Guidelines are often set at urban catchments' outfalls to avert river pollution, where stormwater is discharged into the river. Analytical probabilistic models (APMs) in conjunction with particle swarm optimization (PSO) were used to design a detention pond system at three sub-catchments of a watershed that discharge into a common point. The objective is to design multiple ponds upstream such that the pollution control target downstream is met at the minimum cost. Given the cost of purchasing land plus the cost of construction/maintenance of the ponds in the sub-catchments, the result shows that pond depths of 2.0 m in all three sub-catchments give the least total cost. A runoff control of 88, 94, and 90%, and pollution control of 59, 45, and 66% were obtained in Ponds 1, 2, and 3, respectively, while satisfying the overall watershed's pollution control target. A sensitivity analysis was conducted by varying the land costs and different performances were obtained. The APM/PSO model can search for the optimum design parameters that satisfy upstream runoff control performances and the overall pollution control target downstream. The advantage of the approach is that it can be applied to any combination of ponds in a larger watershed.

  • Optimization of detention pond design in multiple catchment systems.

  • APM in conjunction with PSO was used.

  • Runoff control performances were obtained.

  • The pollution control target was met at the outlet of the entire watershed.

  • The least-cost design combinations of the detention ponds were obtained.

Urban stormwater has been identified as the second most priority pollutant and a major source of impairment to rivers, lakes, and estuaries (Masoner et al. 2019; Fuchte et al. 2022; Spence et al. 2023; Guo et al. 2024). Detention ponds are stormwater management systems that treat and control urban stormwater (Oxley & Mays 2014; Banihabib et al. 2015; Cavadini et al. 2024; Pirone et al. 2024). Carpenter et al. (2014) evaluated the performance of retrofitted detention ponds and found removal efficiencies of 90, 84, and 42% for total suspended solids (TSSs), ammonia-nitrogen, and zinc respectively. Baird et al. (2020) monitored two ponds concerning their ability for stormwater volume reduction, peak flow mitigation, and improvement in water quality. Results indicated a volume reduction of 60 and 51% for the two ponds and peak flow reductions of 99%. Furthermore, more than 30% reduction in the concentrations of TSS, total phosphorus, and dissolved nitrogen species was observed. Guo (2009) retrofitted a flood control detention pond to also serve as a stormwater quality control pond. Three-level outlets including water quality release in 12–48 h were proposed. With the help of runoff capture curves, the water design water quality control volume was determined from a pre-selected runoff capture percentage. Yang et al. (2023) presented a model to optimize the pond volume taking the cost, TSS, and catchment peak outflow (CPO) as the objectives. Martijn et al. (2024) used a hybrid Markov decision process to model a stormwater detention pond and urban catchment in order to maximize retention time for pollutant sedimentation while minimizing the duration of emergency overflow in the detention pond. Abduljaleel et al. (2023) proposed a methodology to improve detention ponds runoff and water quality controls to cater for climate change impacts. Many researches have been carried out to determine the effectiveness of detention ponds for flood and water pollution control (Liew et al. 2012; Krajewski et al. 2017; Krivtsov et al. 2020; Suripin et al. 2020; Hosseinzadeh et al. 2023).

Analytical probabilistic models (APMs) are closed-form analytical expressions for system output performance derived from the probability distribution of the systems' input variables. The approach was originally proposed by Benjamin and Conell in 1970 and later refined by many researchers. In the APM, rainfall data are discretized into individual events using a pre-defined minimum storm separation time (MSST). The probability distributions of the input variables (rainfall depth, duration, intensity, and inter-event time) are transformed into the probability distribution of output performance using derived probability theory (Adams & Papa 2000). Guo (2001) assessed the suitability of APM in the design of urban flood control detention ponds alongside the design storm and continuous simulation approaches, results show that the three approaches generated similar results in the prediction of peak flow of various durations from small urban catchments. APM has been extensively used by researchers in urban stormwater management (Dan'azumi et al. 2013a, b; Aldrees & Dan'azumi 2023).

Due to the scarcity of funds and the various competing demands, there is a need to use models capable of not only design, but optimization. Such models could be used for sensitivity analysis to screen the best combinations of designs. APMs of urban stormwater management are amenable to optimization (Aldrees & Dan'azumi 2023). Optimization of detention ponds design as urban stormwater management system could be to maximize the benefits of runoff quantity and/or quality control or minimize the cost. It can also be based on the uncertainty as deterministic or stochastic or based on the control approach as either static or dynamic (Shishegar et al. 2018). Particle swarm optimization (PSO) is a technique that can be applied to optimize flood control systems, including detention facilities (Qi et al. 2021). It is a stochastic optimization algorithm based on social simulation models. The most significant advantage of the PSO algorithm is its relatively simple coding and hence low computational cost (Parsopoulos & Vrahatis 2010).

Despite numerous publications on optimizations of various systems using PSO, few publications in stormwater management use PSO. Linear programming, dynamic programming, and nonlinear programming are some commonly used optimization methods in water resources (Reddy & Kumar 2020) and few research applications could be found in stormwater management. Nasrin (2014) developed an incremental dynamic programming forward recursive algorithm to minimize the pumping requirement and maximize the utilization of the detention storage for the closed-gate period subject to the external river water level of the Hatirjheel Detention Basin in Bangladesh. Limbrunner et al. (2013) applied linear and dynamic programming to optimize the placement and sediment-trapping capabilities of infiltration-based stormwater BMPs (including detention ponds) at the watershed scale. Compared to the genetic algorithm, the result shows that dynamic programming effectively solves the sediment-management optimization problem. Rathnam et al. (2002) applied the dynamic programming to a catchment in Hyderabad, India optimize the design of detention ponds system. Result indicated that the cost of the system can be minimized using the model.

Studies that applied PSO to detention pond design are rare. Kumar & Reddy (2007) derived reservoir operation policies using an elitist mutated PSO algorithm. Similarly, Reddy & Kumar (2009) also used an elitist mutated PSO model that integrates the dynamics associated with the water released from a reservoir to the water utilized by crops at the farm level. The model was applied to Malaprabha Reservoir, India, and decisions on reservoir releases and crop water allocations for 10-day periods for each crop, over a year, could be estimated. Ngo et al. (2016) coupled EPA-SWMM with an improved version of PSO called extraordinary PSO (EPSO) for the optimal design of a detention pond system in Seoul, Korea. The result under the optimized scheme was that the peak water level in the pond and downstream area was much smaller than what used to be obtainable before the scheme.

