0.00 L132 950 10.02 345.00 3.62 3.36 
L141 350 438.99 0.00 L142 200 21.01 460.00 1.39 0.56 
L151 950 270.00 0.00 L152 900 0.00 270.00 2.63 2.42 
L161 400 553.50 0.00 L162 350 256.50 810.00 2.68 2.52 
L171 900 0.00 0.00 L172 850 170.00 170.00 1.37 1.37 
L181 400 782.03 0.00 L182 350 207.97 990.00 3.31 3.08 
L191 850 0.00 0.00 L192 800 680.00 680.00 4.89 4.89 
L201 315 410.58 0.00 L202 250 199.42 610.00 1.64 1.18 
L211 315 167.30 0.00 L212 250 282.70 450.00 1.06 0.87 
L221 750 560.00 0.00 L222 700 0.00 560.00 3.64 3.25 
L231 315 292.77 0.00 L232 250 217.23 510.00 1.32 0.98 
L241 800 0.00 0.00 L242 750 430.00 430.00 2.49 2.49 
L251 250 84.91 0.00 L252 200 425.09 510.00 0.68 0.62 
L261 700 340.00 0.00 L262 650 0.00 340.00 1.97 1.84 
L271 350 763.99 900.00 L272 315 136.01 0.00 2.79 2.80 
L281 650 185.00 0.00 L282 600 0.00 185.00 1.00 0.93 
L291 500 0.00 0.00 L292 450 900.00 900.00 3.27 3.27 
L301 500 0.00 0.00 L302 450 265.00 265.00 0.96 0.96 
L311 500 0.00 48.39 L312 450 150.00 101.61 0.55 0.57 
L321 350 175.77 328.64 L322 315 304.23 151.36 1.48 1.49 
L331 400 127.91 285.00 L332 350 157.09 0.00 0.92 0.97 
      Million Rupees (M. Rs) 84.99 78.74 
      Million USD 1.15 1.07 
Link/PipeLPJALink/PipeLPJATotal Cost
DiameterLengthLengthDiameterLengthLength(M. Rs.)
(mm)(m)(m)(mm)(m)(m)LPJA
1 2 3 4 5 6 7 8 9 10 
L11 1,150 0.00 0.00 L12 1,100 50.00 50.00 0.60 0.60 
L21 450 503.58 0.00 L22 400 696.42 1,200.00 4.20 4.09 
L31 1,100 685.00 0.00 L32 1,050 0.00 685.00 8.26 7.73 
L41 315 825.00 5.55 L42 300 0.00 819.45 2.53 2.29 
L51 1,100 390.00 0.00 L52 1,050 0.00 390.00 4.70 4.40 
L61 350 345.97 0.00 L62 315 594.03 940.00 2.89 2.88 
L71 1,050 135.00 0.00 L72 1,000 0.00 135.00 1.52 1.31 
L81 315 500.00 0.00 L82 300 0.00 500.00 1.53 1.39 
L91 1,050 155.00 0.00 L92 1,000 0.00 155.00 1.75 1.51 
L101 400 1,415.50 0.00 L102 350 834.50 2,250.00 7.42 7.00 
L111 1,050 0.00 0.00 L112 1,000 470.00 470.00 4.58 4.58 
L121 350 413.30 0.00 L122 200 41.70 455.00 1.34 0.55 
L131 1,000 334.98 0.00 L132 950 10.02 345.00 3.62 3.36 
L141 350 438.99 0.00 L142 200 21.01 460.00 1.39 0.56 
L151 950 270.00 0.00 L152 900 0.00 270.00 2.63 2.42 
L161 400 553.50 0.00 L162 350 256.50 810.00 2.68 2.52 
L171 900 0.00 0.00 L172 850 170.00 170.00 1.37 1.37 
L181 400 782.03 0.00 L182 350 207.97 990.00 3.31 3.08 
L191 850 0.00 0.00 L192 800 680.00 680.00 4.89 4.89 
L201 315 410.58 0.00 L202 250 199.42 610.00 1.64 1.18 
L211 315 167.30 0.00 L212 250 282.70 450.00 1.06 0.87 
L221 750 560.00 0.00 L222 700 0.00 560.00 3.64 3.25 
L231 315 292.77 0.00 L232 250 217.23 510.00 1.32 0.98 
L241 800 0.00 0.00 L242 750 430.00 430.00 2.49 2.49 
L251 250 84.91 0.00 L252 200 425.09 510.00 0.68 0.62 
L261 700 340.00 0.00 L262 650 0.00 340.00 1.97 1.84 
L271 350 763.99 900.00 L272 315 136.01 0.00 2.79 2.80 
L281 650 185.00 0.00 L282 600 0.00 185.00 1.00 0.93 
L291 500 0.00 0.00 L292 450 900.00 900.00 3.27 3.27 
L301 500 0.00 0.00 L302 450 265.00 265.00 0.96 0.96 
L311 500 0.00 48.39 L312 450 150.00 101.61 0.55 0.57 
L321 350 175.77 328.64 L322 315 304.23 151.36 1.48 1.49 
L331 400 127.91 285.00 L332 350 157.09 0.00 0.92 0.97 
      Million Rupees (M. Rs) 84.99 78.74 
      Million USD 1.15 1.07 

