An Imhoff tank was reconstructed into a 250 m3 UASB reactor in order to treat a malting plant wastewater. The UASB was inoculated with sludge from an anaerobic lagoon used for slaughterhouse wastewater treatment. After two months of operation the reactor achieved full load with an HRT of 17 h, a COD removal higher than 80% and a biogas production of 300 m3/day (77% average methane content), with an organic loading rate of 3.6 kgCOD/m3.d (0.24 kgCOD/kgVSS.d). A yield coefficient of 0.09 gVSS/gCODrem was found from a mass balance. The fat present in the inoculated sludge (48 mg/gSSV) did not affect the start up performance. Sludge from the inoculum with high content of fat (270 mg/gSSV), was separated by flotation in the first week of operation. The COD removal efficiency was scarcely influenced by the reactor operation temperature (17–25 °C).
Skip Nav Destination
Article navigation
Research Article|
July 01 2006
Start-up and steady-state results of a full-scale UASB reactor treating malting wastewater
L. Borzacconi;
1Facultad de Ingeniería, Universidad de la República Uruguay, Herrera y Reisig 565, CP 11300, Montevideo, Uruguay
E-mail: lilianab@fing.edu.uy
Search for other works by this author on:
I. López;
I. López
1Facultad de Ingeniería, Universidad de la República Uruguay, Herrera y Reisig 565, CP 11300, Montevideo, Uruguay
Search for other works by this author on:
M. Passeggi
M. Passeggi
1Facultad de Ingeniería, Universidad de la República Uruguay, Herrera y Reisig 565, CP 11300, Montevideo, Uruguay
Search for other works by this author on:
Water Sci Technol (2006) 54 (2): 261–267.
Citation
L. Borzacconi, I. López, M. Passeggi; Start-up and steady-state results of a full-scale UASB reactor treating malting wastewater. Water Sci Technol 1 July 2006; 54 (2): 261–267. doi: https://doi.org/10.2166/wst.2006.515
Download citation file:
Sign in
Don't already have an account? Register
Client Account
You could not be signed in. Please check your email address / username and password and try again.
Impact Factor 1.915
CiteScore 3.3 • Q2
13 days submission to first
decision
1,439,880 downloads in 2021