APM and PSO have been employed in the optimization of pollution control performance of wet detention pond in a tropical urban catchment and results indicated that the PSO model out-performs the APM in terms of computational time. It was also found that the optimum detention time in tropical catchments is shorter than what obtains in temperate regions of the world (Dan'azumi et al. 2013a, b). Also, Shamsudin et al. (2014) developed a PSO model to select the best combination of detention pond's volume and outlet size that gives the minimum cost subject to meeting a certain average annual number of spills. The result showed that the PSO simulation is computationally faster, more accurate, and does not need discretization of outlet size when compared to APM. PSO stands out as one of the best evolutionary multi-objective optimization techniques by many researchers due to its speed and ease in implementation (Gad 2022). Despite the numerous literatures on PSO applications in various fields, literatures in water resources applications are very few and specifically very scarce applications to detention pond design. The advantages of APM + PSO, over other conventional methods, include computational flexibility, ease, speed and ability to conduct sensitivity analysis to screen out best alternative combinations of design. The results predicted by the APM + PSO are more precise as compared to those obtained by exhaustive enumeration using APM alone.

Detention ponds are built in urban areas and therefore occupy valuable lands. In addition to land costs, there are costs associated with the construction, operation, and maintenance of the system. The ponds are expected to treat the urban stormwater to meet environmental regulations before discharge into the receiving water. In a typical urban watershed consisting of multiple sub-catchments, the environmental regulations are normally imposed at the watershed's outfall where the stormwater from the watershed enters into the receiving water body. The objective of the estate developer is to minimize the costs associated with the ponds while satisfying the environmental regulations. Optimization involving a system of detention ponds in a regional watershed, which collectively discharges into a common point, is a multi-objective problem commonly encountered (Behera et al. 1999; Travis & Mays 2008; Lim et al. 2014; Bellu et al. 2016). Due to the nature of the problem and the infinite number of combinations of designs required to get the optimum result, a ‘search technique’ is required. This paper presents the optimization of a detention pond system in a regional watershed, consisting of multiple catchments, which discharge to a common point, using PSO. This paper aims to design individual ponds at the sub-catchments such that the pollution control target at the overall watershed's outlet is met. The major advantage derived from the PSO model is that the model can accommodate many smaller ponds in the system and the optimization can be performed with relative ease compared to other methods. For brevity, three sub-catchments, each with a stormwater detention pond, were employed in this research.

Figure 1 shows the general flowchart used to carry out the research.
Figure 1

Flowchart of the methodology.

Figure 1

Flowchart of the methodology.

Close modal

Rainfall data collection and analysis

Long-term hourly rainfall data were collected from a rain gauge location station in Larkin, Johor Bahru, on the west coast of Peninsula Malaysia (Station ID 1437116). As different criteria are being used in choosing the MSST (Dunkerley 2008); the data were discretized into individual events using a storm separation time of 6 h based on studies by Guo & Urbonas (2002) and Guo (2002). Rainfall characteristics: (i.e. average rainfall duration, average rainfall depth, average rainfall intensity, and average storm separation time) were derived from the rainfall data. APMs of urban stormwater management developed by Adams & Papa 2000 and Chen & Adams (2005, 2006a) were employed in this study. In order to use the APM; the rainfall characteristics must fit the exponential distribution. Therefore, a goodness-of-fit test was conducted with various probability distributions at a 5% level of significance. The null and the alternative hypotheses are:

  • H0: the data follow exponential distribution;

  • HA: the data do not follow exponential distribution.

The one-parameter exponential distribution with scale parameter (λ) is represented by the PDF (f(x)) given by the following equation:
(1)
where λ > 0, and x is the rainfall characteristics under consideration.

The APM parameters: (i.e. inverse of average duration of rainfall event λ (h−1), inverse of average depth of rainfall event ζ (mm−1), inverse of average inter-event time ψ (h−1), and average annual number of rainfall events (θ)) were developed from the rainfall characteristics. These parameters, along with the case study catchment characteristics, were used to determine the runoff and pollution control performances using the PSO.

Case study catchment

A hypothetical catchment comprising three sub-catchments, in the southern city of Johor Bahru- Malaysia, was selected and its land cost was estimated to be RM45 per square meter (NB: 1 USD = 4.30 RM). The cost of pond construction, operation and maintenance was estimated at RM30 per cubic meters. There is an existing downstream stormwater conveyance system in the area and therefore, no cost was attached to that. Figure 2 shows a schematic diagram of the catchment while Table 1 gives physiographic information about the catchment.
Table 1

Data for the catchment

Sub-catchment 1Sub-catchment 2Sub-catchment 3
Catchment area (ha) 126 110 286 
Runoff coefficient 0.69 0.76 0.50 
Depression storage (mm) 4.41 3.77 6.14 
Land cost (RM/m245 45 45 
Construction cost (RM/m330 30 30 
Sub-catchment 1Sub-catchment 2Sub-catchment 3
Catchment area (ha) 126 110 286 
Runoff coefficient 0.69 0.76 0.50 
Depression storage (mm) 4.41 3.77 6.14 
Land cost (RM/m245 45 45 
Construction cost (RM/m330 30 30 
Figure 2

Conceptual view of the catchment and the detention pond system.

Figure 2

Conceptual view of the catchment and the detention pond system.

Close modal

Development of PSO model

PSO was employed to design the onsite detention ponds at the sub-catchments such that the overall pollution control target (CP) is met at the minimum cost. The simulation was started by calibrating the PSO parameters (inertia, correction factor, and swarm size). Median values for the inertia, correction factor, and swarm size of 0.4, 1.2, and 45 were selected after the calibration and these values are in line with optimum values quoted in PSO literature where maximum exploration and exploitation capability of the swarm are obtained (Parsopoulos & Vrahatis 2010).