Also, it is clear from Table 5 that, using JA, there are two pipes (L272, L332), for which the second part of the length of pipe is eliminated, whereas, for three pipes (L41, L311, L321), the cost of pipe is shared by two diameters on either side of the designed diameters obtained from CPM. For the rest of the 28 pipes, the first part of the pipe is wholly eliminated; thereby, the entire length is served by the diameter on the lower side with reference to the diameter obtained in CPM, thus reducing the network's total cost.

Table 6 shows that the Nandgaon network has only five pipes out of which, for two pipes (L421, L431), the first part of the length is eliminated. For L402, the second part is eliminated, and for only one pipe, L411, the cost is shared by two pipe sizes. The column description for Table 6 is similar to that for the Bakhari network (Table 5). Table 6 shows the optimized diameters for the Nandgaon network using JA, which indicates that out of five pipes, only one pipe, L432, bears the cost of the higher diameter for the entire length. For the rest of the four pipes (L401, L411, L421, L441), the first part of the pipe is completely eliminated; therefore, the pipe diameters on the lower side are utilized to reduce the total cost of the network.

Table 6

Optimized diameters and total cost for Nandgaon using LP and JA

LinkLPJALinkLPJATotal Cost
DiameterLengthLengthDiameterLengthLength(M. Rs.)
(mm)(m)(m)(mm)(m)(m)LPJA
1 2 3 4 5 6 7 8 9 10 
L401 1,500 60 L402 1,400 60 1.26 1.10 
L411 1,500 539.03 L412 1,300 90.97 630 12.76 10.19 
L421 1,300 L422 1,200 1,110 1,110 15.50 15.50 
L431 1,000 1,200 L432 900 1,200 10.76 12.61 
L441 800 L442 700 1,020 1,020 5.92 5.92 
      Million Rupees (M. Rs) 46.20 45.31 
      Million USD 0.63 0.61 
LinkLPJALinkLPJATotal Cost
DiameterLengthLengthDiameterLengthLength(M. Rs.)
(mm)(m)(m)(mm)(m)(m)LPJA
1 2 3 4 5 6 7 8 9 10 
L401 1,500 60 L402 1,400 60 1.26 1.10 
L411 1,500 539.03 L412 1,300 90.97 630 12.76 10.19 
L421 1,300 L422 1,200 1,110 1,110 15.50 15.50 
L431 1,000 1,200 L432 900 1,200 10.76 12.61 
L441 800 L442 700 1,020 1,020 5.92 5.92 
      Million Rupees (M. Rs) 46.20 45.31 
      Million USD 0.63 0.61 

The comparison of the total cost for the Bakhari and Nandgaon networks using LP and JA is presented in Table 7. For the present study, the PSC pipes are used for the design using Hazen-Williams (HW) formula as it develops desired positive pressures (Chief Engineer 2012). It is clear from Table 7 that JA gives more cost-effective results for small and relatively larger networks. The total cost of Bakhari using LP is estimated as 84.99 Million Rupees ($1.15 Million), whereas it comes out to be 78.74 Million Rupees ($1.11 Million) using JA, which shows a significant percentage cost reduction of 7.36. On the other hand, for the Nandgaon network, a small five pipe system network, the total cost estimated using JA is lesser than that using LP, but the percentage reduction is comparatively less. The total length of the Bakhari network is 18,355 m, and the total cost estimated for the complete network is 78.74 Million Rupees using JA. Therefore, the network's per meter cost is found out to be 4,289.89 Rupees ($58.11).

Table 7

Cost comparison for LP and JA

NetworkLength of Network (m)LP
JA
Cost (M. Rs.)Cost per meter (Rs/m)Cost (US Million $)Cost per meter ($/m)Cost (M. Rs.)Cost per meter (Rs/m)Cost (US Million $)Cost per meter ($/m)
Bakhari 18,355.00 84.99 4,630.54 1.15 62.72 78.74 4,289.89 1.07 58.11 
Nandgaon 4,020.00 46.20 11,493.02 0.63 155.67 45.31 11,270.26 0.61 152.65 
NetworkLength of Network (m)LP
JA
Cost (M. Rs.)Cost per meter (Rs/m)Cost (US Million $)Cost per meter ($/m)Cost (M. Rs.)Cost per meter (Rs/m)Cost (US Million $)Cost per meter ($/m)
Bakhari 18,355.00 84.99 4,630.54 1.15 62.72 78.74 4,289.89 1.07 58.11 
Nandgaon 4,020.00 46.20 11,493.02 0.63 155.67 45.31 11,270.26 0.61 152.65 

