On the basis of a cost-benefit analysis it was decided to expand the Arnsberg WWTP by a multistage biological process which allows for cost-effective integration of the existing facilities. Carbon removal will then be accomplished in a high-loaded activated sludge stage for which the existing primary clarifier is to be reconstructed. The existing trickling filters will be used for nitrification during a midterm period and will be replaced later on either by a moving bed system or by new trickling filters. Line 3 of the existing secondary clarifiers will be reconstructed and used for post denitrification in a moving bed system. The carbon needed for denitrification will be provided by means of sludge hydrolysis and the use of an external carbon source.