The average annual number of spills in Ponds 1, 2, and 3 were arbitrarily set to be 2, 1, and 3 spills per annum, respectively (Table 2). By this, more stringent runoff control is set in Pond 2 (1 spill per annum) compared to Ponds 1 and 3 (2 and 3 spills per annum, respectively). A situation like this arises when one sub-catchment is considered more important in terms of runoff control than the others due to the presence of strategic properties that need to be protected against flood (Rathnam et al. 2002).

Table 2

Pond depths and number of allowable spills per annum

Sub-catchment 1Sub-catchment 2Sub-catchment 3
No. of allowable spills per annum 
Minimum pond depth (m) 1.0 1.0 1.0 
Maximum pond depth (m) 2.0 2.0 2.0 
Sub-catchment 1Sub-catchment 2Sub-catchment 3
No. of allowable spills per annum 
Minimum pond depth (m) 1.0 1.0 1.0 
Maximum pond depth (m) 2.0 2.0 2.0 

The design variables are the pond's storage volume (SA), release rate (Ω), and pond depth (hA). Since the cost of a pond is directly proportional to the pond's storage volume, it is evident that any search procedure that locates the minimum volume also locates the minimum cost and vice-versa. The PSO search was conducted; the release rate was varied while keeping the pond's depth and the average annual number of spills constant. The pond's depth was then varied between a minimum value of 1.0 m and a maximum value of 2.0 m (i.e. 1.0, 1.5, and 2.0 m) (Table 2). The PSO simulation was conducted to obtain the least volume and the corresponding release rate that gives the minimum cost.

Problem formulation

The pollution control performance is the product of runoff quantity control and the TSS dynamic settling efficiency (Equation (4)). The runoff quantity control (which is the inverse of the overflow rate) and the TSS dynamic settling efficiency were both related to the detention time. As detention time increases, the runoff quantity control decreases due to the risk of overflow. Conversely, as the detention time increases, the pollution control efficiency increases. A trade-off exists between the runoff quantity control and the TSS dynamic settling efficiency. If the design parameters of storage capacity and release rate are kept constant, the overflow probability will be higher for detention ponds designed for catchments in tropical climates (with heavy and frequent rainfall) compared to detention ponds designed for catchments in arid climates (with little and scarce rainfall). Alternatively, keeping the overflow probability constant, will result in frequent release rates from ponds designed in tropical climates compared to ponds designed in arid climates. The optimum pollution control performance of the detention ponds as a function of both the two parameters was presented in Dan'azumi et al. (2013a, b) and Shamsudin et al. (2014).

As mentioned earlier, detention ponds are mostly found at an onsite level and in most cases, the pollution control requirements are set at the watersheds' outfall. In this case, it is more economical to design individual ponds at the sub-catchment level while meeting pollution control regulations at the watershed level. The constraint optimization problem is formulated in Equation (2) (Behera et al. 1999):
(2)
subject to CPtot ≥ CPmin.
where TC is the total cost of n ponds (in RM), PLi and PEi are the land cost and construction, operation, and maintenance cost (in RM/square meters and RM per cubic meter) and ACi is the catchment area (ha) of ith sub-catchment. SAi, and hAi are decision variables representing the pond's storage volume and pond's depth (m) of ith catchment respectively and CPmin is the pollution control constraint at the watersheds' outfall. The pollution control performance at the watersheds' outlet (CPtot) is the area-weighted pollution control performances provided by individual ponds (Cpi) in the various sub-catchments and is given by Equation (3):
(3)
where Cpi is the pollution control performance at the ith sub-catchment.
The problem has been formulated in Equation (2). The long-term pollution control (Cp) is the product of runoff quantity control (Cr) and the dynamic settling efficiency (Ed) given by Equation (4) (Chen & Adams 2006a): In this optimization, a pollution control performance of 60% is required. Regulatory agencies normally set a pollution control target and 100% pollution control is unattainable. Therefore, in this research, a pollution control of 60% was assumed to be set by regulatory agencies to control the level of pollution from urban stormwater discharge. This value can be altered and the optimization re-run to obtain different sets of designs:
(4)
The dynamic settling efficiency is the overall fractional TSS removal efficiency in the active pool under dynamic settling given by Equation (5) (Adams & Papa 2000):
(5)
where Fi is the fraction of total mass contained in the ith size fraction, Vsi is the average settling velocity (m/h) determined using typical stormwater particle diameters. In this work, the median particle diameter was selected as representative, n is the pond settling performance factor or turbulence factor and a value of n = 3 (i.e. good performance was assigned) (Adams & Papa 2000), hA is the pond depth and Ω is the release rate from the pond. SA is the storage volume given by Equation (8). The detention ponds' pollutants removal from urban stormwater were estimated based on TSS removal because many pollutants are found to adhere to the suspended solids and many pollutants were assumed to be positively correlated to TSS (Guo 2002; Chen & Adams 2006a, b; Gong et al. 2016). Pollutants build-up may vary across different catchments. However, typical size of the suspended solid particles washed by urban stormwater was based on data from many countries. The mean suspended solids size ranging between 60 μm and 0.13 mm, with a settling velocity of 0.4572 m/h was assumed (Athayde 1986; Adams & Papa 2000).
The runoff quantity control is the average annual fraction of runoff that is controlled by the pond given by Equation (6) (Chen & Adams 2006a):
(6)
where Sd is the depression storage of the catchment and Gp(0) is the probability of spill per rainfall event given by Equation (7) (Chen & Adams 2005):
(7)
where λ (h−1) is the parameter for the exponential PDF of rainfall duration, ζ (mm−1) is the parameter for the exponential PDF of rainfall volume, β (h/mm) is the parameter for the exponential PDF of rainfall intensity, ψ (h−1) is the parameter for the exponential PDF of inter-event time and θ (number/y) is the average annual number of rainfall events, and φ is the runoff coefficient of the catchment.
The analytical expression of the required pond storage volume (SA) is presented in Equation (8). In the equation, the design variable of storage volume (SA) is explicitly expressed in terms of outlet size (Ω) and other design variables (Adams & Papa 2000).
(8)
where ns is the average annual number of allowable spills. The remaining terms have been defined in Equation (7).