Similarly, the total length of the Nandgaon network is 4,020 m, and its total cost is 45.31 Million Rupees. The per meter cost obtained for the Nandgaon network is 11,270.26 Rupees ($152.65). The Nandgaon network, being a small five-pipe system with a total network length of 4,020 m, has little room for optimization against the Bakhari network with 33 pipes, having a total network length of 18,355 m. Hence the per meter cost obtained is higher for Nandgaon relative to the Bakhari network. The per meter cost comparison using both the optimization techniques shows that JA outstands the results.

The overall efficiency of the canal system considered for the study is 45% (Pench Irrigation Project Report, 2001). With the consideration of leakage losses to the maximum of 30% and eliminating seepage and evaporation losses entirely, the efficiency achieved is 70%. With the saved water, the area irrigated for the Bakhari distributary will increase to 1471. Ha, which was 820 Ha with the existing canal system. For Nandgaon, it will increase to 328 Ha, which was 183 with the canal system. It indicates a 44% increase in the irrigation area, which is considerable. This study may further be extended to obtain the entire construction cost of the systems.

The optimal design of IPDN is presented using the CPM. The diameters thus obtained in CPM are optimized using LP and JA. JA being a parameterless algorithm-specific algorithm, a sensitivity analysis is carried out to select the population size. For the population size of 50 in the sensitivity analysis with FES count of 1000, the model lead to the optimum solution. The cost per meter of the Bakhari network is 4,630.54 Rupees ($62.72) using LP, and that using JA, it comes out to be 4,289.89 Rupees ($58.11). Similarly, the cost per meter for the Nandgaon, which is a smaller network, is 11,493.02 Rupees ($155.67) using LP whereas, it is 11,270.26 Rupees ($152) using JA. The Nandgaon network, being a small five-pipe system with a total network length of 4,020 m, has little room for optimization against the Bakhari network with 33 pipes, having a total network length of 18,355 m. Hence the per meter cost obtained is higher for Nandgaon relative to the Bakhari network. The results indicate that JA's cost is lesser than that obtained using LP for both networks. The percentage decrease in cost for the Bakhari network is 7.36 while for the Nandgaon network is 1.94, respectively. It can be concluded that JA has reached a better-optimized solution than LP for the IPDN. Thus, JA can be promisingly implemented for the optimization of real existing IPDN. The study can be extended to the entire command area network for further reduction in the cost. Also, it can be explored for the layout optimization as well.

The cooperation extended by the Pench Irrigation Division, Nagpur Maharashtra, India, under Vidarbha Irrigation Development Corporation, is gratefully acknowledged for providing the necessary data to carry out the present study.

All relevant data are included in the paper or its Supplementary Information.