Rainfall statistics

Rainfall statistics is necessary for developing APM and PSO models because rainfall is the main input to the detention ponds. Table 3 presents the descriptive statistics of the hourly rainfall depth, duration, intensity, and inter-event time. The station has an average annual number of 169 rainfall events. The highest recorded rainfall depth was 526 mm, the highest duration was 200 h and the highest intensity was 45 mm/h. Even though the values are high, the east coast of the peninsular receives much higher rainfall due to the occurrence of the northeast monsoon. Stations on the west coast are blocked by the main range of Banjaran Titiwangsa, thus affecting the quantity of rainfall they receive (Suhaila & Jemain 2007). These values affect the sizing of the pond as areas having higher rainfall need a larger pond volume.

Table 3

Statistical analysis of hourly rainfall for Johor Bahru (Station 1437116) (1971–2010)

Rainfall depthRainfall durationRainfall intensityInter-event dry period
Period of data collection (years) 40 40 40 40 
Rainfall frequency per annum 169 169 169 169 
Highest observed 526 mm 200 h 45 mm/h 971 h 
Mean 14.30 mm 6.39 h 3.00 mm/h 45.99 h 
Standard deviation 22.14 mm 9.78 h 4.24 mm/h 60.72 h 
CV 1.55 1.53 1.41 1.32 
Skewness 5.48 6.60 13.80 5.00 
Kurtosis 70.43 69.91 13.80 41.58 
Rainfall depthRainfall durationRainfall intensityInter-event dry period
Period of data collection (years) 40 40 40 40 
Rainfall frequency per annum 169 169 169 169 
Highest observed 526 mm 200 h 45 mm/h 971 h 
Mean 14.30 mm 6.39 h 3.00 mm/h 45.99 h 
Standard deviation 22.14 mm 9.78 h 4.24 mm/h 60.72 h 
CV 1.55 1.53 1.41 1.32 
Skewness 5.48 6.60 13.80 5.00 
Kurtosis 70.43 69.91 13.80 41.58 

Goodness-of-fit tests

The exponential distribution was fitted on the histogram of rainfall characteristics and a goodness-of-fit test was conducted using Kolmogorov–Smirnov, Anderson–Darling, and chi-squared tests. The null hypothesis was accepted in all three tests, and the data followed exponential distribution. The result of goodness-of-fit tests using exponential distribution is presented and the distribution fits well (Figure 3). This confirms the validity of modeling Malaysian rainfall with exponential distribution.
Figure 3

Exponential distribution fit to rainfall characteristics with 6-h MSST.

Figure 3

Exponential distribution fit to rainfall characteristics with 6-h MSST.

Close modal

The APM used herein is based on the exponential distribution of rainfall and its application is only valid if the rainfall data follows the distribution. This is true for catchments in Canada, the USA, and Malaysia (Asia). However, Raimondi et al. (2023), Bacchi et al. (2008) and Becciu & Raimondi (2015) tested other probability distributions for many Italian catchments and found that the Weibull and Weibull distributions better fit the frequency distribution of the rainfall characteristics from the observed data. However, they noted that the benefits of their use in the APM are not justifiable since it would make the integration longer and more complex. In addition, its use only brings little improvement in the accuracy of results. This makes the APM amenable to use in various urban stormwater management systems by many researchers (Raimondi et al. 2023).

APM parameters

The result of the APM parameters is presented in Table 4. The parameters are calculated as the inverse of rainfall characteristics, thus the parameters are higher with lower values of rainfall characteristics and vice-versa.

Table 4

Result of APM parameters for Johor Bahru (Station 1437116)

t (h)λ (h−1)v (mm)ζ (mm−1)i (mm/h)β (h/mm)b (h)ψ (h−1)θ (/yr)
6.394 0.156 14.329 0.070 3.004 0.333 45.99 0.022 169 
t (h)λ (h−1)v (mm)ζ (mm−1)i (mm/h)β (h/mm)b (h)ψ (h−1)θ (/yr)
6.394 0.156 14.329 0.070 3.004 0.333 45.99 0.022 169 

PSO simulations result

As mentioned earlier, the PSO model was calibrated and the simulation converged before 100 iterations. Median values for the inertia, correction factor, and swarm size of 0.4, 1.2, and 45 were selected which is in line with Parsopoulos & Vrahatis (2010). The inertia (W) was calibrated using 45 swarms and a correction factor (C) = 1.2. The correction factor (C) was calibrated using 45 swarms and inertia (W) = 0.4. Finally, the number of swarm (N) was calibrated using inertia (W) = 0.4 and C = 1.5. The results of the calibrations are presented in Supplementary material (Tables S1, S2, and S3).

The problem has been formulated in Equation (2). This type of problem is commonly encountered in detention pond systems' design (Adams & Papa 2000; Rathnam et al. 2004). Due to the multi-objective nature of this problem, and the infinite number of combinations of ponds' design parameters required to get the optimum result, a ‘search technique’ is required and the PSO model performed very well. A PSO simulation was conducted using the calibrated PSO parameters described in the previous section.

Tables 57 show the result of the least cost. Depth combinations of 2.0 m each in the three ponds give the lowest total cost of RM4,784,558. This corresponds to a combination of pond depth in the three sub-catchments that occupy the least land area. The designed ponds' storage volume and outflow rate from the sub-catchments 1, 2, and 3 were 17.86 mm, 21.49 mm, 15.73 mm and 1.54 mm/h, 3.33 mm/h, 1.08 mm/h, respectively (Table 7). In this case study, the higher cost of land (RM45/m2) compared to construction and maintenance cost (RM30/m3) makes deep ponds cheaper compared to shallow ones. A runoff control of 88, 94, and 90%, and pollution controls of 59, 45, and 66% were obtained in ponds 1, 2, and 3 respectively. Even though, some ponds have a pollution control performance of less than 60% in some cases; the area-weighted pollution control at the overall catchments' outfall has satisfied the overall watershed's pollution control of 60%. The results of runoff and pollution control performances obtained from this work compared well with values obtained by Baird et al. (2020) and Carpenter et al. (2014). Figure 4 shows the PSO fitness graph indicating the optimum cost. It was observed that the PSO algorithm converged in less than 20 iterations, the lowest cost being RM4,784,558.
Table 5

Heat map showing the PSO simulation output with varying pond depth combinations

 
 

Depth of Pond 1 is fixed at 1.0 m, (Land cost = RM45/m2).

Table 6

Heat map showing the PSO simulation output with varying pond depth combinations

 
 

Depth of Pond 2 is fixed at 1.0 m (Land cost = RM45/m2).

Table 7

Heat map showing the PSO simulation output with varying pond depth combinations

 
 

Depth of Pond 3 is fixed at 1.0 m (Land cost = RM45/m2).

Figure 4

PSO simulation output for Cases 1, 14, and 27 at a land cost of RM45/m2.

Figure 4

PSO simulation output for Cases 1, 14, and 27 at a land cost of RM45/m2.

Close modal
Figure 5 displays the box plots of runoff and pollution control for the least-cost combinations. It is observed that the runoff control ranges from 87 to 90% with a mean value of 89% for Pond 1 and remains constant at 94% for Pond 2. The value ranges from 90 to 91% for Pond 3 with a mean value of 90.5%. Overall, there change in runoff control was very minimal. On the other hand, the pollution control changes from 49 to 62% for Pond 1 with a mean value of 56%. For Pond 2, the pollution control ranges from 40 to 57% with a mean value of 47% while the range for Pond 3 was 64–70% with a mean value of 67%. Pond 2 gives the highest runoff control while Pond 3 gives the highest pollution control. The three ponds collectively satisfy the pollution control target of 60%.
Figure 5

Box plots of runoff and pollution control performances for the least costs.

Figure 5

Box plots of runoff and pollution control performances for the least costs.

Close modal

Sensitivity analysis

The sensitivity of land cost to the least-cost pond combination was investigated by decreasing the land cost to RM15/m2 in steps of RM10/m2 while maintaining the construction and maintenance cost at RM30/m3. The PSO simulation was run and Figure 6 displays the sensitivity curves for the three least costs combinations. Case 1 was observed to be more sensitive to change in land cost under the three scenarios. The lowest cost was RM3,223,734 which is contrary to previous results. The ponds' storage and outflow from sub-catchments 1, 2, and 3 were 12.94 mm, 18.90 mm, and 12.08 mm and 2.81 mm/h, 4.22 mm/h, and 1.80 mm/h, respectively. Runoff controls of 90, 94, and 91% and pollution controls of 53, 55, and 65% were obtained in ponds 1, 2, and 3, respectively (Table 8). This shows that the least (optimum) cost depends on the land cost as well as construction and maintenance costs. If the land cost is very high relative to the construction and maintenance cost, deep ponds tend to give the least total cost and if the land cost is lower relative to the cost of construction and maintenance, shallow ponds tend to give the least total cost. Even though the optimum costs in the two cases illustrated gave the optimum costs at the two extremes, a situation may arise when the optimum cost lies somewhere in the middle of the table. This depends on the ratio of the land cost to construction/maintenance cost.
Table 8

PSO simulation output with varying pond depths using a land cost of RM15/m2

Pond 1Pond 2Pond 3Total Cost (RM)
Case 1(b) Pond outflow (mm/h) 2.81 4.22 1.80  
Pond storage (mm) 12.94 18.90 12.08  
Runoff control 0.90 0.94 0.91  
Pollution control 0.53 0.55 0.65  
Cost (RM) 733,833 935,614 1,554,287 3,223,734 
Case 14(b) Pond outflow (mm/h) 1.85 4.38 1.25  
Pond storage (mm) 16.07 18.52 14.32  
Runoff control 0.89 0.94 0.90  
Pollution control 0.59 0.42 0.67  
Cost (RM) 809,985 814,863 1,638,771 3,263,619 
Case 27(b) Pond outflow (mm/h) 1.63 3.23 1.06  
Pond storage (mm) 17.26 21.87 15.89  
Runoff control 0.88 0.94 0.90  
Pollution control 0.56 0.46 0.67  
Cost (RM) 815,567 901,984 1,704,572 3,422,123 
Pond 1Pond 2Pond 3Total Cost (RM)
Case 1(b) Pond outflow (mm/h) 2.81 4.22 1.80  
Pond storage (mm) 12.94 18.90 12.08  
Runoff control 0.90 0.94 0.91  
Pollution control 0.53 0.55 0.65  
Cost (RM) 733,833 935,614 1,554,287 3,223,734 
Case 14(b) Pond outflow (mm/h) 1.85 4.38 1.25  
Pond storage (mm) 16.07 18.52 14.32  
Runoff control 0.89 0.94 0.90  
Pollution control 0.59 0.42 0.67  
Cost (RM) 809,985 814,863 1,638,771 3,263,619 
Case 27(b) Pond outflow (mm/h) 1.63 3.23 1.06  
Pond storage (mm) 17.26 21.87 15.89  
Runoff control 0.88 0.94 0.90  
Pollution control 0.56 0.46 0.67  
Cost (RM) 815,567 901,984 1,704,572 3,422,123 
Figure 6

Sensitivity curves for Cases 1, 14, and 27.

Figure 6

Sensitivity curves for Cases 1, 14, and 27.

Close modal

A situation may arise when there are many sub-catchments and the land costs change from one sub-catchment to another. In such cases, the least-cost design for the ponds and the ponds combination can only be obtained through a search technique of this kind and PSO stands tall amongst others (Poli 2008). Moreover, the combination of APM and PSO model out-performs the APM alone in terms of computational time. It is therefore suggested that in tackling optimization problems of this kind, all pond configurations have to be exhausted and the unit costs have to be properly known in order to obtain the optimum (least) cost.