Alperovits
E.
&
Shamir
U.
1977
Design of optimal water distribution system
.
Water Resources Research
13
,
885
900
.
Bhave
P. R.
1978
Non-computer optimization of single source networks
.
Journal of Environmental Engineering, ASCE
104
(
4
),
799
814
.
Bhave
P. R.
1983
Optimization of gravity-fed water distribution systems: application
.
Journal of Environmental Engineering, ASCE
109
(
2
),
383
395
.
Bhave
P. R.
&
Gupta
R.
2004
Optimal design of water distribution networks for fuzzy demands
.
Civil Engineering and Environmental Systems
21
(
4
),
229
245
.
Bhave
P.
&
Gupta
R.
2006
Analysis of Water Distribution Network. Narosa Publication House, New Delhi, India
.
Chief Engineer
2012–2013
Schedule of Rates, Report Water Management, Maharashtra Jeevan Pradhikaran, Government of India Undertaking
.
Cunha
M. C.
&
Sousa
J.
1999
Water distribution network design optimization: simulated annealing approach
.
Journal of Water Resources Planning and Management, ASCE
125
(
4
),
215
221
.
Das
S. R.
,
Mishra
D.
&
Rout
M.
2017
A hybridized ELM-Jaya forecasting model for currency exchange prediction
.
Journal of King Saud University –Computer and Information Sciences
.
doi:10.1016/j.jksuci.2017.09.006
.
Deng
W.
,
Xu
J.
,
Song
Y.
&
Zhao
H.
2020a
Differential evolution algorithm with wavelet basis function and optimal mutation strategy for complex optimization problem
.
Applied Soft Computing Journal
.
doi:10.1016/j.asoc.2020.106724
.
Deng
W.
,
Junjie Xu
J.
,
Xiao-Zhi Gao
X.
&
Zhao
H.
2020b
An enhanced MSIQDE algorithm with novel multiple strategies for global optimization problems
.
IEEE Transactions on Systems, Man, and Cybernetics: Systems
.
doi:10.1109/TSMC.2020.3030792
.
Ensuff
M. M.
&
Lansey
K. E.
2003
Optimization of water distribution network design using the shuffled frog leaping algorithm
.
Journal of Water Resources Planning and Management, ASCE
129
(
3
),
210
225
.
Gajghate
P. W.
&
Mirajkar
A.
2020
Irrigation pipe network planning at tertiary level: an Indian case study
.
KSCE Journal of Civil Engineering
24
(
1
),
322
335
.
Kadu
M. S.
,
Gupta
R.
&
Bhave
P. R.
2008
Optimal design of water networks using a modified genetic algorithm with reduction in search space
.
Journal of Water Resources Planning and Management, ASCE
134
(
2
),
147
160
.
Lapo
C. M.
,
García
R. P.
,
Izquierdob
J.
&
Cabrerab
D. A.
2016
Hybrid optimization proposal for the design of collective on-rotation operating irrigation networks
. In:
XVIII International Conference on Water Distribution Systems Analysis, WDSA
.
Maier
H. R.
,
Simpson
A. R.
,
Zecchin
A. C.
,
Foong
W. K.
,
Phang
K. Y.
,
Seah
H. Y.
&
Tan
C. L.
2003
Ant colony optimization for design of water distribution systems
.
Journal of Water Resources Planning and Management, ASCE
129
(
3
),
200
209
.
Mansouri
R.
,
Torabi
H.
,
Hoseini
M.
&
Morshedzadeh
H.
2015
Optimization of the water distribution networks with Differential Evolution (DE) and Mixed Integer Linear Programming (MILP)
.
Journal of Water Resource and Protection
7
,
715
729
.
Paliwal
V.
,
Ghare
A. D.
,
Mirajkar
A. B.
,
Bokde
N. D.
&
Lorenzo
A. E. F.
2020
Computer modeling for the operation optimization of mula reservoir, Upper Godavari Basin, India, Using the Jaya Algorithm
.
Sustainability
12
(
1
),
84
.
Pandey
H. M.
2016
Jaya a novel optimization algorithm: what, how and why?
In:
Cloud System and Big Data Engineering (Confluence) 6th International Conference
.
IEEE
, pp.
728
730
.
Praks
P.
&
Brkic
D.
2020
Review of new flow friction equations: Constructing Colebrook's explicit correlations accurately
.
Revista Internacional de Métodos Numéricos para Cálculo y Diseño en Ingeniería
.
doi:10.23967/j.rimni.2020.09.001
.
Rao
R. V.
2016
Jaya: a simple and new optimization algorithm for solving constrained and unconstrained optimization problems
.
International Journal of Industrial Engineering Computations
7
(
1
),
19
34
.
Rao
R. V.
,
Saroj
A.
&
Bhattacharyya
S.
2018
Design optimization of heat pipes using elitism-based self-adaptive multipopulation Jaya Algorithm
.
Journal of Thermophysics and Heat Transfer
32
(
3
),
702
712
.
Satpute
M. M.
,
Khandve
P. V.
&
Gulhane
M. L.
2012
Pipe distribution network for irrigation-an alternative to flow irrigation
. In:
Proc. of 99th Indian Science Congress, Part II
,
Bhubaneshwar, India
, pp.
106
114
.
Song
Y.
,
Wu
D.
,
Wu
D.
,
Gao
X.
,
Li
T.
,
Zhang
B.
&
Li
Y.
2020
MPPCEDE: Multi-population parallel co-evolutionary differential evolution for parameter optimization
.
Energy Conversion and Management
.
doi:10.1016/j.enconman.2020.113661
.
Sudan
V.
&
Gupta
R.
2017
Canal versus pipe water distribution network for irrigation: a case study of Khangaon Branch of Lower Wardha Project
. In:
49th Annual Convention of IWWA on Smart Water Management
,
January 18–21
,
Nagpur, India
.
Varade
S.
&
Patel
J. N.
2018
Determination of optimum cropping pattern using advanced optimization algorithms
.
Journal of Hydrology Engineering, ASCE
23
(
6
),
05018010
.
Viccione
G.
&
Tibullo
V.
2012
An effective approach for designing circular pipes with the colebrook-white formula numerical
. In:
Analysis and Applied Mathematics ICNAAM 2012 AIP Conf. Proc. 1479
, pp. 205–208.
doi:10.1063/1.4756098
.
This is an Open Access article distributed under the terms of the Creative Commons Attribution Licence (CC BY-NC-ND 4.0), which permits copying and redistribution for non-commercial purposes with no derivatives, provided the original work is properly cited (http://creativecommons.org/licenses/by-nc-nd/4.0/)

Supplementary data