In this research, the PSO algorithm was used to obtain the least-cost design of detention ponds in small sub-catchments such that the pollution control target at the larger watershed is met. The decision variables are the storage volume, release rate, and pond depth. Results indicate that, at a land cost of RM45/m2 and construction/maintenance cost of RM30/m2, the least-cost combination was that of deep ponds in all the sub-catchments and this corresponds to a combination that occupies the least land area. However, when the land cost was decreased to RM15/m2 while maintaining the construction/maintenance cost, the least-cost combination is that of the shallower ponds in all the catchments. This indicates that the least/optimum cost depends on the two costs relative to one another. In all two cases, the runoff and pollution control performances of the onsite ponds and the area-weighted pollution control at the overall watershed were determined from the PSO simulation. It was observed that the PSO can search for the optimum combinations of the design variables that satisfied both the runoff control at individual sub-catchments and the overall downstream pollution control target at the least cost. Although the present example limits the number of sub-catchments to three for clarity, the model can be applied to any number of sub-catchments within a larger watershed and the various combinations of designs can be obtained with relative ease. The APM is based on the assumption of exponential distribution which is true for Canada, USA (North America), and Malaysia (Southeast Asia). Researchers in Italy (Europe) have also used the exponential distribution and their results were found to be very reliable when compared with results from the continuous simulation. Therefore, the APM/PSO model can be applied to other regions of the world with different climates provided the assumption of exponential distribution is used to describe the rainfall characteristics which was found to be reasonable for many climates of the world. The PSO/APM combination for multiple catchment system is novel. It is recommended that a decision support system that will incorporate meteorological, catchment, and pond characteristics altogether be developed, which eventually can be used for the design of detention ponds. Further research on the use APM/PSO model for real time control of detention pond system is also recommended.

The authors extend their appreciation to Prince Sattam bin Abdulaziz University for funding this research work through the project number (PSAU/2024/01/29617).

This study was funded under Prince Sattam bin Abdulaziz project number (PSAU/2024/01/29617).

S.D., A.A., and S.I.A. conceptualized the study. S.D. carried the analysis, A.A., S.D., and S.I.A. wrote, reviewed, and edited the article.

The study did not involve any human participant .

The study did not involve any animal testing.

All relevant data are included in the paper or its Supplementary Information.

The authors declare there is no conflict.

Abduljaleel
Y.
,
Salem
A.
,
ul Haq, F., Awad, A. & Amiri, M.
(
2023
)
Improving detention ponds for effective stormwater management and water quality enhancement under future climate change: a simulation study using the PCSWMM model
,
Scientific Reports
,
13
,
5555
.
https://doi.org/10.1038/s41598-023-32556-x
.
Adams
B. J.
&
Papa
F.
(
2000
)
Urban Stormwater Management Planning with Analytical Probabilistic Models
.
New York, NY, USA
:
John Wiley & Sons
.
Athayde
D. N.
(
1986
)
Methodology for the Analysis of Detention Basins for Control of Urban Runoff Quality
.
Washington, DC, USA
:
Office of Water Non-point Source Division USEPA
.
Bacchi
B.
,
Balistrocchi
M.
&
Grossi
G.
(
2008
)
Proposal of a semi-probabilistic approach for storage facility design
,
Urban Water Journal
,
5
,
195
208
.
https://doi.org/10.1080/15730620801980723
.
Baird
J. B.
,
Winston
R. J.
&
Hunt
W. F.
(
2020
)
Evaluating the hydrologic and water quality performance of novel infiltrating wet retention ponds
,
Blue-Green Systems
,
2
(
1
),
282
299
.
https://doi.org/10.2166/bgs.2020.010
.
Banihabib
M. E.
,
Mirmomen
S.
&
Eivazi
M.
(
2015
)
Open drainage and detention basin combined system optimization
,
Water and Soil
,
5
(
5
),
1086
1094
.
https://doi.org/10.22067/jsw.v29i5.25201
.
Becciu
G.
&
Raimondi
A.
(
2015
)
Probabilistic analysis of the retention time in stormwater detention facilities
,
Procedia Engineering
,
119
,
1299
1307
.
https://doi.org/10.1016/j.proeng.2015.08.951
.
Behera
P.
,
Papa
F.
&
Adams
B. J.
(
1999
)
Optimization of regional storm-water management systems
,
Journal of Water Resources Planning and Management, ASCE
,
125
(
2
),
107
114
.
https://doi.org/10.1061/(ASCE)0733-9496(1999)125:2(107)
.
Bellu
A.
,
Sanches
C. F.
,
Cortes
R. M. V.
&
Pacheco
F. A. L.
(
2016
)
A framework model for the dimensioning and allocation of a detention basin system: the case of a flood-prone mountainous watershed
,
Journal of Hydrology
,
533
,
567
580
.
doi:10.1016/j.jhydrol.2015.12.043
.
Carpenter
J. F.
,
Vallet
B.
,
Pelletier
G.
,
Lessard
P.
&
Vanrolleghem
P. A.
(
2014
)
Pollutant removal efficiency of a retrofitted stormwater detention pond
,
Water Quality Research Journal
,
49
(
2
),
124
134
.
https://doi.org/10.2166/wqrjc.2013.020
.
Cavadini
G. B.
,
Rodriguez
M.
&
Cook
L. M.
(
2024
)
Connecting blue-green infrastructure elements to reduce combined sewer overflows
,
Journal of Environmental Management
,
365
,
121465
.
https://doi.org/10.1016/j.jenvman.2024.121465
.
Chen
J.
&
Adams
B. J.
(
2005
)
Urban stormwater control evaluation with analytical probabilistic models
,
Journal of Water Resources Planning and Management, ASCE
,
131
,
362
374
.
https://doi.org/10.1061/(ASCE)0733-9496(2005)131:5(362)
.
Chen
J.
&
Adams
B. J.
(
2006a
)
Urban stormwater quality control analysis with detention ponds
,
Water Environment Research
,
78
,
744
753
.
https://doi.org/10.2175/106143005(72939
.
Chen
J.
&
Adams
B. J.
(
2006b
)
Analytical urban storm water quality models based on pollutant buildup and washoff processes
,
Journal of Environmental Engineering, ASCE
,
132
,
1314
1330
.
Dan'azumi
S.
,
Shamsudin
S.
&
Aris
A.
(
2013a
)
Optimization of pollution control performance of wet detention ponds in tropical urban catchments using particle swarm optimization
,
Journal of Hydroinformatics
,
15
(
2
),
529
539
.
https://doi.org/10.2166/hydro.2012.206
.
Dan'azumi
S.
,
Shamsudin
S.
&
Aris
A.
(
2013b
)
Development of analytical probabilistic model parameters for urban stormwater management
,
Sains Malaysiana
,
42
(
3
),
325
322
.
Fuchte
H. E.
,
Beck
N.
,
Bieg
E.
,
Bayer
B. J.
,
Achten
C.
,
Krauss
M.
,
Schäffer
A.
&
Smith
K. E. C.
(
2022
)
A look down the drain: identification of dissolved and particle-bound organic pollutants in urban runoff waters and sediments
,
Environmental Pollution
,
302
,
119047
.
https://doi.org/10.1016/j.envpol.2022.119047
.
Gad
A. G.
(
2022
)
Particle swarm optimization algorithm and its applications: a systematic review
,
Archives of Computational Methods in Engineering
,
29
,
2531
2561
.
https://doi.org/10.1007/s11831-021-09694-4
.
Gong
Y.
,
Liang
X.
,
Li
X.
,
Li
J.
,
Fang
X.
&
Song
R.
(
2016
)
Influence of rainfall characteristics on total suspended solids in urban runoff: a case study in Beijing, China
,
Water
,
8
,
278
.
https://doi.org/10.3390/w8070278
.
Guo
Y.
(
2001
)
Hydrologic design of urban flood control detention ponds
,
Journal of Hydrologic Engineering, ASCE
,
6
,
472
479
.
https://doi.org/10.1061/(ASCE)1084-0699(2001)6:6(472)
.
Guo
J. C. Y.
(
2002
)
Overflow risk analysis for stormwater quality control basins
,
Journal of Hydrologic Engineering, ASCE
,
7
(
6
),
428
434
.
https://doi.org/10.1061/(ASCE)1084-0699(2002)7:6(428)
.
Guo
J. C. Y.
(
2009
)
Retrofitting detention basin with water quality control pool
,
Journal of Irrigation and Drainage Engineering ASCE
,
135
,
671
675
.
https://doi.org/10.1061/(ASCE)IR.1943-4774.0000051
.
Guo
J. C. Y.
&
Urbonas
B.
(
2002
)
Runoff capture and delivery curves for storm-water quality control designs
,
Journal of Water Resources Planning and Management
,
128
,
208
215
.
https://doi.org/10.1061/(ASCE)0733-9496(2002)128:3(208)
.
Guo
K.
,
Wang
H.
,
Mu
T.
,
Chen
J.
,
Luo
H.
&
He
B.
(
2024
)
Characterization and microbial mechanism of pollutant removal from stormwater runoff in the composite filler bioretention system
,
Water Reuse
,
14
(
1
),
95
114
.
https://doi.org/10.2166/wrd.2024.145
.
Hosseinzadeh
A.
,
Behzadian
K.
,
Rossi
P.
,
Karami
M.
,
Ardeshir
A.
&
Torabi Haghighi
A.
(
2023
)
A new multi-criteria framework to identify optimal detention ponds in urban drainage systems
,
Journal of Flood Risk Management
,
16
(
2
),
e12890
.
https://doi.org/10.1111/jfr3.12890
.
Krajewski
A.
,
Wasilewicz
M.
,
Banasik
K.
&
Sikorska
A. E.
(
2017
)
Operation of Detention Pond in Urban Area – Example of Wyścigi Pond in Warsaw in Environmental Engineering V
.
Warsaw, Poland: CRC Press
.
Krivtsov
V.
,
Arthur
S.
,
Buckman
J.
,
Kraiphet
A.
,
Needham
T.
,
Gu
W.
,
Gogoi
P.
&
Thorne
C.
(
2020
)
Characterisation of suspended and sedimented particulate matter in blue-green infrastructure ponds
,
Blue-Green Systems
,
2
(
1
),
214
236
.
https://doi.org/10.2166/bgs.2020.102
.
Kumar
D. N.
&
Reddy
M. J.
(
2007
)
Multipurpose reservoir operation using particle swarm optimization
,
Journal of Water Resources Planning and Management, ASCE
,
133
,
192
201
.
https://doi.org/10.1061/(ASCE)0733-9496(2007)133:3(192)
.
Liew
Y. S.
,
Selamat
Z.
,
Ab. Ghani
A.
&
Zakaria
N. A.
(
2012
)
Performance of a dry detention pond: case study of Kota Damansara, Selangor, Malaysia
,
Urban Water Journal
,
9
(
2
),
129
136
.
https://doi.org/10.1080/1573062X.2011.644567
.
Lim
S.
,
Ho
V. H.
,
Lee
S. Y.
,
Yoo
D. G.
&
Kim
J. H.
(
2014
)
Determination of optimal location and capacity of detention facilities
,
Procedia Engineering
,
70
(
2014
),
1037
1045
.
https://doi.org/10.1016/j.proeng.2014.02.115
.
Limbrunner
J. F.
,
Vogel
R. M.
,
Chapra
S. C.
&
Kirshen
P. H.
(
2013
)
Classic optimization techniques applied to stormwater and nonpoint source pollution management at the watershed scale
,
Journal of Water Resources Planning and Management, ASCE
,
139
(
5
), 486–491.
Martijn
A. G.
,
Kim
G. L.
,
Jesper
E. N.
,
Thomas
D. N.
,
Weizhu
Q.
,
Michael
R. R.
,
Jiří
S.
&
Guohan
Z.
(
2024
)
Optimal control strategies for stormwater detention ponds
,
Nonlinear Analysis: Hybrid Systems
,
53
,
101504
.
https://doi.org/10.1016/j.nahs.2024.101504
.
Masoner
J. R.
,
Kolpin
D. W.
,
Cozzarelli
I. M.
,
Barber, L. B., Burden, D. S., Foreman, W. T., Forshay, K. J., Furlong, E. T., Groves, J. F., Hladik, M. L., Hopton, M. E., Jaeschke, J. B., Keefe, S. H., Krabbenhoft, D. P., Lowrance, R., Romanok, K. M., Rus, D. L., Selbig, W. R., Williams, B. H. & Bradley, P. M.
(
2019
)
Urban stormwater: an overlooked pathway of extensive mixed contaminants to surface and groundwaters in the United States
,
Environmental Science & Technology
,
53
(
17
), 10070–10081.
https://doi.org/10.1021/acs.est.9b02867
.
Nasrin
S.
(
2014
)
Detention-based Stormwater Drainage Management Using A Dynamic Programming Approach in A Selected Area in Dhaka
.
Master of Science dissertation, Institute of Water and Flood Management, Bangladesh University of Engineering and Technology, Dhaka, Bangladesh
.
Available at: http://lib.buet.ac.bd:8080/xmlui/handle/123456789/2949 (Accessed: 07/11/2024)
.
Ngo
T. T.
,
Yoo
D. G.
,
Lee
Y. S.
&
Kim
J. H.
(
2016
)
Optimization of upstream detention reservoir facilities for downstream flood mitigation in urban areas
,
Water
,
8
,
290
.
https://doi.org/10.3390/w8070290
.
Oxley
R. L.
&
Mays
L. W.
(
2014
)
Optimization – simulation model for detention basin system design
,
Water Resources Management
,
28
(
4
),
1157
1171
.
https://doi.org/10.1007/s11269-014-0552-z
.
Parsopoulos
K. E.
&
Vrahatis
M. N.
(
2010
)
Particle Swarm Optimization and Intelligence: Advances and Applications
.
New York, NY, USA
:
Information Science Reference
.
Pirone
D.
,
Cimorelli
L.
&
Pianese
D.
(
2024
)
The effect of flood-mitigation reservoir configuration on peak-discharge reduction during preliminary design
,
Journal of Hydrology: Regional Studies
,
52
,
101676
.
https://doi.org/10.1016/j.ejrh.2024.101676
.
Poli
R.
(
2008
)
Analysis of the publications on the applications of particle swarm optimisation
,
Journal of Artificial Evolution and Applications
, 2008,
2
10
.
https://doi.org/10.1155/2008/685175
.
Qi
W.
,
Ma
C.
,
Xu
H.
,
Chen
Z.
,
Zhao
K.
&
Han
H.
(
2021
)
A review on applications of urban flood models in flood mitigation strategies
,
Natural Hazards
,
108
(
1
),
31
62
.
doi:10.1007/s11069-021-04715-8
.
Raimondi
A.
,
Sanfilippo
U.
,
Marchioni
M.
,
Di Chiano
M.
&
Becciu
G.
(
2023
)
Influence of climatic parameters on the probabilistic design of green roofs
,
Science of the Total Environment
,
865
,
161291
.
https://doi.org/10.1016/j.scitotenv.2022.161291
.
Rathnam
E. V.
,
Abdulla
S. M.
&
Jayakumar
K. V.
(
2002
). '
Urban Runoff Estimation and Optimization of Stormwater Detention Systems: a Case Study for Hyderabad City, India
',
9th International Conference on Urban Drainage
.
Oregon, USA
:
ASCE
.
Rathnam
E. V.
,
Cheeralaiah
N.
&
Jayakumar
K. V.
(
2004
)
Dynamic programming model for optimization of stormwater retention ponds in multiple catchment system
,
Hydrology: Science Practice for the 21st Century
,
2
,
326
330
.
Reddy
M. J.
&
Kumar
D. N.
(
2009
)
Performance evaluation of elitist-mutated multi-objective particle swarm optimization for integrated water resources management
,
Journal of Hydroinformatics
,
11
(
1
),
79
88
.
https://doi.org/10.2166/hydro.2009.042
.
Reddy
M. J.
&
Kumar
D. N.
(
2020
)
Evolutionary algorithms, swarm intelligence methods, and their applications in water resources engineering: a state-of-the-art review
,
H2Open Journal
,
3
(
1
),
135
188
.
https://doi.org/10.2166/h2oj.2020.128
.
Shamsudin
S.
,
Dan'azumi
S.
,
Aris
A.
&
Yusop
Z.
(
2014
)
Optimum combination of pond volume and outlet capacity of a stormwater detention pond using particle swarm optimization
,
Urban Water Journal
,
11
(
2
),
127
136
.
https://doi.org/10.1080/1573062X.2013.768680
.
Shishegar
S.
,
Duchesne
S.
&
Pelletier
G.
(
2018
)
Optimization methods applied to stormwater management problems: a review
,
Urban Water Journal
,
15
(
3
),
276
286
.
https://doi.org/10.1080/1573062X.2018.1439976
.
Spence
K.
,
Gilbert
I.
&
Robson
M.
(
2023
)
Stormwater suspended solids and pollutant concentrations in an urban stream
,
Water Air Soil Pollut
,
234
,
599
.
https://doi.org/10.1007/s11270-023-06513-3
.
Suhaila
J.
&
Jemain
A. A.
(
2007
)
Fitting daily rainfall amount in peninsular Malaysia using several types of exponential distributions
,
Journal of Applied Scinces Research
,
3
,
1027
1036
.
Suripin
S.
,
Darsono
S.
,
Kurniani
D.
,
Hutagalung
W. F.
&
Dintia
D. V.
(
2020
)
Development of sustainable detention ponds for flood and sediment control in urban areas
,
Journal of Physics: Conference Series
,
1625
, 1–7.
doi:10.1088/1742-6596/1625/1/012046
.
Travis
Q. B.
&
Mays
L. W.
(
2008
)
Optimizing retention basin networks
,
Journal of Water Resources Planning and Management, ASCE
,
134
(
5
),
432
439
.
https://doi.org/10.1061/(ASCE)0733-9496(2008)134:5(432)
.
Yang
Y.
,
Xin
Y.
&
Li
J.
(
2023
)
Surrogate-based multiobjective optimization of detention pond volume in sponge city
,
Water
,
15
(
15
),
2705
.
https://doi.org/10.3390/w15152705
.
This is an Open Access article distributed under the terms of the Creative Commons Attribution Licence (CC BY 4.0), which permits copying, adaptation and redistribution, provided the original work is properly cited (http://creativecommons.org/licenses/by/4.0/).

Supplementary data